Movatterモバイル変換


[0]ホーム

URL:


CN114764641B - Two-ticket management method, system, computer equipment and medium based on security verification - Google Patents

Two-ticket management method, system, computer equipment and medium based on security verification
Download PDF

Info

Publication number
CN114764641B
CN114764641BCN202210484635.8ACN202210484635ACN114764641BCN 114764641 BCN114764641 BCN 114764641BCN 202210484635 ACN202210484635 ACN 202210484635ACN 114764641 BCN114764641 BCN 114764641B
Authority
CN
China
Prior art keywords
bill
verification
power plant
process equipment
ticket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210484635.8A
Other languages
Chinese (zh)
Other versions
CN114764641A (en
Inventor
李维聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co LtdfiledCriticalChina Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN202210484635.8ApriorityCriticalpatent/CN114764641B/en
Publication of CN114764641ApublicationCriticalpatent/CN114764641A/en
Application grantedgrantedCritical
Publication of CN114764641BpublicationCriticalpatent/CN114764641B/en
Activelegal-statusCriticalCurrent
Anticipated expirationlegal-statusCritical

Links

Classifications

Landscapes

Abstract

The invention provides a two-ticket management method, a system, computer equipment and a medium based on security verification, wherein the method comprises the following steps: the method comprises the steps of building a power plant operation simulation model in advance according to the process flow of actual operation of a power plant, after generating an electronic bill according to acquired basic bill information, acquiring a corresponding bill operation flow and security measures, loading the power plant operation simulation model, reading equipment monitoring information of a power plant process control system and a plant-level real-time information system, executing the bill operation flow on an operation interface associated with process equipment to be operated in the retrieved power plant process control system, carrying out bill operation security verification by combining with the corresponding security measures, generating a bill operation verification report, and adjusting the bill operation flow to re-verify until successful when verification fails, and issuing approval. According to the invention, two ticket approvals and security verification are combined, and potential risks of ticket practice are effectively estimated through simulation of the ticket practice process, so that the security and stability of the ticket practice are improved.

Description

Two-ticket management method, system, computer equipment and medium based on security verification
Technical Field
The invention relates to the technical field of operation and maintenance of power systems, in particular to a two-ticket management method, a system, computer equipment and a storage medium based on security verification.
Background
With the enlargement of domestic power plants and the refinement of production management, new requirements are put forward for the safe production work of electric power. The two-ticket management system is used as a management system for simultaneously supervising the operation ticket and the work ticket, is a basis for the safety production management of the power plant, and provides important guarantee for the safe and stable operation of the power system.
In a conventional power enterprise, two-ticket management mainly comprises two modes of traditional manual management and digital intelligent management: the traditional manual management is a management mode that operation and maintenance personnel manually fill in two tickets, the two tickets are approved through paper files in a flow mode, the operation and maintenance personnel hold the approved tickets to the site for operation, and after the operation is completed, the two tickets of the paper form are archived; the digitalized intelligent management is to produce working tickets and operation tickets in a digitalized mode, adopt an electronic flow to examine and approve, and automatically finish the management mode of filing on a system after operation and maintenance personnel hold the electronic two tickets. The two existing two-ticket management modes have corresponding defects in the actual production management application, such as inconvenient archiving and recording of the traditional manually-managed handwritten ticket, time and labor waste in the examination and approval circulation process, whether the operation flow and the operation measure meet the safety production requirement or not are ensured by totally depending on the working experience of the maintainer and the examination and approval person, the risk of imperfect two-ticket management caused by the insufficient working experience of the maintainer and the examination and approval person exists, the actual situation of the production site cannot be reflected in time, and safety accidents are caused by unpredictable situations in the production and operation process; although the digital intelligent management realizes the electronization of the two-ticket management system, solves the problem that archiving records and examination and approval circulation are time-consuming and labor-consuming, the two-ticket filling and examination in the electronization system still depends on the working experience of an applicant and an examination and approval person, and the problems that the two-ticket management lacks of data association with a field control system, the actual situation of a production field cannot be timely reflected, and the risks of influencing the normal operation of a machine set, damaging an equipment body or associated equipment, fluctuation of a power grid, or influence of scheduling load and the like can not be timely estimated in the actual operation process of the ticket can be solved.
Therefore, it is needed to provide an intelligent two-ticket management system capable of reacting in real time to the actual situation of the ticket operation process according to the application requirements of two tickets and timely sensing the potential risk of the actual ticket operation.
Disclosure of Invention
The invention aims to provide a two-ticket management method, a system, computer equipment and a storage medium based on security verification, which are used for effectively predicting potential risks of actual operation of a ticket, improving the security and stability of the actual operation of the ticket, further improving the effectiveness and rationality of two-ticket management and providing reliable guarantee for the safe and stable operation of an electric power system by combining two-ticket approval with the logic security verification of the operation of a power plant.
In order to achieve the above object, it is necessary to provide a two-ticket management method, system, computer device and storage medium based on security verification.
In a first aspect, an embodiment of the present invention provides a security verification-based two-ticket management method, including the steps of:
carrying out systematic modeling on actual process equipment of a power plant according to the actual operation process flow of the power plant in advance, and constructing a power plant operation simulation model;
Responding to a bill application request, acquiring bill basic information, and generating a corresponding electronic bill according to the bill basic information; the bill comprises a work bill and an operation bill;
according to the electronic bill, acquiring a corresponding bill operation flow and safety measures, loading a power plant operation simulation model, reading process equipment monitoring information of a power plant process control system and a plant-level real-time information system, and calling an operation interface associated with process equipment to be operated in the power plant process control system;
executing the bill operation flow on the operation interface, carrying out bill operation safety verification by combining the safety measures according to the power plant operation simulation model, a power plant process control system and a plant-level real-time information system, and generating a bill operation verification report;
and judging whether the verification is successful or not according to the bill operation verification report, if so, executing the electronic bill issuing and approval, otherwise, adjusting the bill operation flow, and re-executing the bill operation safety verification until the verification is successful.
Further, the basic bill information comprises a code of the technological equipment to be operated, a name of the technological equipment to be operated, working time length, related professional and personnel information;
The step of retrieving an operation interface associated with the process equipment to be operated in the process control system of the power plant comprises the following steps:
extracting an operation interface associated with the process equipment to be operated in the power plant process control system from a database according to the code of the process equipment to be operated of the electronic bill, and displaying the running state information of each process equipment in real time; the operating state information includes device parameters and device states.
Further, the step of obtaining the corresponding bill operation flow and the security measure includes:
traversing a database according to the operation type of the electronic bill, and judging whether a preset bill operation flow and safety measures exist or not;
if the preset bill operation flow and the safety measure exist, the corresponding bill operation flow and the safety measure are directly acquired, otherwise, the bill operation flow and the safety measure which are input in real time are acquired through an operation interface related to the process equipment to be operated.
Further, the power plant process control system comprises a distributed control system, a programmable logic control system, a plant electricity monitoring management system and a power network computing monitoring system.
Further, the steps of executing the bill operation flow on the operation interface, carrying out bill operation safety verification by combining the safety measures according to the power plant operation simulation model, the power plant process control system and the plant-level real-time information system, and generating a bill operation verification report comprise the following steps:
Executing the bill operation flow on the operation interface in a step sequence, synchronizing corresponding operation instructions to the power plant operation simulation model in combination with the safety measures, adjusting the process equipment to be operated, and synchronizing process equipment monitoring information of a power plant process control system and a plant-level real-time information system in real time; the process equipment monitoring information comprises operation state information of all process equipment in the power plant operation simulation model corresponding to each step of the bill operation flow;
according to the process equipment monitoring information, analyzing whether each step of the bill operation flow is executed with related equipment safety risks in real time, and obtaining verification analysis results corresponding to each step;
and finishing and generating a bill operation verification report according to each verification analysis result in response to the completion of the bill operation flow.
Further, the step of analyzing whether the safety risk of the related equipment exists in each step of the bill operation flow in real time according to the process equipment monitoring information includes:
analyzing whether linkage action relations between the process equipment to be operated and other process equipment exist or not according to the process equipment monitoring information corresponding to each step;
Judging whether the parameter fluctuation and the state change of each process equipment with the linkage action relationship are in a normal range, if so, judging that the safety risk of the related equipment does not exist, otherwise, judging that the safety risk of the related equipment exists.
Further, the bill operation verification report comprises an adjustment suggestion of verification failure;
the step of adjusting the bill operation flow and re-executing the bill operation safety verification until the verification is successful comprises the following steps:
and adjusting the bill operation flow according to the adjustment suggestion in the bill operation verification report, and executing the adjusted bill operation flow on the operation interface again according to the step sequence.
In a second aspect, an embodiment of the present invention provides a two-ticket management system based on security verification, the system including:
the system comprises a power plant simulation module, a two-ticket management module, an information synchronization module, a logic verification module, a verification adjustment module and a database:
the power plant simulation module is used for carrying out systematic modeling on actual process equipment of the power plant according to the actual operation process flow of the power plant and constructing a power plant operation simulation model; the power plant operation simulation model is also used for loading the state of the process equipment and the operation instruction, and the power plant operation simulation model is interacted with the logic verification module through the information synchronization module;
The two-ticket management module is used for responding to a ticket application request, acquiring ticket basic information and generating a corresponding electronic ticket according to the ticket basic information; the electronic bill verification system is also used for configuring a two-bill generation standard, a two-bill operation flow and safety measures, and carrying out approval on the electronic bill according to the verification result of the logic verification module;
the information synchronization module is used for acquiring a corresponding bill operation flow and safety measures according to the electronic bill, loading a power plant operation simulation model, reading process equipment monitoring information of a power plant process control system and a plant-level real-time information system, and calling an operation interface associated with process equipment to be operated in the power plant process control system from the database; the system is also used for synchronously acquiring and displaying the state information of the process equipment from the power plant process control system and the plant-level real-time information monitoring system; the power plant process control system comprises a distributed control system, a programmable logic control system, a plant power monitoring management system and a power network computing and monitoring system; the state information comprises equipment parameters and equipment states;
the logic verification module is used for executing the bill operation flow on the operation interface, synchronizing information with the power plant operation simulation model, the power plant process control system and the plant-level real-time information system through the information synchronization module, performing bill operation safety verification, and generating a bill operation verification report;
The verification adjustment module is used for adjusting the bill operation flow when judging that the bill operation verification report is verification failure, and re-executing the bill operation safety verification through the logic verification module until the verification is successful;
the database is used for storing the data information of each module.
In a third aspect, embodiments of the present application further provide a computer device, including a memory, a processor, and a computer program stored on the memory and executable on the processor, the processor implementing the steps of the above method when executing the computer program.
In a fourth aspect, embodiments of the present application also provide a computer readable storage medium having stored thereon a computer program which, when executed by a processor, implements the steps of the above method.
The application provides a two-ticket management method, a system, computer equipment and a storage medium based on security verification, by the method, the application realizes that the actual process equipment of a power plant is systematically modeled in advance according to the actual process flow of the power plant, a power plant operation simulation model is built, after an electronic ticket is generated according to the acquired basic information of the ticket, the corresponding ticket operation flow and security measures are acquired, the power plant operation simulation model is loaded, the process equipment monitoring information of a power plant process control system and a plant-level real-time information system is read, then the ticket operation flow is executed on an operation interface associated with the process equipment to be operated in the acquired power plant process control system, the security verification of the ticket operation is carried out by combining with the corresponding security measures, a ticket operation verification report is generated, and when verification fails, the ticket operation flow is adjusted to be re-verified until success, and the technical scheme of electronic ticket issuing approval is executed. Compared with the prior art, the two-ticket management method based on the security verification combines two-ticket approval with the power plant operation logic security verification, comprehensively verifies and analyzes factors such as execution operation, execution time length and execution result of the ticket through simulation of the ticket actual operation process and monitoring of the equipment operation state, effectively predicts potential risks of ticket actual operation, improves the security and stability of ticket actual operation, further improves the effectiveness and rationality of two-ticket management, and provides reliable guarantee for safe and stable operation of an electric power system.
Drawings
FIG. 1 is a schematic diagram of an application scenario of a two-ticket management method based on security verification in an embodiment of the present application;
FIG. 2 is a flow chart of a two-ticket management method based on security verification in an embodiment of the application;
FIG. 3 is a schematic flow chart of a logical security verification of the two-ticket operation flow in FIG. 2;
FIG. 4 is a schematic diagram of a two-ticket management system based on security verification in an embodiment of the present application;
fig. 5 is an internal structural view of a computer device in an embodiment of the present application.
Detailed Description
In order to make the objects, technical solutions and advantageous effects of the present application more apparent, the present application will be further described in detail with reference to the accompanying drawings and examples, and it is apparent that the examples described below are part of the examples of the present application, which are provided for illustration only and are not intended to limit the scope of the present application. All other embodiments, which can be made by those skilled in the art based on the embodiments of the application without making any inventive effort, are intended to be within the scope of the application.
The two-ticket management method based on the security verification provided by the application can be applied to the two-ticket management method based on the security verification shown in the figure 1, and can be applied to a server or terminal equipment shown in the figure 1. The terminal may be, but not limited to, various personal computers, notebook computers, smartphones, tablet computers and portable wearable devices, and the server may be implemented by a separate server or a server cluster formed by a plurality of servers. The server can preset a standard flow of two-ticket management, realize interactive butt joint with a power plant process control system and a factory-level real-time information system, build a power plant operation simulation model according to the process flow of the actual operation of a power plant, acquire a corresponding operation flow and safety measures according to the type of an application ticket when receiving an operation ticket or a work ticket filling application of a user terminal, execute control of process equipment to be operated according to the operation flow and the safety measures on a related operation interface of the power plant process control system, synchronize to the power plant operation simulation model for simulation, and perform ticket operation safety risk assessment verification according to equipment state monitoring information synchronized by the power plant process control system and the factory-level real-time information system, judge whether the ticket passes the verification result, inform a user terminal to adjust and re-verify the operation flow when the ticket passes the verification, inform the user terminal to receive the actual operation of the ticket and complete storage and archiving after the corresponding actual operation is completed, and effectively improve the safety and stability of the actual operation ticket. The security verification-based two-ticket management method of the present application will be described in detail by way of examples.
In one embodiment, as shown in fig. 2, there is provided a two-ticket management method based on security verification, the method comprising the steps of:
s11, carrying out systematic modeling on actual process equipment of the power plant in advance according to the actual operation process flow of the power plant, and building a power plant operation simulation model;
the power plant operation simulation model can be understood as that by carrying out mechanism analysis on actual operation process equipment of the power plant and carrying out systematic modeling which accords with the process operation characteristics of the power plant on different process equipment, the simulation of the mechanism operation of the actual process equipment of the power plant can be realized by loading the state and the operation instruction of the actual operation equipment, the mathematical model which truly reflects the actual operation condition of the power plant can be more similar to the actual operation environment analysis, a reliable and effective logic operation environment is provided for logic security verification of the follow-up bill operation flow, and the security of the actual operation of the bill is further effectively improved.
S12, responding to a bill application request, acquiring bill basic information, and generating a corresponding electronic bill according to the bill basic information; the bill comprises a work bill and an operation bill;
the operation ticket is an electric operation application ticket for carrying out dispatching instructions or control operations on the power plant side; the work ticket is a public ticket of the power generation part, the equipment maintenance part and the security monitoring part, and is an application ticket for performing maintenance, safe execution, management and other operations on equipment; bill basic information may be understood as bill content that must be filled in according to the type of bill according to the creation requirement of a preset bill generation template, which includes, but is not limited to, a process equipment code to be operated, a process equipment name to be operated, a working time period, related professional and personnel information (personnel basic information, department team information, etc.). When receiving the application request of the operation ticket or the working ticket which is filled in the basic information of the ticket by the user through the terminal equipment, the corresponding electronic ticket can be generated according to the template of the ticket type, and the generated electronic ticket is subjected to logic security verification and ticket approval according to the operation flow and security measures of the ticket according to the standard flow management specification of the corresponding ticket type, wherein the specific electronic ticket generation mode is realized by adopting the prior art and is not repeated here.
S13, acquiring a corresponding bill operation flow and safety measures according to the electronic bill, loading a power plant operation simulation model, reading process equipment monitoring information of a power plant process control system and a plant-level real-time information system, and calling an operation interface associated with process equipment to be operated in the power plant process control system;
the power plant operation simulation model is used for simulating an actual operation mechanism of a power plant, the power plant process control system and the plant-level real-time information system are systems for monitoring the operation states of all process equipment and equipment cabinets of the power plant, and numerous data supports such as actual control system pictures, data, equipment states and equipment attributes are provided for subsequent logic security verification, wherein the power plant process control system comprises a distributed control system, a programmable logic control system, a plant power monitoring management system and a power network computing monitoring system, and can be selected and adjusted according to actual application requirements; the operation interface associated with the process equipment to be operated can be understood as a visual operation interface which is extracted based on the database information corresponding to each power plant process control system according to the visual control requirement, according to the code of the process equipment to be operated or the name of the process equipment to be operated of the electronic bill, and is used for performing operation control on the related process equipment and updating and displaying the real-time state of the related process equipment including the equipment parameters and the equipment state.
The logical security verification of the electronic bill can be understood as operation security verification and risk assessment performed on the operation flow and security measures of the electronic bill to be used based on the actual process operation mechanism of the power plant; in order to better solve the problems that the existing two-ticket approval excessively depends on the working experience of operation staff and approval staff, safety accidents are easy to cause due to the fact that the running condition of a power plant in the actual operation process is invisible, and the like, the embodiment preferably carries out corresponding visual logic safety simulation verification on the bill operation flow and safety measures through a power plant running simulation model, a power plant process control system and a plant-level real-time information system after the electronic bill is generated according to a standard template or preset requirements, and is then used for actual production operation. Before starting verification, the corresponding operation flow and safety measures are required to be obtained according to the electronic bill information, and a power plant operation simulation model, a power plant process control system and a plant-level real-time information system are loaded and operated, and an operation interface associated with process equipment to be operated in the power plant process control system is called based on a database;
the bill operation flow can be understood as the operation method steps of the process equipment related to the bill, and the corresponding safety measures can be understood as the means for ensuring the safety production, such as isolation point setting corresponding to the operation method steps; it should be noted that, in order to ensure the intelligence and efficiency of logic security verification, in this embodiment, preferably, the operation flow and security measures corresponding to a common operation ticket or work ticket may be preconfigured according to working experience and stored in a database to implement the full-automatic operation of subsequent logic verification, and for the case that no operation flow and security measure exist in the existing database, the user may flexibly formulate and adjust the operation flow according to actual requirements, and directly manually input the operation flow and security measure on an operation interface associated with the process equipment to be operated, and correspondingly, the step of obtaining the corresponding ticket operation flow and security measure includes:
Traversing a database according to the operation type of the electronic bill, and judging whether a preset bill operation flow and safety measures exist or not;
if the preset bill operation flow and the safety measure exist, the corresponding bill operation flow and the safety measure are directly acquired, otherwise, the bill operation flow and the safety measure which are input in real time are acquired through an operation interface related to the process equipment to be operated.
S14, executing the bill operation flow on the operation interface, carrying out bill operation safety verification by combining the safety measures according to the power plant operation simulation model, the power plant process control system and the plant-level real-time information system, and generating a bill operation verification report; in order to ensure feasibility, safety and integrity of related logic safety verification, the embodiment preferably performs verification in steps, in sequence and in a preset execution duration, and performs real-time observation and analysis on the running state of process equipment of a power plant to evaluate and record operation risks of each step, as shown in fig. 3, the specific steps for performing the safety verification of the bill operation include:
Executing the bill operation flow on the operation interface in a step sequence, synchronizing corresponding operation instructions to the power plant operation simulation model in combination with the safety measures, adjusting the process equipment to be operated, and synchronizing process equipment monitoring information of a power plant process control system and a plant-level real-time information system in real time; the process equipment monitoring information comprises operation state information of all process equipment in the power plant operation simulation model corresponding to each step of the bill operation flow; wherein, the operation instructions comprise equipment start/stop, cabinet switch on/off, valve on/off and the like; the operation state information comprises equipment parameters and equipment states, wherein the equipment parameters comprise, but are not limited to, temperature, pressure, flow, current, quality and the like, and the equipment states comprise, but are not limited to, start/stop instructions, opening and closing instructions, cabinet switch states, fault alarms and the like;
according to the process equipment monitoring information, analyzing whether each step of the bill operation flow is executed with related equipment safety risks in real time, and obtaining verification analysis results corresponding to each step; the related equipment safety risk can be understood as the evaluation analysis conclusion and the risk of whether the related equipment safety risk exists in the execution process of the corresponding step sequence action of each step or not are obvious, wherein the evaluation analysis conclusion and the risk are that the unit operation influence is generated, the process equipment is damaged, the personnel operation environment is unsuitable, and the like; specifically, the step of analyzing, in real time, whether the execution of each step of the bill operation flow has a related equipment security risk according to the process equipment monitoring information includes:
Analyzing whether linkage action relations between the process equipment to be operated and other process equipment exist or not according to the process equipment monitoring information corresponding to each step;
judging whether the parameter fluctuation and the state change of each process equipment with the linkage action relationship are in a normal range, if so, judging that the safety risk of the related equipment does not exist, otherwise, judging that the safety risk of the related equipment exists;
according to the method, the ticket operation flow is executed step by step, a control system interface of an actual operation process is loaded, real-time equipment state synchronization is carried out through a database, consistency of pictures and states and an operation picture of an actual power plant process control system is achieved, understanding and execution of personnel are facilitated, convenience is brought to selection of manual operation in the process of executing two related tickets, actual conditions of a production site can be reflected timely, whether normal operation of a machine set, damage of an equipment body or associated equipment, power grid fluctuation or scheduling load influence and the like are influenced due to operation in the ticket execution process is perceived timely, reliable and effective verification and analysis functions are achieved, and safety, rationality and effectiveness of two ticket approval are guaranteed;
And finishing and generating a bill operation verification report according to each verification analysis result in response to the completion of the bill operation flow.
S15, judging whether the verification is successful or not according to the bill operation verification report, if so, executing the electronic bill issuing approval, otherwise, adjusting the bill operation flow, and re-executing the bill operation safety verification until the verification is successful; wherein the bill operation verification report comprises adjustment advice of verification failure; correspondingly, the step of adjusting the bill operation flow and re-executing the bill operation safety verification until the verification is successful comprises the following steps:
according to the adjustment suggestion in the bill operation verification report, adjusting the bill operation flow, and executing the adjusted bill operation flow again according to the step sequence on the operation interface; in principle, the preset bill operation flow of the database can be modified by adjusting the bill operation flow, and the verification is performed according to the steps, but in order to ensure the high efficiency of the logic security verification, the embodiment preferably adopts manual adjustment of the bill operation flow and directly performs real-time operation verification on the corresponding operation interface, and after the verification is passed, the corresponding operation flow and security measures are stored in the database, so as to provide data support for the operation security verification of the subsequent electronic bill.
After the electronic bill issuing and approval work is completed through the steps, operation and maintenance personnel can start working isolation to overhaul or maintain related process equipment according to the bill operation flow and safety measures which pass verification, and after the related work task is completed and the test is successful, archiving and storing of the corresponding electronic bill are completed.
According to the embodiment of the application, the flow standardized work approval flow of the two-ticket management is associated with the equipment state data of the on-site control system of the power plant, the simulation of the ticket actual operation process is carried out by combining the power plant simulation model, the comprehensive and effective visual logic safety verification analysis is carried out on the factors such as the execution operation, the execution time length and the execution result of each step of the ticket operation flow, the ticket actual operation risk is effectively evaluated in time, the safety and the stability of the ticket actual operation are improved, the effectiveness and the rationality of the two-ticket management are further improved, the reliable guarantee is provided for the safe and stable operation of the power system, and meanwhile, the related operation and maintenance personnel can be subjected to actual operation training learning by utilizing the simulation logic safety verification method of the application, so that the operation flow is quickly understood and the skill level is improved.
Although the steps in the flowcharts described above are shown in order as indicated by arrows, these steps are not necessarily executed in order as indicated by the arrows. The steps are not strictly limited to the order of execution unless explicitly recited herein, and the steps may be executed in other orders.
In one embodiment, as shown in fig. 4, a two-ticket management system based on security verification is provided, the system comprising a power plant simulation module, a two-ticket management module, an information synchronization module, a logic verification module, a verification adjustment module, and a database:
the power plant simulation module 1 is used for carrying out systematic modeling on actual process equipment of a power plant according to the actual operation process flow of the power plant, and building a power plant operation simulation model; the power plant operation simulation model is also used for loading the state of the process equipment and the operation instruction, and the power plant operation simulation model is interacted with the logic verification module through the information synchronization module;
the two-ticket management module 2 is used for responding to a ticket application request, acquiring ticket basic information and generating a corresponding electronic ticket according to the ticket basic information; the electronic bill verification system is also used for configuring a two-bill generation standard, a two-bill operation flow and safety measures, and carrying out approval on the electronic bill according to the verification result of the logic verification module;
the information synchronization module 3 is used for acquiring a corresponding bill operation flow and safety measures according to the electronic bill, loading a power plant operation simulation model, reading process equipment monitoring information of a power plant process control system and a plant-level real-time information system, and retrieving an operation interface associated with process equipment to be operated in the power plant process control system from the database; the system is also used for synchronously acquiring and displaying the state information of the process equipment from the power plant process control system and the plant-level real-time information monitoring system; the power plant process control system comprises a distributed control system, a programmable logic control system, a plant power monitoring management system and a power network computing and monitoring system; the state information comprises equipment parameters and equipment states;
The logic verification module 4 is configured to execute the bill operation flow on the operation interface, perform information synchronization with the power plant operation simulation model, the power plant process control system and the plant-level real-time information system through the information synchronization module, perform safety verification on bill operation, and generate a bill operation verification report;
the verification adjustment module 5 is configured to adjust the bill operation flow when the bill operation verification report is determined to be verification failure, and re-execute the bill operation security verification through the logic verification module until the verification is successful;
the database 6 is used for storing data information of each module.
It should be noted that, for specific limitation of the two-ticket management system based on security verification, reference may be made to the limitation of the two-ticket management method based on security verification hereinabove, and the description thereof is omitted herein. The respective modules in the above-described security verification-based two-ticket management system may be implemented in whole or in part by software, hardware, and combinations thereof. The above modules may be embedded in hardware or may be independent of a processor in the computer device, or may be stored in software in a memory in the computer device, so that the processor may call and execute operations corresponding to the above modules.
Fig. 5 shows an internal structural diagram of a computer device, which may be a terminal or a server in particular, in one embodiment. As shown in fig. 5, the computer device includes a processor, a memory, a network interface, a display, and an input device connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and computer programs in the non-volatile storage media. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program, when executed by a processor, implements the two-ticket management method based on security verification described above. The display screen of the computer equipment can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer equipment can be a touch layer covered on the display screen, can also be keys, a track ball or a touch pad arranged on the shell of the computer equipment, and can also be an external keyboard, a touch pad or a mouse and the like.
It will be appreciated by those of ordinary skill in the art that the structure shown in FIG. 5 is merely a block diagram of some of the structures associated with the present inventive arrangements and is not limiting of the computer device to which the present inventive arrangements may be applied, and that a particular computing power device may include more or fewer components than shown, or may combine some of the components, or have the same arrangement of components.
In one embodiment, a computer device is provided comprising a memory, a processor, and a computer program stored on the memory and executable on the processor, the processor implementing the steps of the above method when the computer program is executed.
In one embodiment, a computer readable storage medium is provided having a computer program stored thereon, which when executed by a processor, implements the steps of the above method.
In summary, the two-ticket management method, the system, the computer equipment and the storage medium based on the security verification provided by the embodiment of the application are characterized in that the two-ticket management method based on the security verification carries out systematic modeling on the actual process equipment of the power plant through the process flow which is actually operated in advance according to the power plant, builds a power plant operation simulation model, acquires corresponding ticket operation flows and security measures after generating an electronic ticket according to acquired ticket basic information, loads the corresponding ticket operation simulation model and process equipment monitoring information of a power plant process control system and a factory-level real-time information system, then carries out ticket operation flows on an operation interface which is associated with the process equipment to be operated in the acquired power plant process control system, carries out ticket operation security verification by combining corresponding security measures, generates ticket operation verification reports, and adjusts the ticket operation flows to carry out verification again until successful, carries out comprehensive and effective visual security verification analysis on factors such as execution operation, execution duration, execution results and the like of each step of the ticket operation flows, and the like, effectively carries out real-time operation risk assessment according to the fact, improves the security and stability of the real-time operation, further carries out the security verification and reliability of the ticket operation, and the security management of the two-ticket operation flows can be effectively and effectively provides the security training and training for the relevant operation and operation skills.
In this specification, each embodiment is described in a progressive manner, and all the embodiments are directly the same or similar parts referring to each other, and each embodiment mainly describes differences from other embodiments. In particular, for system embodiments, since they are substantially similar to method embodiments, the description is relatively simple, as relevant to see a section of the description of method embodiments. It should be noted that, any combination of the technical features of the foregoing embodiments may be used, and for brevity, all of the possible combinations of the technical features of the foregoing embodiments are not described, however, as long as there is no contradiction between the combinations of the technical features, they should be considered as the scope of the description.
The foregoing examples represent only a few preferred embodiments of the present application, which are described in more detail and are not to be construed as limiting the scope of the application. It should be noted that modifications and substitutions can be made by those skilled in the art without departing from the technical principles of the present application, and such modifications and substitutions should also be considered to be within the scope of the present application. Therefore, the protection scope of the patent of the application is subject to the protection scope of the claims.

Claims (8)

the information synchronization module is used for acquiring a corresponding bill operation flow and safety measures according to the electronic bill, loading a power plant operation simulation model, reading process equipment monitoring information of a power plant process control system and a plant-level real-time information system, and calling an operation interface associated with process equipment to be operated in the power plant process control system from the database; the system is also used for synchronously acquiring and displaying the state information of the process equipment from the power plant process control system and the plant-level real-time information monitoring system; the power plant process control system comprises a distributed control system, a programmable logic control system, a plant power monitoring management system and a power network computing and monitoring system; the state information comprises equipment parameters and equipment states;
CN202210484635.8A2022-04-292022-04-29Two-ticket management method, system, computer equipment and medium based on security verificationActiveCN114764641B (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN202210484635.8ACN114764641B (en)2022-04-292022-04-29Two-ticket management method, system, computer equipment and medium based on security verification

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN202210484635.8ACN114764641B (en)2022-04-292022-04-29Two-ticket management method, system, computer equipment and medium based on security verification

Publications (2)

Publication NumberPublication Date
CN114764641A CN114764641A (en)2022-07-19
CN114764641Btrue CN114764641B (en)2023-11-14

Family

ID=82365216

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN202210484635.8AActiveCN114764641B (en)2022-04-292022-04-29Two-ticket management method, system, computer equipment and medium based on security verification

Country Status (1)

CountryLink
CN (1)CN114764641B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN115481862A (en)*2022-08-122022-12-16华能山东发电有限公司Safety production management platform for realizing dual management and control
CN116228191A (en)*2022-12-262023-06-06深圳供电局有限公司Operation ticket generation method, device, computer equipment and storage medium

Citations (12)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
IL202029A0 (en)*2009-11-102010-06-16Icts Holding Company LtdComputerized integrated authentication/ document bearer verification system and methods useful in conjunction therewith
JP2012252433A (en)*2011-06-012012-12-20Fujitsu Semiconductor LtdVerification method and verification program
CN106372786A (en)*2016-08-292017-02-01长园共创电力安全技术股份有限公司"Two ticket" operation safety management and control system and method
CN108388158A (en)*2018-04-102018-08-10济南纵向软件有限公司Internet of Things wind turbine hatch door safe related function control method based on two ticket management of electric power
CN109299843A (en)*2018-01-122019-02-01上海麟益信息科技有限公司A kind of Risk Pre-control analysis intelligent management
CN110908347A (en)*2019-11-142020-03-24中国大唐集团科学技术研究院有限公司火力发电技术研究院Intelligent power plant management and control system based on Internet of things
CN111274780A (en)*2020-01-172020-06-12浙江中控技术股份有限公司Two-ticket management method and system
CN112381413A (en)*2020-11-162021-02-19安徽亦能电力科技有限公司Two-ticket software system based on industrial internet and digitization technology
CN113537695A (en)*2021-05-282021-10-22东莞理工学院Quantitative evaluation method for excessive emission risk of flue gas pollutants of waste incineration power plant
CN113658366A (en)*2021-08-202021-11-16华能国际电力股份有限公司上海石洞口第二电厂 A safety management and control system for limited space operation in thermal power plants
CN113673100A (en)*2021-08-182021-11-19雅砻江流域水电开发有限公司 A three-dimensional visualization intelligent simulation system for hydropower station and its training method
AU2021102711A4 (en)*2021-05-202021-12-02Himadri BiswasSystem and method for cloud management for provisioning multiple services through smart virtual green cloud

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
US8532342B2 (en)*2008-02-122013-09-10Certusview Technologies, LlcElectronic manifest of underground facility locate marks

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
IL202029A0 (en)*2009-11-102010-06-16Icts Holding Company LtdComputerized integrated authentication/ document bearer verification system and methods useful in conjunction therewith
JP2012252433A (en)*2011-06-012012-12-20Fujitsu Semiconductor LtdVerification method and verification program
CN106372786A (en)*2016-08-292017-02-01长园共创电力安全技术股份有限公司"Two ticket" operation safety management and control system and method
CN109299843A (en)*2018-01-122019-02-01上海麟益信息科技有限公司A kind of Risk Pre-control analysis intelligent management
CN108388158A (en)*2018-04-102018-08-10济南纵向软件有限公司Internet of Things wind turbine hatch door safe related function control method based on two ticket management of electric power
CN110908347A (en)*2019-11-142020-03-24中国大唐集团科学技术研究院有限公司火力发电技术研究院Intelligent power plant management and control system based on Internet of things
CN111274780A (en)*2020-01-172020-06-12浙江中控技术股份有限公司Two-ticket management method and system
CN112381413A (en)*2020-11-162021-02-19安徽亦能电力科技有限公司Two-ticket software system based on industrial internet and digitization technology
AU2021102711A4 (en)*2021-05-202021-12-02Himadri BiswasSystem and method for cloud management for provisioning multiple services through smart virtual green cloud
CN113537695A (en)*2021-05-282021-10-22东莞理工学院Quantitative evaluation method for excessive emission risk of flue gas pollutants of waste incineration power plant
CN113673100A (en)*2021-08-182021-11-19雅砻江流域水电开发有限公司 A three-dimensional visualization intelligent simulation system for hydropower station and its training method
CN113658366A (en)*2021-08-202021-11-16华能国际电力股份有限公司上海石洞口第二电厂 A safety management and control system for limited space operation in thermal power plants

Also Published As

Publication numberPublication date
CN114764641A (en)2022-07-19

Similar Documents

PublicationPublication DateTitle
CN107193375B (en)Electric power safety production scene interaction system based on virtual reality
Zou et al.Human reliability analysis for digitized nuclear power plants: case study on the LingAo II nuclear power plant
CN114764641B (en)Two-ticket management method, system, computer equipment and medium based on security verification
LaGrangeDeveloping a digital twin: The roadmap for oil and gas optimization
AmblerProcess patterns: building large-scale systems using object technology
Lin et al.Developing Mobile‐and BIM‐Based Integrated Visual Facility Maintenance Management System
Choo et al.Pragmatic adaptation of the ISO 31000: 2009 enterprise risk management framework in a high-tech organization using Six Sigma
Al Hayek et al.Cloud ERP vs On-Premise ERP
CN109933934A (en)A kind of equipment maintenance and management method and system, computer readable storage medium
CN107591216B (en) A mixed reality system and method for nuclear power plant digital instrumentation and control
EkanemA model-based human reliability analysis methodology (Phoenix method)
CN115423133A (en)Power plant maintenance platform and maintenance method
Cai et al.A framework analyzing system status and human activities: Illustrated using 2011 Fukushima nuclear power plant accident scenarios
KR102173137B1 (en)Method for providing remote test service for mobile application
CN116110265A (en) A visual simulation training method and system based on thermal power plant digital twin
Hall et al.The evolution of the Human Systems and Simulation Laboratory in nuclear power research
Posada et al.Job roles for digital twinning building construction processes. Introducing the digital twin manager position
CN111898993A (en)Operation ticket management system
CN118233309A (en) Cloud seat management method, device, equipment and storage medium based on simulation cloud
CN117114600A (en) A RPA virtual employee management method and system for power grid production command center
CN113537507B (en)Machine learning system, method and electronic equipment
Angelopoulou et al.A framework for simulation-based task analysis-The development of a universal task analysis simulation model
Hunton et al.Integrated Operations for Nuclear: Work Reduction Opportunity Demonstration Strategy
Jeong et al.Development of severe accident management advisory and training simulator (SAMAT)
Lobato et al.The importance of documentation, design and reuse in risk management for SPL

Legal Events

DateCodeTitleDescription
PB01Publication
PB01Publication
SE01Entry into force of request for substantive examination
SE01Entry into force of request for substantive examination
GR01Patent grant
GR01Patent grant

[8]ページ先頭

©2009-2025 Movatter.jp