BACKGROUNDIn present aerospace power generation systems generator voltage regulation is accomplished using precise measurement of the generator output voltage and modulation of the generator excitation currents. This is typically done by a Generator Control Unit which incorporates a Voltage Regulator. When large electrical loads are applied to the generator output terminals the voltage will rapidly decrease until the Generator Control Unit/Voltage Regulator applies additional excitation current, recovering the generator output voltage to the desired level. In this implementation the Generator Control Unit/Voltage Regulator is reacting to the drooping generator output voltage, after the electric load is applied. Conversely, when a large electrical load is removed the generator the output voltage will increase and the Generator Control Unit/Voltage Regulator decreases generator excitation to decrease the generator output voltage back to desired levels. In this example the voltage regulator is again reacting to the increased generator output voltage. These systems typically have power quality requirements that specify the upper and lower transient voltage limits that are permitted. Voltage regulation can be improved if the Generator Control Unit/Voltage Regulator can anticipate or prepare for the application or removal of electrical loads and the transient voltage limits can be more easily met.
BRIEF DESCRIPTIONIn accordance with one or more embodiments, a method of altering a generator output voltage in anticipation of a change with respect to a specific electrical load is provided. The method comprises altering, by a voltage regulator of the generator control unit, a set point to produce an altered set point; implementing, by the voltage regulator, a change of the altered set point; matching the generator output voltage to the altered set point to produce a matched generator output voltage; and providing the matched generator output voltage to the specific electrical load based on an operation of a contactor.
In accordance with an embodiment or the method embodiment above, implementing the change of the altered set point can include implementing a linear decay with respect to applying the matched generator output voltage.
In accordance with an embodiment or any of the method embodiments above, implementing the change of the altered set point can include implementing a linear increase with respect to removing the matched generator output voltage.
In accordance with an embodiment or any of the method embodiments above, a bus power control unit can receive a request to switch on the specific electrical load at a first time, and the specific electrical load can be required at an expected time.
In accordance with an embodiment or any of the method embodiments above, the bus power control unit can transmit communication signals to the generator control unit, and the generator control unit can receive the communication signals identifying the specific electrical load at a second time, and the first and second time can occur before the expected time.
In accordance with an embodiment or any of the method embodiments above, the communication signals from the bus power control unit can be responsive to a request to apply the specific electrical load.
In accordance with an embodiment or any of the method embodiments above, the communication signals from the bus power control unit can be responsive to a request to remove the specific electrical load.
In accordance with an embodiment or any of the method embodiments above, the bus power control unit can open and close the contactor in accordance with applying or removing the generator output voltage.
In accordance with an embodiment or any of the method embodiments above, the generator control unit can receive a request to switch on the specific electrical load at a first time, and the specific electrical load can be required at an expected time.
In accordance with an embodiment or any of the method embodiments above, the generator control unit can identify the specific electrical load at a second time, and the first and second time can occur before the expected time.
In accordance with one or more embodiment embodiments, a system of altering a generator output voltage in anticipation of a change with respect to a specific electrical load is provided. The system comprises a generator control unit comprising a voltage regulator; a generator; and a contactor, wherein the voltage regulator of the generator control unit alters a set point to produce an altered set point, wherein the voltage regulator of the generator control unit implements a change of the altered set point, wherein the generator matches the generator output voltage to the altered set point to produce a matched generator output voltage; and wherein the generator provides the matched generator output voltage to a specific electrical load based on an operation of the contactor.
In accordance with an embodiment or the system embodiment above, implementing the change of the altered set point can include implementing a linear decay with respect to applying the matched generator output voltage.
In accordance with an embodiment or any of the system embodiments above, implementing the change of the altered set point can include implementing a linear increase with respect to removing the matched generator output voltage.
In accordance with an embodiment or any of the system embodiments above, a bus power control unit can receive a request to switch on the specific electrical load at a first time, and the specific electrical load can be required at an expected time.
In accordance with an embodiment or any of the system embodiments above, the bus power control unit can transmit communication signals to the generator control unit, the generator control unit receives the communication signals identifying the specific electrical load at a second time, and the first and second time can occur before the expected time.
BRIEF DESCRIPTION OF THE DRAWINGSThe following descriptions should not be considered limiting in any way. With reference to the accompanying drawings, like elements are numbered alike:
FIG. 1 depicts a system for an improved generator output voltage regulation in accordance with one or more embodiments;
FIG. 2 depicts a process flow for an improved generator output voltage regulation in accordance with one or more embodiments; and
FIG. 3 depicts a process flow for an improved generator output voltage regulation in accordance with one or more embodiments.
DETAILED DESCRIPTIONA detailed description of one or more embodiments of the disclosed apparatus and method are presented herein by way of exemplification and not limitation with reference to the Figures.
Embodiments herein relate to a voltage regulator within a system that can increase a generator output voltage before large known loads are applied and decrease the generator output voltage before the large known loads are removed.
FIG. 1 depicts asystem100 in accordance with one or more embodiments. Thesystem100 comprises a bus power control unit (BPCU)110 and generator control unit (GCU)120 that includes avoltage regulator125. The BPCU110 and the GCU120 can be processing units or components thereof that direct operations within thesystem100.
The BPCU110 and the GCU120 can be implemented in hardware, software, and/or combination thereof, in combination with a memory (e.g., whether integrated or external to the processing units). TheBPCU110 and the GCU120 can utilize arithmetic logic and/or program instructions (stored on the memory) to direct the operations within thesystem100. Examples of the BPCU110 and the GCU120 can include, but are not limited to, digital signal processors, microcontrollers, microprocessor, system on chip designs, network on chips, field-programmable arrays, and the like. BPCU110 and GCU120 could also be integrated together into one unit and still function as described.
Thesystem100 further comprises agenerator130, acontactor140, a firstelectrical load150, and one or more additional loads155. Thegenerator130 is an electro-mechanical device that converts mechanical energy to electrical energy for use in a circuit, such as thesystem100. Examples of what propels thegenerator130 can include, but are not limited to, aircraft engines, internal combustion engines, steam and gas turbines, and the like (e.g., a turbine, a gas engine, a diesel engine, a water turbine, etc. that produces shaft horsepower to drive the generator). Thecontactor140 is an electrically controlled switch used for switching an electrical power circuit, such as the circuit between thegenerator130 and theelectrical load150.
According to one or more embodiments, the BPCU110 and the GCU120transfer communication signals161 via a communication bus, while the GCU120 and thegenerator130 transfer control signals163 via control wires. Thegenerator130 can further provide one ormore outputs165 via electrical wiring. As shown, the one ormore outputs165 can be provided to the firstelectrical load150 via thecontactor140 and/or the one or more additional loads155. Note that the BPCU110 based on thecontrol signal167 can control thecontactor140.
Thevoltage regulator125 of theGCU120 is an electromechanical mechanism that regulates one or more AC or DC voltages of thegenerator130. For example, theBPCU110, which controls the electrical loads, can notify thevoltage regulator125 via the communication signals161 (or other method) that a specific load is imminent. Thevoltage regulator125 can, in response, increase theoutput voltage165 in anticipation of the specific load. Similarly, thevoltage regulator125 can reduce theoutput voltage165 in anticipation of the specific load removal.
In view of thesystem100, it can be appreciated that, for alternating current (AC) loads controlled by theBPCU110, theGCU120, and/or other line replaceable units, the technical effects and benefits can include improved AC voltage regulation via the voltage regulator125 (which also leads to improved DC bus voltage regulation), along with increased voltage regulator gains and phase margins. Further, embodiments herein and the technical effects and benefits thereof are not limited to that function being performed by theBPCU110, theGCU120, and/or other line replaceable units, as preparing for load applications or removals by altering the generator output voltage in anticipation of load changes can be performed by alternative hardware, software, and/or combinations thereof
FIG. 2 depicts aprocess flow200 for an improved generator output voltage regulation in accordance with an embodiment. Theprocess flow200 can generally be implemented by and/or within thesystem100. Theprocess flow200 is described with respect to an aircraft implementation; however, embodiments herein are not limited thereto.
Theprocess flow200 begins atblock205, where the BPCU110 receives a request to switch on a specific electrical load. The request can be received at a first time T1. In accordance with an embodiment, the first time T1 can be equal to zero (e.g., T1=0).
The request can be, for example, from a hydraulic system of the aircraft to switch on an electric motor driven hydraulic pump that has inrush current. The inrush current can be large enough to cause a generator output voltage (e.g., theoutput voltage165 of the generator130) to exceed transient voltage limits. For example, an application of the specific electrical load can cause the generator output voltage to dip from a nominal 115 Vrms to 70 Vrms, outside of the transient voltage limits.
Atblock210, theBPCU110 transmits communication signals indicating that the specific electrical load will be applied. The communication signals can be transmitted at a second time T2. In accordance with an embodiment, the second time T2 can be at 5 milliseconds (e.g., T2=T1+5 milliseconds).
For instance, theBPCU110 can notify thevoltage regulator125 of theGCU120 via the communication signals161 that the specific electrical load is imminent. In accordance with one or more embodiments, the communication signals indicate that the specific electrical load can be applied within an expected time TX (TX=T1+X, where X can be 20 milliseconds).
Atblock215, theGCU120 receives communication signals. In this way, theGCU120 receives a warning that the specific electrical load is imminent (e.g., receives a warning at5 milliseconds that the specific electrical load is expected within the expected time TX). Atblock220, theGCU120 alters the generator output voltage set point. TheGCU120 can utilize thevoltage regulator125 to alter the set point in response to the warning from theBPCU110. For instance, thevoltage regulator125 can change the set point to aset voltage 165 volts. Atblock225, theGCU120 can utilize thevoltage regulator125 to implement a change. The change can be a linear change (such as a linear decay of the set point), a nonlinear change, etc. In accordance with one or more embodiments, theGCU120 linearly decays the set voltage at 300 volts/sec until normal set voltage of 115 Vrms is reached (e.g., can occur in less than 200 milliseconds). Thevoltage regulator125 can implement the linear decay in response to the changing the set point.
Atblock230, thegenerator control unit120 andvoltage regulator125 matches the generator output voltage to a specific voltage (e.g., based on the set point) to produce a matched generator output voltage. Thevoltage regulator125 of theGCU120 rapidly increases generator excitation current that causes the generator output voltage of thegenerator130 to rapidly increase (e.g., to 165 Vrms). Note that this rapid increase will occur in response to the increased set point. Also note that the rapid increase can occur at a third time T3. In accordance with an embodiment, the third time T3 can be at 10 milliseconds (e.g., T3=T1+10−milliseconds). In accordance with one or more embodiments, increasing an excitation current to the generator can be performed without altering the set point, such as by altering the measured generator output voltage within the voltage regulator to cause an increase in the excitation current and the generator output voltage.
Atblock235, theBPCU110 transmits a command to close thecontactor140. The command can be received at a fourth time T4. In accordance with an embodiment, the fourth time T4 can be at 15 milliseconds (e.g., T4=T1+15 milliseconds).
Atblock240, thecontactor140 closes to apply the generator output voltage. Thecontactor140 closes in response to the command ofblock235. Thecontactor140 can close at a fifth time T5, which can be in accordance with a delay between receiving the command and the actual closing. In accordance with an embodiment, the fifth time T5 can be at 30 milliseconds (e.g., T5=T1+30 milliseconds). Note that the set voltage can be approximately 160 volts, when the contactor closes and the voltage droops. Further, because the load application starts at a higher voltage, the low end of the voltage transient requirement is not violated. In addition, when the set voltage has returned to 115 Vrms at a sixth time T6, normal operation of thesystem100 can resume. In accordance with an embodiment, the sixth time T6 can be at 200 milliseconds (e.g., T6=T1+200 milliseconds)
In view of the above, improved regulation for a specific electrical load removal can be accomplished in complementary manner by lowering the set point. Turning now toFIG. 3, aprocess flow300 for an improved generator output voltage regulation is shown in accordance with an embodiment. The process flow300 can generally be implemented by and/or within thesystem100. Theprocess flow300 is described with respect to an aircraft implementation; however, embodiments herein are not limited thereto.
Theprocess flow300 begins atblock305, where theBPCU110 receives a request to switch off a specific electrical load. The request can be received at a first time T1. In accordance with an embodiment, the first time T1 can be equal zero (e.g., T1=0). The request can be, for example, from a hydraulic system of the aircraft to switch off an electric motor driven hydraulic pump that will result in a rapid increase in generator output voltage.
Atblock310, theBPCU110 transmits communication signals indicating that the specific electrical load will be removed. The communication signals can be transmitted at a second time T2. In accordance with an embodiment, the second time T2 can be at 5 milliseconds (e.g., T2=T1+5 milliseconds). For instance, theBPCU110 can notify thevoltage regulator125 of theGCU120 via the communication signals161 that the removal of the specific electrical load is imminent. In accordance with one or more embodiments, the communication signals indicate that the specific electrical load can be removed within an expected time TX (TX=T1+X, where X can be 20 milliseconds).
Atblock315, theGCU120 receives communication signals. Atblocks320 and325, theGCU120 alters a set point and utilizes thevoltage regulator125 to implement a change. The change can be a linear change (such as a gradual increase of the set point), a nonlinear change, etc. In accordance with one or more embodiments, the set point can be lowered to approximately 80 Vrms in anticipation of the specific electrical load removal. Further, the set point can then be gradually increased to 115 Vrms (such as over a time period of 200 milliseconds).
Atblock330, thegenerator control unit120 andvoltage regulator125 matches the generator output voltage to a specific voltage (e.g., based on the set point) to produce a matched generator output voltage. Thevoltage regulator125 of theGCU120 rapidly decreases generator excitation current that causes the generator output voltage of thegenerator130 to rapidly decrease. In accordance with one or more embodiments, decreasing an excitation current to the generator can be performed without altering the set point, such as by altering the measured generator output voltage within the voltage regulator to cause a decrease in the excitation current and the generator output voltage.
Atblock335, theBPCU110 transmits a command to open thecontactor140. The command can be received at a fourth time T4. In accordance with an embodiment, the fourth time T4 can be at 15 milliseconds (e.g., T4=T1+15 milliseconds). Atblock340, thecontactor140 opens to remove the generator output voltage.
In accordance with one or more embodiments, specific timings and alterations can be calibrated with respect to applications and components within the aircraft. In this way, thesystem100 can store and utilize multiple process flows for applying and/or removing specific electric loads based on the above process flows200 and300.
In accordance with one or more embodiments, thegenerator130 can be driven by an auxiliary power unit or an aircraft turbine with respect to an increase throttle setting and/or pneumatic loads. Further, theGCU120 can communicate to a full authority digital engine/electronics control (FADEC) instead of or in conjunction with theBPCU110. Furthermore, theGCU120 can communicate to an engine controller connected to an engine and/or to theBPCU110 through a communication bus can. In the latter case, like with the voltage regulator, theBPCU110 can instruct the engine controller to produce more power in anticipation of a specific load application or less power in anticipation of a specific load removal.
In accordance with one or more embodiments, the set voltage can be elevated and held until thecontactor140 actually closes or until after a specific time limit is exceeded. Once load is applied and voltage reached (or is near a set voltage), the ramp rate back to 115 Vrms can be accelerated. The amount of the ramp rate can depend on the closed loop damping of the voltage regulation.
The term “about” is intended to include the degree of error associated with measurement of the particular quantity based upon the equipment available at the time of filing the application. For example, “about” can include a range of ±8% or 5%, or 2% of a given value.
The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the present disclosure. As used herein, the singular forms “a”, “an” and “the” are intended to include the plural forms as well, unless the context clearly indicates otherwise. It will be further understood that the terms “comprises” and/or “comprising,” when used in this specification, specify the presence of stated features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, element components, and/or groups thereof
While the present disclosure has been described with reference to an exemplary embodiment or embodiments, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the scope of the present disclosure. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the present disclosure without departing from the essential scope thereof. Therefore, it is intended that the present disclosure not be limited to the particular embodiment disclosed as the best mode contemplated for carrying out this present disclosure, but that the present disclosure will include all embodiments falling within the scope of the claims.