Heathrow Terminal 5

Coordinates:51°28′22″N0°29′15″W / 51.47278°N 0.48756°W /51.47278; -0.48756
From Wikipedia, the free encyclopedia
Airport terminal at London Heathrow Airport

Heathrow Terminal 5
Terminal 5A exterior
Heathrow Terminal 5 is located in Greater London
Heathrow Terminal 5
Location within Greater London
Alternative namesTerminal 5, British Airways Terminal 5, T5
General information
StatusCompleted
TypeAirport terminal
LocationJunction 14 of theM25 off the A3044
AddressHarmondsworth, Hounslow, TW6 2GA
Coordinates51°28′22″N0°29′15″W / 51.47278°N 0.48756°W /51.47278; -0.48756
Elevation22 m (72 ft)
Construction startedSeptember 2002
Completed2008
Opened27 March 2008
Inaugurated14 March 2008
Cost£4.2 billion
ClientHeathrow Airport Holdings
LandlordHeathrow Airport Holdings
Technical details
Structural systemSteel frame roof with glass facades
Floor area353,020 m2 (3,799,900 sq ft) (main terminal building), 18,500 m2 (199,000 sq ft) (retail area)
Design and construction
Architect(s)Richard Rogers
Architecture firmRichard Rogers Partnership
Services engineerHathaway Roofing Ltd (roof)
Civil engineerArup (above ground),Mott MacDonald (substructures)
Main contractorMace,AMEC,Laing O'Rourke,MorganVinci JV (tunnelling)
Other information
Public transit accessElizabeth LinePiccadilly LineHeathrow ExpressHeathrow Terminal 5 station
Website
Heathrow Airport

Heathrow Terminal 5 is anairport terminal atHeathrow Airport, the main airport servingLondon. Opened in 2008, the main building in the complex is the largest free-standing structure in the United Kingdom. Until 2012, the terminal was used solely by British Airways. It now is used as one of the three global hubs ofIAG, served byBritish Airways andIberia.

The terminal was designed to handle 72.29 million passengers a year. In 2018, Terminal 5 handled 32.1 million passengers on 211,000 flights. It was the busiest terminal at the airport, measured both by passenger numbers and flight movements.[1]

The building's leading architects were from theRichard Rogers Partnership and production design was completed by aviation architectsPascall+Watson. The engineers for the structure wereArup andMott MacDonald. The building cost £4 billion and took almost 20 years from conception to completion, including the longestpublic inquiry in British history.

History

[edit]

Plans

[edit]

The possibility of a fifth terminal at Heathrow emerged as early as 1982, when there was debate over whether the expansion ofStansted or the expansion of Heathrow (advocated by BA) was the way forward for the UK aviation industry.[2] Planning studies for the terminal began in February 1988 andRichard Rogers Partnership was selected to design the terminal in 1989.Richard Rogers compared his design to theCentre Pompidou, an earlier project that has similar flexibility in its use of space.[3]

BAA formally announced its proposal for construction of Terminal 5 in May 1992, submitting a formal planning application on 17 February 1993.[4][5] Apublic inquiry into the proposals began on 16 May 1995 and lasted nearly four years, finally ending on 17 March 1999 after sitting for 525 days. The inquiry, based at the Renaissance Hotel Heathrow, was the longest planning inquiry ever held in the UK.[6] Finally, more than eight years after the initial planning application,Secretary of State for TransportStephen Byers announced on 20 November 2001 the British government's decision to grant planning permission for the building of a fifth passenger terminal at Heathrow.[7]

Construction

[edit]
Terminal 5 under construction in July 2006. The frontal car park building can be seen to the left, air side is to the right

Construction, which was undertaken byLaing O'Rourke,[8] began in September 2002, with earthworks for the construction of the buildings' foundation.

A preparatoryarchaeological dig at the site found more than 80,000 artefacts.[9] Among the artefacts discovered by the archaeological dig include 18,000 pieces of pottery, 40,000 pieces of workedflint, and a wooden bowl dating to the Middle Bronze Age, around 3,000 years ago. Earthworks were also discovered, including a pathway and evidence of agricultural boundaries. Objects recovered from the dig site were immediately analysed and catalogued, allowing for the preparation works for Terminal 5 to occur simultaneously alongside the research being conducted.[10]

In November 2003, work started on the steel superstructure of the main terminal building. By January 2005, the nine tunnels needed to provide road and rail access, and to provide drainage, were completed. In March that year, the sixth and final section of the main terminal roof was lifted into position, and in December the building was made weatherproof. The roof could not have been lifted with conventional cranes because it would have vertically intersected with the airport'sradar field. Therefore, the roof was assembled on the ground using smaller cranes, then lifted into place by eight custom-built towers, each fitted with two hydraulic jacks to pull the roof up. At peak there were around 8,000 people working on the construction site, whilst over the life of the project over 60,000 people were involved in the construction.[11][12] Over 15,000 volunteers were recruited for a total of 68 trials lasting from September 2007 until March 2008 to test the operational readiness of Terminal 5 prior to its opening.[11]

Opening

[edit]

QueenElizabeth II officially opened Terminal 5 in a ceremony on 14 March 2008. Used byBritish Airways (and now IAG (Iberia)) as well as American Airlines (OneWorld Partner), the terminal opened for passenger use on 27 March 2008, with flight BA26 from Hong Kong its first arrival at 04:50 GMT.[11][13] The first passenger to enter Terminal 5 was Paul Walker, a UK emigrant from Kenya who entered through security at 04:30 on 27 March 2008 and was presented with a boarding pass by the British Airways CEOWillie Walsh for the first departing flight, BA302 to Paris.

Controversy

[edit]

On the day of opening, it quickly became apparent that the new terminal was not operating as planned, forcing British Airways to cancel 34 flights and suspend baggagecheck-in.[14][15] Over the following 10 days some 42,000 bags failed to travel with their owners,[16] and over 500 flights were cancelled. British Airways was not able to operate its full schedule from Terminal 5 until 8 April 2008 and had to postpone the transfer of its long-haul flights from Terminal 4 to Terminal 5.[17] The difficulties were later blamed on a number of problems with the terminal's IT systems, coupled with car parking.[18] These resulted in the sacking of BA's director of operationsGareth Kirkwood, and director of customer services David Noyes.[19] Four months after opening, British Airways launched an advertising campaign to assure the public that things were working normally.[20]

Site

[edit]

Overview

[edit]

The Terminal 5 building is on a 260-hectare (640-acre) site on the western side of the airport, between the western ends of the northern and southern runways. The site was previously occupied by thePerry Oaks sewage works and an area ofsmallholdings called Burrows Hill Close Estate, and is east of theM25 motorway; see alsoHeathrow (hamlet). Two artificial watercourses, theLongford River and theDuke of Northumberland's River, originally ran through the middle of the site.[12] Most of the terminal is in the ecclesiastical parish of Harmondsworth. The southern section, including therailway station, is in the ecclesiastical parish ofStanwell. The whole area is in theLondon Borough of Hillingdon.

Twin Rivers Diversion Scheme

[edit]

One of the most time-critical civil engineering sub-projects of the Terminal's construction programme was the diversion of the Longford River and Duke of Northumberland's River around the western perimeter of the airport. This was a complex scheme, which involved not only the re-routing of the two rivers but also the realignment of the A3044 dual carriageway and Western Perimeter Road. The challenge was complicated by strict time constraints and the proximity of the works to local residents. Further restrictions to site activities resulted from the overhead flight path from both runways. 95% of the diverted rivers were placed in two open man-made channels 6 kilometres (3.7 mi) in length, compared with only 50% of the original rivers which were conveyed beneath the runways in culverts. The Twin Rivers Diversion scheme achieved a Civil Engineering Environmental Quality (CEEQUAL) Award for its ability to maintain high environmental standards and quality during design and construction of the project.[21] It involved much moving and planting of river wildlife and plants.[22]

Buildings

[edit]
The main building from the air
Interior of Heathrow Terminal 5
Check-in Area in the main building
Satellite Terminal 5C

The Terminal 5 complex includes several buildings, a new control tower and a railway station. The main terminal building is referred to as Terminal 5A. There are two satellite buildings, Terminal 5B and Terminal 5C. At the time of opening, Terminal 5A and Terminal 5B were completed, whilst Terminal 5C, which was built byCarillion,[23] was under construction and scheduled to open later in May 2010; however it only opened in June 2011.[24] The whole complex is fronted by a separate building containing road transport facilities. Within the complex there are more than 100 shops and restaurants.[25]

Terminal 5

[edit]

The main terminal building is 396 metres (1,299 ft) long, 176 metres (577 ft) wide and 40 metres (130 ft) tall.[26] It is the largest building in the Terminal 5 complex and is the largest free-standing building in the United Kingdom.[27] Its four storeys are covered by a single-span undulating steel frame roof, with glass façades angled at 6.5 degrees to the vertical. The area covered by the roof is the size of five football pitches, and each section weighs 2,200 tonnes.

T5A contains acheck-in hall, a departure lounge with retail stores and other passenger services, and a baggage reclaim hall. T5A contains the bulk of the terminal'sbaggage handling system. This baggage handling system is the largest in the world with 5 miles (8.0 km) of high-speed track and 11 miles (18 km) of regular conveyor belts. It is designed to handle 4,000 bags per hour, and also has an "early bag store" which can temporarily store up to 4,000 bags.

Departing passengers enter the departures level on the third floor by lift or escalator from the interchange plaza. Upon entering the departures concourse, passengers see views across Heathrow and the surrounding area, and are in a space that is unobstructed to the rising roof above. After check-in and security screening, the airside departure lounge also provides views across the airport, its runways and beyond.

There are 53 gates numbered A1–A23, B32–B48 and C52–C66. All are equipped withjetbridges except for gates A4 and A10 which are coaching gates. A number of jet bridge equipped gates can also be used for coaching departures if required.

British Airways maintains offices overlooking the main Terminal 5 passenger handling areas, designed so that staff can have, in the words ofAviation Transport Weekly, a "visual connection to customers". When Terminal 5 opened on 27 March 2008, British Airways staff, including crew check-in staff, relocated from theCompass Centre to Terminal 5.[28] London based interior designer Katharine Pooley was commissioned to design the interior of the Windsor Suite which receives and hosts VIPs.[29]

In April 2023, Heathrow proposed renaming Terminal 5 as "The King's Terminal" after KingCharles III to celebrate hiscoronation, similar to Terminal 2 being named "The Queen's Terminal" after his mother Queen Elizabeth II. However, King Charles declined the offer due to environmental concerns.[30]

Satellite terminal buildings

[edit]

Terminal 5B was the first satellite building to be built. Terminal 5C is the second satellite building, opening unofficially on 20 May 2011, with official opening on 1 June 2011, in conjunction with the relaunch of British Airways service to San Diego. Terminal 5B measures 442 metres (1,450 ft) long by 52 metres (171 ft) wide and 19.5 metres (64 ft) high, and contains 37lifts and 29escalators.[12]

There is also the potential for an additional satellite building, T5D, to be located to the east of T5C, as displayed in Heathrow's Capital Investment Plan for 2009. As of 2022 there were no plans to add T5D.[31]

An underground automated people mover (APM), known as theTransit, connects passengers between Terminal 5A, Terminal 5B and Terminal 5C. The escalators which service the APM system from the main T5A concourse are the longest in the United Kingdom[32] – previously this record had been held byAngel station on theLondon Underground, which had held the title since1992.

In a level below the APM are pedestrian walkways, which were opened for passenger use in 2015.

Frontal building

[edit]

Unlike most airport terminals, the main terminal building does not have direct road access. Instead it is fronted by a six-level frontal building, which contains a bus station and taxi rank (at ground level), a 3,800-space short-staymulti-storey car park (levels 1 to 4) and a drop-off zone (level 5). A walkway at level 1 of the frontal building provides under-cover access to theSofitel Heathrow Airport T5 Hotel, while a section of level 2 is used for the link to the long-term business car park (see below).[12]

The frontal building is connected to the main terminal by covered walkways at ground level (the arrivals level of the main terminal building) and skybridges at level 5 (departures level). The combination of the two buildings with the linking walkways creates a series of open courtyards. One of these courtyards is occupied by the access structures for the railway station below; others contain a dancing fountain and a grove of 40London planes, and are accessible to passengers and other visitors.[12]

Taller control tower

[edit]

At the time of its design Terminal 5's proposed height was so tall that it would have blocked runway views from Heathrow Airport's then control tower. Therefore, before construction began on the terminal building, a new taller air trafficcontrol tower was constructed. Costing £50 million,[33] it was assembled off-site before being manoeuvred into position within the central terminal area near toHeathrow Terminal 3 during 2004.[34][35] This control tower weighs nearly 1000 tons and is 87 metres (285 ft) in height, making it one of the tallest in Europe and twice the height of London'sNelson's Column.[36] It became operational in April 2007.

Airlines

[edit]

As of 1 June 2023[update],British Airways andIberia use Terminal 5, withBritish Airways operating the majority of its flights from Heathrow there, with some short-haul destinations served fromTerminal 3 due to T5 capacity restrictions. In summer 2023 British Airways was to move 12 of its long-haul flights to Terminal 3, and 6 of its short haul flights from Terminal 3 to Terminal 5.

Since March 2012,International Airlines Group subsidiaryIberia has operated from Terminal 5,[37] apart from a temporary relocation to Terminal 3 from 12 July 2022[38] until 31 May 2023.[39]

During the COVID-19 pandemic, severalOneworld members other than British Airways and Iberia also used this terminal.American Airlines moved into Terminal 5 on 7 July 2020,[40] but has since moved back to Terminal 3 on 12 July 2022. On 27 July 2020,Qatar Airways moved into Terminal 5,[41] but moved back to Terminal 4 on 14 June 2022. On 29 July 2020,Japan Airlines moved into Terminal 5.[citation needed] It has since moved back to Terminal 3.[citation needed]China Southern Airlines previously operated from this terminal until it was relocated toTerminal 4 in November 2022.[citation needed]

Terminal 5 handles not only international flights, but also UK and Irish flights like Terminal 2 unlike Terminal 3 and 4.Loganair was planning to use this terminal to codeshare with British Airways,[42] but usesTerminal 2 rather than Terminal 5 due to the amount of space used at Terminal 5.

Ground transport

[edit]

The transport network around the airport has been extended to cope with the increase in passenger numbers. This has involved widening of theM25 motorway, the construction of new branches of both theHeathrow Express and theLondon UndergroundPiccadilly line, and connection to theElizabeth line, opened in 2022.

Railway links

[edit]
Heathrow Express at therailway station
A1973 StockLondon Underground Piccadilly line train on Platform 6 at Terminal 5

TheLondon Underground,Elizabeth line, andHeathrow Express all provide rail connections to Terminal 5, all usingHeathrow Terminal 5 station, beneath the main terminal building. The railway station also has two additional platforms for use by a proposed westward railway connection (proposal suspended pending finance).

Heathrow Express provides an express service toPaddington station in central London, stopping only at Heathrow stations (T5, andT2/T3). Trains run every 15 minutes and the journey time to Paddington is 21 minutes. Premium fares are charged for the service to Paddington. However no fares are charged for the journey to Heathrow Central, which provides access to Terminals 2 & 3, to theHeathrow Airport Central bus station, and to the Elizabeth line semi-fast rail service to Paddington. Terminal 4 can be reached by changing trains to the free-of-charge Heathrow Express Shuttle service at Heathrow Central.

Heathrow Terminal 5 is served by the newer Elizabeth line (since 2022),[43] connecting to central London with a few stops faster than the Piccadilly line, and to destinations beyond London to the west and to the east. Fares are lower than the Heathrow Express, although a supplement to the standard Underground fare is charged.

ThePiccadilly line of the London Underground provides a slower service every ten minutes through central London toCockfosters, stopping at many stations and with connections to the whole London Underground network. Journey time to central London is about an hour, depending on destination. The Piccadilly line is integrated into theTransport for London fare system, with lower fares than other rail options.

Terminal 5 is also served byRailAir express buses, which link the terminal's bus station (see below) withReading station for rail services to the west, andWoking station for services to the south.

Road links

[edit]

A dedicatedmotorway spur has been built from theM25 between junctions 14 and 15 to the terminal. The spur also connects to the airport's perimeter road, and provides direct connections to the frontal building at ground level (for bus station and taxi rank), level 4 (for car parking) and level 5 (for departure set down). The car parking on levels 1 to 3 is accessed from a series of spiral ramps that descend from level 4 to ground level.

Besides the short-stay car parking in front of the main terminal, Terminal 5 is also served by separate business and long-term car parks. These are accessed from the airport's perimeter road and are some distance from the terminal. The long-term car park is linked to the terminal by bus, and the business car park is served by an elevated personal rapid transit system (see below).

The terminal is also connected to Terminals 1, 2 and 3 by theHeathrow Airside Road Tunnel, which is not available for public traffic.

Bus links

[edit]

The bus and coach station in the frontal building is served by a number of bus and coach services, including long-distanceNational Express coach service, "The Airline" service running from Oxford, RailAir buses, local public bus services, shuttle buses to airport hotels, long term car parking and car hire lots, and staff shuttle buses.

Because Terminal 5 is close to the boundary ofGreater London, some local buses are part of theLondon Buses network, whilst others are run by operators from outside the London Buses area.

Personal rapid transit

[edit]
AHeathrow Pod vehicle at the T5 business car park
Further information:London Heathrow Terminal 5 PRT

A 2.4-mile (3.9 km)-longpersonal rapid transit system, known as thePod, links the nearby business car park and the main Terminal 5A building. The Pod system is operatedlandside with a fleet of battery-powered, driverlessULTra vehicles running on an elevated and at-grade segregated guideway. Pod vehicles are operated by passengers using a touch-screen device at Pod stations in the car parks or inside the terminal building.[44]

The service commenced in September 2011.[45][46] This system was designed byBristol based Advanced Transport Systems, and the intention is that it will eventually transport passengers around the perimeter fence to Terminals 2 and 3.[citation needed]

Automated people mover

[edit]
Main article:Heathrow Terminal 5 Transit
Terminal 5airside Transit system

An undergroundautomated people mover (APM) system, known as theTransit, is used to transport passengers between the 5A, 5B and 5C buildings. The Transit usesBombardier Innovia APM 200 vehicles and operates exclusivelyairside, and is thus only available to passengers and other authorised personnel.[47][48]

The Transit can accommodate up to 6,000 passengers per hour[47] and the trains run at 50 kilometres per hour (31 mph) with a journey time of 45 seconds. Passengers descend to the station via a pair of escalators "thought to be the largest in Europe in an open environment".[49] The escalators are also the longest in the United Kingdom, longer than those atAngel Underground station on theLondon Underground, which had held the title since 1992.

Future developments

[edit]
The proposed Western Rail Approach to Heathrow
See also:Heathrow Airport transport proposals

A proposal for the construction of aWestern Rail Approach to Heathrow, a railway link connecting Heathrow Terminal 5 to theGreat Western Main Line, was suspended in 2020 pending a satisfactory business case and funding agreement. This link would allow rail services to continue westwards from Terminal 5 to serve stations in theWest of England.[50]

See also

[edit]

References

[edit]
  1. ^"Heathrow facts and figures". Heathrow Airport. Retrieved7 July 2019.
  2. ^Donne, Michael (12 January 1982). "The battle of Heathrow".Financial Times. London. p. 16.
  3. ^"Heathrow Terminal 5".rsh-p.com. Archived fromthe original on 16 September 2021. Retrieved2 October 2015.
  4. ^Fagan, Mary (13 May 1992). "BAA presses on with Heathrow fifth terminal".The Independent. London. p. 5.
  5. ^Bray, Roger (17 February 1993). "Plans are ready for huge fifth Heathrow terminal".Evening Standard. London. p. 5.
  6. ^"Heathrow Terminal 5 Inquiry".Department for Transport. January 2005. Archived fromthe original on 24 December 2007. Retrieved2 November 2007.
  7. ^Harper, Keith (20 November 2001)."Long-awaited go-ahead for Heathrow terminal 5".The Guardian.ISSN 0261-3077. Retrieved2 October 2024.
  8. ^"Terminal 5 must have union official on site, says UCATT". Building. 2002. Retrieved12 April 2012.
  9. ^"Archaeology at Heathrow Terminal 5". Framearch.co.uk. Retrieved12 July 2013.
  10. ^"Ancient Worlds News - London airport yields Stone Age finds - 08/08/2003".www.abc.net.au. Retrieved14 March 2025.
  11. ^abc"The making of Terminal 5". BAA. 2009. Archived fromthe original on 7 February 2009.
  12. ^abcde"Press Room / Highlights / T5 Heathrow / T5 making off". Grupo Ferrovial. Retrieved5 November 2008.[permanent dead link]
  13. ^"Queen opens new Heathrow Terminal". BBC News. 14 March 2009. Retrieved14 March 2009.
  14. ^"Air travel: Terminal 5 still losing 900 bags every day".The Guardian. 10 July 2008.
  15. ^"Baggage halted at new £4.3bn T5". BBC News. 27 March 2008. Retrieved27 March 2008.
  16. ^"28,000 bags caught in T5 foul-up". BBC News. 31 March 2008. Retrieved12 July 2013.
  17. ^"BA postpones long-haul move to T5". BBC News. 11 April 2008. Retrieved17 May 2008.
  18. ^"British Airways reveals what went wrong with Terminal 5".Computer Weekly. 14 May 2008. Retrieved17 May 2008.
  19. ^Hickman, Martin (16 April 2008)."Two BA chiefs lose jobs over Terminal 5 mess".The Independent. Retrieved4 November 2022.
  20. ^Mark Sweney (4 August 2008)."'Live' adverts to plug Terminal 5".The Guardian. Retrieved12 July 2013.
  21. ^IEMA Website – Sustainable Construction at Terminal 5Archived 13 February 2012 at theWayback Machine. Retrieved 3 December 2008
  22. ^"River diversion achieves excellent award one year on". Heathrowairport.com. Retrieved12 July 2013.
  23. ^"Carillion land Heathrow Terminal 5 contract". Builder & Engineer. 11 September 2007. Archived fromthe original on 2 October 2013. Retrieved23 August 2013.
  24. ^"Terminal 5 C opens". 7 June 2011. Retrieved7 June 2011.
  25. ^"Heathrow Terminal 5: retail destination or gateway to Britain?".Brand Republic. 14 March 2008. Retrieved28 March 2008.
  26. ^Hales-Dutton, Bruce (September–October 2007). "Heathrow Looks Ahead".Airports of the World. Key Publishing Ltd. pp. 28–33.
  27. ^"Exclusive pictures: The first images of Heathrow Terminal Five". 13 April 2012.
  28. ^Paylor, Anne. "T5 Prepares to Go Live."Air Transport World. 1 March 2008. Retrieved 2 October 2010.
  29. ^"02-Heathrow-T5—Royal-Suite".Katharine Pooley Studio. Retrieved11 May 2018.[permanent dead link]
  30. ^"King 'turned down Heathrow Airport plans to rename Terminal 5 after him'". Sky News. 26 April 2023. Retrieved16 November 2023.
  31. ^"American Airlines to move more flights to Heathrow Terminal 5".Head for Points. 12 March 2022.
  32. ^Bateman, Charlotte."The London Underground's longest escalator that is a nightmare when you are running late".My London. Retrieved11 December 2023.
  33. ^Muir, Hugh (1 December 2003)."Takeoff for Heathrow plan for £50m control tower".The Guardian. Retrieved28 January 2023.
  34. ^"London Heathrow Airport (LHA/EGLL)".Airport Technology. 14 February 2001. Retrieved28 January 2023.
  35. ^"Heathrow plan worlds largest traffic tower".Richmond & Twickenham Times. 27 November 2003. Retrieved28 January 2023.
  36. ^Milstein, Michael (January 2007)."475,000 Takeoffs and Landings a Year".Smithsonian Magazine. Smithsonian Institution. Retrieved28 January 2023.
  37. ^"Iberia to move to Heathrow T5".Business Traveller. 8 February 2012. Retrieved10 February 2012.
  38. ^"The Great Heathrow Shuffle – Iberia flights to move to Terminal 3". Retrieved18 February 2023.
  39. ^"Iberia Returns to London-Heathrow Terminal 5". Retrieved24 May 2024.
  40. ^Otley, Tom (3 July 2020)."American Airlines moves into Terminal 5 at London Heathrow".Business Traveller. Retrieved4 July 2020.
  41. ^Caswell, Tom (24 July 2020)."Qatar Airways moves into Heathrow T5work=Business Traveller". Retrieved21 October 2022.
  42. ^McWhiter, Tom (2 April 2020)."Loganair flies to Heathrow for the first time".Business Traveller. Retrieved3 April 2020.
  43. ^Flynn, David (10 November 2022)."Review: London's Elizabeth Line vs Heathrow Express". Executive Traveller.
  44. ^"Heathrow Pod Self Guided Tour Instructions"(PDF).ultraglobalprt.com. Ultra Global PRT.Archived(PDF) from the original on 26 March 2014. Retrieved30 October 2019.
  45. ^"Heathrow Pod Passenger Trials Begin". ULTra PRT. Archived fromthe original on 13 July 2011. Retrieved13 June 2011.
  46. ^"Press Release: Heathrow pods transport passengers to the future". ULTra PRT. Archived fromthe original on 18 September 2012. Retrieved28 February 2012.
  47. ^ab"INNOVIA APM 200 – London Heathrow Airport, UK".Bombardier. Retrieved4 June 2018.
  48. ^"Travel advice for anxious passengers"(PDF).LHR Airports Limited. Archived fromthe original(PDF) on 29 June 2017. Retrieved4 June 2018.
  49. ^"Lifts, escalators and autowalks BAA Terminal 5".KONE Great Britain. Archived fromthe original on 18 January 2016. Retrieved18 September 2018.
  50. ^"Heathrow rail link". Network Rail. December 2020.

External links

[edit]

Media related toHeathrow Terminal 5 at Wikimedia Commons
Geographic data related toHeathrow Terminal 5 atOpenStreetMap

Portals:
YearWinning organisationWinning structure
  • 2003
  • 2004
  • 2005
  • 2006
  • 2007
  • 2008
  • 2009
  • 2010
  • 2011
  • 2012
  • 2013
  • 2014
  • 2015
  • 2016
  • 2017
  • 2018
  • 2019
Terminals
Current
Former
Air hub for
Rail transport
Railway stations
Rail services
Automated people movers
Proposed
Bus connections
Tunnels
History
Accidents and incidents
Miscellaneous
Retrieved from "https://en.wikipedia.org/w/index.php?title=Heathrow_Terminal_5&oldid=1283641793"
Categories:
Hidden categories:

[8]ページ先頭

©2009-2025 Movatter.jp