The equipment production information management method and device of assembled architecture platformTechnical field
The invention belongs to a kind of productions of the equipment of as-built information modelling technique field more particularly to assembled architecture platform to believeCease management method and device.
Background technique
BIM, i.e. Building Information Model (Building Information Modeling) are based on construction-engineering projectThe big data established of every relevant information data, integrated architecture information model greatly is believed the engineering project correlationThe detailed expression of breath.
In terms of traditional BIM application predominantly stays in BIM Digital Design, can not achieve design, buying, production, construction andThe information realtime interactive of delivery, this causes materials procurement to lag, and production plan cannot be adjusted in real time according to raw materials inventory situationIt is whole, seriously affect the development of construction industry.
Summary of the invention
In view of this, the embodiment of the invention provides a kind of equipment production information management method of assembled architecture platform andDevice, to solve construction industry production process chinese raw materials buying lag in the prior art, production plan cannot be according to raw material storeDeposit the problem of situation adjusts in real time.
The first aspect of the embodiment of the present invention provides a kind of equipment production information management method of assembled architecture platform,The assembled architecture platform includes server, first database, the second database, comprising:
Raw Material Demand amount and the Raw Material Demand time of current production plan are obtained from the first database;
Current raw material store storage is obtained from second database;
Compare the size of the Raw Material Demand amount and the raw material store storage, if the Raw Material Demand amount is greater than instituteRaw material store storage is stated, then generates materials procurement instruction.
The second aspect of the embodiment of the present invention provides a kind of equipment production information management device of assembled architecture platform,The assembled architecture platform includes server, first database, the second database, comprising:
First information acquiring unit, for obtained from the first database current production plan Raw Material Demand amount andThe Raw Material Demand time;
Second information acquisition unit, for obtaining current raw material store storage from second database;
Procurement directive generation unit generates when being greater than current raw material store storage for the former material doses required for producingUnit generates materials procurement instruction.
The third aspect of the embodiment of the present invention provides a kind of terminal device, and the terminal device includes memory, processingDevice and storage in the memory and the computer program that can run on the processor, described in the processor executionThe step of method such as above-mentioned first aspect is realized when computer program.
The fourth aspect of the embodiment of the present invention provides a kind of computer readable storage medium, the computer-readable storageMedia storage has computer program, and the step of the method such as above-mentioned first aspect is realized when the computer program is executed by processorSuddenly.
5th aspect of the embodiment of the present invention provides a kind of computer program product, and the computer program product includesComputer program realizes the step of the method such as above-mentioned first aspect when the computer program is executed by one or more processorsSuddenly.
Existing beneficial effect is the embodiment of the present invention compared with prior art: original of the application based on current production planMaterials demand amount, Raw Material Demand time and current raw material store storage generate materials procurement instruction in real time, much soonerMaterials procurement is carried out, the intelligence degree of the equipment production information management process of assembled architecture platform is improved.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior artNeeded in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention someEmbodiment for those of ordinary skill in the art without any creative labor, can also be according to theseAttached drawing obtains other attached drawings.
Fig. 1 is the assembled architecture platform schematic diagram that the embodiment of the present invention one provides;
Fig. 2 is a kind of reality of the equipment production information management method of assembled architecture platform provided by Embodiment 2 of the present inventionExisting flow diagram;
Fig. 3 is a kind of reality of the equipment production information management method for assembled architecture platform that the embodiment of the present invention three providesExisting flow diagram;
Fig. 4 is a kind of showing for the equipment production information management device for assembled architecture platform that the embodiment of the present invention four providesIt is intended to;
Fig. 5 is a kind of equipment production information management device inventory for assembled architecture platform that the embodiment of the present invention four providesThe schematic diagram of analysis and early warning unit;
Fig. 6 is the schematic diagram for the terminal device that the embodiment of the present invention five provides.
Specific embodiment
In being described below, for illustration and not for limitation, the tool of such as particular system structure, technology etc is proposedBody details, to understand thoroughly the embodiment of the present invention.However, it will be clear to one skilled in the art that there is no these specificThe present invention also may be implemented in the other embodiments of details.In other situations, it omits to well-known system, device, electricityThe detailed description of road and method, in case unnecessary details interferes description of the invention.
It should be appreciated that ought use in this specification and in the appended claims, term " includes " instruction is described specialSign, entirety, step, operation, the presence of element and/or component, but be not precluded one or more of the other feature, entirety, step,Operation, the presence or addition of element, component and/or its set.
It is also understood that mesh of the term used in this description of the invention merely for the sake of description specific embodimentAnd be not intended to limit the present invention.As description of the invention and it is used in the attached claims, unless onOther situations are hereafter clearly indicated, otherwise " one " of singular, "one" and "the" are intended to include plural form.
It will be further appreciated that the term "and/or" used in description of the invention and the appended claims isRefer to any combination and all possible combinations of one or more of associated item listed, and including these combinations.
Embodiment one
Fig. 1 shows assembled architecture platform schematic diagram provided in an embodiment of the present invention, it should be noted that Fig. 1 is only mentionedA kind of specific implementation framework for having supplied the assembled architecture platform, it is contemplated that other can be realized the embodiment of the present inventionThe system architecture of the relative theory of the assembled architecture platform of offer may be used to realize this programme, and therefore, Fig. 1 embodiment mentionsThe specific implementation framework of confession is not used in the restriction present invention herein.
As shown in Figure 1, the assembled architecture platform is around assembled architecture design, Systemizing production and construction in concrete project;It buildsIt builds, structure, electromechanics, built-in integrated and technology, management, industrial integration (referred to as three integrations) integrated needs built,The technologies such as systematicness integrated BIM, internet, Internet of Things, assembled architecture, innovation research and development building+internet platform.The assemblyThe web interface of formula construction platform include Digital Design module, cloud build online shopping module, intelligent plant module, wisdom building site module withAnd happy space module.
The Digital Design module includes project library and component and component part library, and the project library is used for this platform pipeThe all items of reason carry out Classification Management, wherein further include panorama, high building, index bed, project component under each project directoryThe subdirectories such as library and project component library.The all items that the component and component part library are used to manage this platform are usedComponent and component component carry out Classification Management, wherein the component is shown by way of two dimensional code, user can pass through platformTerminal clicks the two dimensional code and carries out the displaying of component material picture, or by two dimensional code described in mobile scanning terminal, is then movingIt is shown in dynamic terminal.The component component is shown by three-dimensional live model image, and user can lead on platform terminalIt crosses mouse to rotate the three-dimensional live model image of the component component, so as to realize that different angle is real to the three-dimensionalScape model image is shown.
It includes that BIM Cost Management submodule and cloud build net module that the cloud, which builds online shopping module, wherein BIM Cost ManagementModule is used to carry out Cost Management to all items of the platform management, and the cost includes civil engineering, steel construction, light currentIntelligent, metal Roof cost.The cloud build net module provided by way of online shopping mall bidding relevant to project,The interface of worker's recruitment, the purchase of component component.User directly can realize online bidding, work by this assembled architecture platformPeople's recruitment and the purchase of component and component.
The intelligent plant module includes PC (prestressed concrete) factory management system, Active Eyes, lifeProduce plan designing system, prefabricated components production information system.The PC factory management system is for providing the office of each factoryThe login interface of system.The Active Eyes is used to transfer the interface of the monitoring camera of different factories, Yong HukeTo select corresponding factory in the Active Eyes of this platform, so that it may the monitoring camera in the factory is called,The production of factory, personnel status are monitored.The production plan designing system is currently being carried out for providing for userProject manufacturing plan sheet is provided, user can carry out plan design by production plan designing system, and by the design sideCase is sent to corresponding responsible party.The prefabricated components production information system is used to carry out the component information of all plant producedsSummarize, user can check the relevant information of component, such as amount of concrete, structure in the prefabricated components production information system of platformPart weight, reinforcing bar volume, reinforcing bar weight, steel content, sleeve number, suspender number, sunpender, screw number, hole count through walls and electricityBox number etc..
Wisdom building site module includes remote monitoring unit, construction quality unit, site safety unit, contract planning listMember, cost accounting unit, component trace-back unit, personal management unit, point cloud scanning element.
The remote monitoring unit is used to carry out video monitoring to the different zones of construction site.The construction quality unitIt is expired not rectify and improve quantity for showing quality related information, such as hidden danger quantity, quantity to be rectified and improved, quantity to be checked and accepted andQuantity is closed, and is classified to the hidden danger according to severity, is classified as major hidden danger, larger hidden danger and general hiddenSuffer from.In this platform, shown by way of histogram by hidden danger that different subcontractors occur is strong.The site safetyFor showing the safety problem in building-site to user by way of chart, for example, by safety problem present in building siteIt is classified as high altitude operation, administration behaviour, falsework, hoisting machinery, four mouthfuls of Triratna, construction equipment, power supply for construction, external scaffoldingAnd civilized construction, and above-mentioned safety problem is shown in the form of cake chart.The contract planning unit for pairContract recruits the preposition pre-control for plan of adopting, and realizes the self energy monitoring for recruiting plan of adopting and task supervisor, it is ensured that and contract is correctly fulfiled, andIt realizes the structured storage recruited and adopt contract, quick search, task supervisor and workflow examination and approval, realizes that data efficient is practical.It is described atThis measuring and calculating unit is realized and is refined to subpackage, goods and materials, machinery, artificial and expense multi-level oil for being associated with project image progressControl, preposition early warning, correction assist business people to carry out whole process supervision to cost control, find risk, and take and accordingly arrangeIt applies, save the cost is generated profit.The component trace back block is realized by the component two dimensional code generated by BIM model to componentIt is traced from the Life cycle of design, production, examination, lifting.Using single component as basic unit body, the full Life Cycle of component is realizedThe information of phase summarizes.With docking BIM light weighed model, the real-time control to building-site progress is realized.By being based on lightweightThe real-time mounting of component progress and model not only may be implemented in the virtual construction of BIM model, and segmentation, subregion carry out, according to colorSubregion carries out progress simulation, also analog information can be associated with PROJECT, carries out target advance and reality by chart and model interactionThe comparison of construction speed deviation is completed in the comparison of border progress.Key node payment plan in expansible docking commerce module simultaneously,Realize the one-to-one correspondence of engineering construction plan and commercial payment plan in engineering key node, the practical branch of the Zhi Fuyu that realizes a planThe real time contrast of the amount of money is paid, realize to the accurate control of cost caused by each node of engineering and provides auxiliary for project administrator and determinesPlan information maximizes.
The personal management unit is big by completion personnel real name system, personnel positioning information, video monitoring information threeThe three-dimensional management to live labor service personnel may be implemented in combination of the data of function on platform.In conjunction with account permissionSetting and critical data summarize, and manager is facilitated to pass through real-time control of the visualized data to live labor service personnel's situation.In conjunction withFront end bio-identification gate system carries out real-time remote monitoring to worker's number on the scene and personal information.Pass through analysis, cross simultaneouslyThe digitization system management to project labor service worker is completed than personal information data.
Described cloud scanning element is scanned by infrared point cloud, it can be achieved that sweeping to completed indoor engineering Centimeter Level qualityIt retouches and is modeled with outdoor scene.Platform database is compared and is uploaded to BIM light weighed model for scanning result simultaneously to put on record,In conjunction with design information, construction deviation report is generated, provides data foundation for Construction Quality report.By the way that cloud scanning knot will be putFruit input database is put on record, in conjunction with information is delivered, can also provide three-dimensional data for the house use of numerals specification of owner.
The happiness space module is based on VR, panoramic virtual reality technology, provides new home delivery, panorama building operation instructionThe services such as book, panorama estate management navigation, panorama building physical examination.The VR and panorama experience sense for supporting mobile terminal are by auxiliary is checked and acceptedHand over room.It supports to identify the key messages such as property present position, surrounding enviroment, room number by mobile terminal barcode scanning, and Gao Pin can be based onIt is made on the basis of matter is visual and selects room decision, select room result that can realize data statistics on platform.It is related during livingArchitectural drawing and household component library may be implemented on-line selection, the information of related maintenance facility may be implemented to visualize online and look intoIt askes.
Embodiment two
It is a kind of equipment production information management method of assembled architecture platform provided by Embodiment 2 of the present invention referring to fig. 2Implementation process schematic diagram, concrete application method of the present embodiment as system described in embodiment one.It is described to be based on assembledThe production management method of construction platform is executed by production management device, and the data production management device is configured at server, canBy software and or hardware realization.
Assembled architecture platform described in the present embodiment includes server, first database and the second database, described one kindThe equipment production information management method of assembled architecture platform is applied to server.It the described method comprises the following steps:
Step S201, when obtaining the Raw Material Demand amount and Raw Material Demand of current production plan from the first databaseBetween;
In the present embodiment, the first database is for storing production plan data, including raw material coding, raw materialDemand, Raw Material Demand time, Raw Material Demand station, operation number, production plan odd numbers and production plan performance numberAccording to the production plan performance data include in not completing, producing, are completed.A production is selected in the present embodimentPlan performance data are unfinished production plan, and are set as current production plan.
Step S202 obtains current raw material store storage from second database;
In the present embodiment, second database is for storing raw material integrated information, including raw material coding, former materialGauge lattice, supplier information, serial code, raw material store storage, raw material geographical location information, entry time and Life Cycle issueAccording to.In the present embodiment, raw material are attached to identifiable identity, and each raw material have unique raw material information textPart, by identifying that the identity can the second database acquisition raw material integrated information.
Further, the file in second database is encoded with raw material and is named.It will be described by read-write equipmentRaw material information file is written in raw material integrated information, and the raw material information file is named with serial code, the raw material letterFile storage to the raw material are ceased to encode in corresponding file.
Preferably, the raw material store storage of raw material needed for the present embodiment only obtains current production plan.
Step S203, the size of the Raw Material Demand amount and the raw material store storage, if the raw material needThe amount of asking is greater than the raw material store storage, then generates materials procurement instruction.
In the present embodiment, the Raw Material Demand that the assembled architecture platform will be got from the first databaseAmount data and the raw material store storage data got from the second database are compared, if per a in current production planThe demand of raw material is respectively less than its quantity in stock and then issues resource allocation instruction and fabrication order, refers to when receiving the resource allocationResource allocation is carried out when enabling, the resource allocation is included in required time and required raw material is assigned to corresponding station before,When receiving the fabrication order, execution unit executes current production plan;If the Raw Material Demand amount data are greater than former materialExpect that then the assembled architecture platform generates procurement directive to inventory data.
Further, the procurement directive generated in step S203 includes the raw material coding and raw material that need to be purchasedAmount of purchase.
Preferably, the materials procurement amount is the Raw Material Demand amount and current raw material store storage of current production planDifference.That is:
Materials procurement amount=current production plan Raw Material Demand amount-raw material store storage
Preferably, the difference of the estimated consumption of the raw material and current quantity in stock is difference A in a procurement cycle P, whenThe difference of the Raw Material Demand amount of preceding production plan and current raw material store storage is difference B, and the materials procurement amount is poorThe greater in value A and difference B.I.e.
Preferably, the procurement cycle P is the average buying hour obtained according to the passing buying hour of the raw material.
Preferably, the procurement directive is pushed to preset buying terminal device.
Preferably, the procurement directive is pushed to relevant procurement staff.
Embodiment three
It is the equipment production information management of one of third embodiment of the invention assembled architecture platform refering to Fig. 3, Fig. 3The implementation process schematic diagram of method.The difference of the present embodiment and second embodiment is, in the present embodiment after step S203It further include S304~S305.S301~S303 particular content in the present embodiment please refers to S201~S203 in second embodimentAssociated description, details are not described herein again.S304~S305 is specific as follows:
Step S304 obtains the raw material time of delivery from the third database;
In the present embodiment, third database is established in the server of the assembled architecture platform, for being stored inWay raw material data.It is described refer in way raw material purchased, but still on order raw material of supplier.The third numberWhat it is according to library storage includes raw material coding, specifications of raw materials, supplier information and time of delivery in way raw material data.The friendshipETCD estimated time of commencing discharging refers to the estimated entry time in way raw material.
The raw material time of delivery is compared step S305 with the Raw Material Demand time, generates and compares knotFruit;
In the present embodiment, after the completion of the procurement directive, the server of assembled architecture platform is by the raw materialTime of delivery is compared with the Raw Material Demand time, generates comparison result.The comparison result represents raw material deliveryWhether the time can satisfy the Raw Material Demand time of current production plan, and the comparison result includes: morning time of deliveryIn the Raw Material Demand time, the time of delivery is later than the Raw Material Demand time but earlier than deadline H and describedTime of delivery is later than deadline H.
Further, step S305 further include:
Step S3051, if the comparison result is the time of delivery earlier than the Raw Material Demand time, basis is worked asPreceding production plan generates production ordering;
Step S3052, if the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than mostSlow time limit H, then take level-one shortage of stock measure;
Step S3053 takes bi- inventory not if the comparison result is the time of delivery to be later than deadline HSufficient measure.
In the present embodiment, the assembled architecture platform if the time of delivery is earlier than the Raw Material Demand timeServer judges current production plan without adjustment, and the assembled architecture Platform Server assigns life to preset terminal deviceInstruction is produced, preset terminal device can be automatically processing device, be also possible to production information issue terminal, and user logs inIt is available after production information issue terminal to arrive production ordering.
Further, the assembled architecture platform can also be under preset terminal device while assigning production orderingIt is instructed up to resource allocation.The resource allocation instruction includes that raw material encode, raw material blending amount, demand station.It is described defaultTerminal device can be raw material blending equipment, be also possible to raw material deployment information issue terminal, user logs in former materialThe available resource allocation that arrives instructs after expecting deployment information issue terminal.
In the present embodiment, if the time of delivery is later than the Raw Material Demand time but earlier than deadline H, instituteIt states assembled architecture Platform Server and judges that raw material supply is not able to satisfy production plan demand, the assembled architecture platform clothesBusiness device takes level-one shortage of stock measure.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate fromRaw material time of delivery at the latest.
Preferably, the level-one shortage of stock measure includes: to generate new production plan.
In the present embodiment, if the time of delivery is later than deadline H, the assembled architecture platform judges former materialMaterial supply is not able to satisfy production plan demand, and the assembled architecture platform takes bi- inventory deficiency measure.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate fromRaw material time of delivery at the latest.
Preferably, the bi- inventory deficiency measure includes: push raw material shortage of goods information to default terminal device.
It should be understood that the size of the serial number of each step is not meant that the order of the execution order in above-described embodiment, each processExecution sequence should be determined by its function and internal logic, the implementation process without coping with the embodiment of the present invention constitutes any limitIt is fixed.
Example IV
It is a kind of equipment production information management device for assembled architecture platform that the embodiment of the present invention four provides referring to fig. 4Schematic diagram, assembled architecture platform described in the present embodiment includes server, first database and the second database, described one kindThe equipment production information management method of assembled architecture platform is applied to server.Described device includes:
First information acquiring unit 401, for obtaining the Raw Material Demand of current production plan from the first databaseAmount and Raw Material Demand time;
Second information acquisition unit 402, for obtaining current raw material store storage from second database;
Procurement directive generation unit 403, when being greater than current raw material store storage for the former material doses required for producingGeneration unit generates materials procurement instruction.
Third information acquisition unit 404, for obtaining the raw material time of delivery from the third database;
Inventory analysis prewarning unit 405, for carrying out the raw material time of delivery and the Raw Material Demand timeIt compares, generates comparison result.
Fig. 5 is a kind of equipment production information management device inventory for assembled architecture platform that the embodiment of the present invention four providesThe workflow schematic diagram of analysis and early warning unit 405, comprising:
If the comparison result is the time of delivery earlier than the Raw Material Demand time, according to current production planGenerate production ordering;
If the comparison result is the time of delivery to be later than the Raw Material Demand time but earlier than deadline H,Take level-one shortage of stock measure;
If the comparison result is the time of delivery to be later than deadline H, bi- inventory deficiency measure is taken.
Preferably, the level-one shortage of stock measure includes: to generate new production plan;
Preferably, the bi- inventory deficiency measure includes: push raw material shortage of goods information to default terminal device.
Preferably, the deadline H be according to the production and operation situation setting from the procurement directive generate fromRaw material time of delivery at the latest.
Embodiment five
Fig. 6 is the schematic diagram for the terminal device that one embodiment of the invention provides.As shown in fig. 6, the terminal of the embodiment is setStandby 6 include: processor 60, memory 61 and are stored in the meter that can be run in the memory 61 and on the processor 60Calculation machine program 62.The processor 60 is realized above-mentioned each based on assembled architecture platform when executing the computer program 62Step in data processing method embodiment, such as step S301 to S305 shown in Fig. 3.Alternatively, the processor 60 executesThe function of each module/unit in above-mentioned each Installation practice, such as module 401 shown in Fig. 4 are realized when the computer program 62To 405 function.
Illustratively, the computer program 62 can be divided into one or more module/units, it is one orMultiple module/units are stored in the memory 61, and are executed by the processor 60, to complete the present invention.Described oneA or multiple module/units can be the series of computation machine program instruction section that can complete specific function, which is used forImplementation procedure of the computer program 62 in the terminal device 6 is described.
The terminal device 6 can be desktop PC, notebook, palm PC, cloud server or server etc.Calculate equipment.The terminal device may include, but be not limited only to, processor 60, memory 61.Those skilled in the art can manageSolution, Fig. 6 is only the example of terminal device 6, does not constitute the restriction to terminal device 6, may include more or more than illustratingFew component perhaps combines certain components or different components, such as the terminal device can also be set including input and outputStandby, network access equipment, bus etc..
Alleged processor 60 can be central processing unit (Central Processing Unit, CPU), can also beOther general processors, digital signal processor (Digital Signal Processor, DSP), specific integrated circuit(Application Specific Integrated Circuit, ASIC), ready-made programmable gate array (Field-Programmable Gate Array, FPGA) either other programmable logic device, discrete gate or transistor logic,Discrete hardware components etc..General processor can be microprocessor or the processor is also possible to any conventional processorDeng.
The memory 61 can be the internal storage unit of the terminal device 6, such as the hard disk or interior of terminal device 6It deposits.The memory 61 is also possible to the External memory equipment of the terminal device 6, such as be equipped on the terminal device 6Plug-in type hard disk, intelligent memory card (Smart Media Card, SMC), secure digital (Secure Digital, SD) card dodgeDeposit card (Flash Card) etc..Further, the memory 61 can also both include the storage inside list of the terminal device 6Member also includes External memory equipment.The memory 61 is for storing needed for the computer program and the terminal deviceOther programs and data.The memory 61 can be also used for temporarily storing the data that has exported or will export.
It is apparent to those skilled in the art that for convenience of description and succinctly, only with above-mentioned each functionCan unit, module division progress for example, in practical application, can according to need and by above-mentioned function distribution by differentFunctional unit, module are completed, i.e., the internal structure of described device is divided into different functional unit or module, more than completingThe all or part of function of description.Each functional unit in embodiment, module can integrate in one processing unit, can alsoTo be that each unit physically exists alone, can also be integrated in one unit with two or more units, it is above-mentioned integratedUnit both can take the form of hardware realization, can also realize in the form of software functional units.In addition, each function listMember, the specific name of module are also only for convenience of distinguishing each other, the protection scope being not intended to restrict the invention.Above systemThe specific work process of middle unit, module, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In the above-described embodiments, it all emphasizes particularly on different fields to the description of each embodiment, is not described in detail or remembers in some embodimentThe part of load may refer to the associated description of other embodiments.
Those of ordinary skill in the art may be aware that list described in conjunction with the examples disclosed in the embodiments of the present disclosureMember and algorithm steps can be realized with the combination of electronic hardware or computer software and electronic hardware.These functions are actuallyIt is implemented in hardware or software, the specific application and design constraint depending on technical solution.Professional technicianEach specific application can be used different methods to achieve the described function, but this realization is it is not considered that exceedThe scope of the present invention.
In embodiment provided by the present invention, it should be understood that disclosed device/terminal device and method, it can be withIt realizes by another way.For example, device described above/terminal device embodiment is only schematical, for example, instituteThe division of module or unit is stated, only a kind of logical function partition, there may be another division manner in actual implementation, such asMultiple units or components can be combined or can be integrated into another system, or some features can be ignored or not executed.SeparatelyA bit, shown or discussed mutual coupling or direct-coupling or communication connection can be through some interfaces, deviceOr the INDIRECT COUPLING or communication connection of unit, it can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unitThe component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multipleIn network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unitIt is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated listMember both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated module/unit be realized in the form of SFU software functional unit and as independent product sale orIn use, can store in a computer readable storage medium.Based on this understanding, the present invention realizes above-mentioned implementationAll or part of the process in example method, can also instruct relevant hardware to complete, the meter by computer programCalculation machine program can be stored in a computer readable storage medium, the computer program when being executed by processor, it can be achieved that onThe step of stating each embodiment of the method.Wherein, the computer program includes computer program code, the computer program generationCode can be source code form, object identification code form, executable file or certain intermediate forms etc..The computer-readable mediumIt may include: any entity or device, recording medium, USB flash disk, mobile hard disk, magnetic that can carry the computer program codeDish, CD, computer storage, read-only memory (Read-Only Memory, ROM), random access memory (RandomAccess Memory, RAM), electric carrier signal, telecommunication signal and software distribution medium etc..It should be noted that the meterThe content that calculation machine readable medium includes can carry out increase and decrease appropriate according to the requirement made laws in jurisdiction with patent practice,Such as in certain jurisdictions, according to legislation and patent practice, computer-readable medium do not include be electric carrier signal and electricityBelieve signal.
Embodiment described above is merely illustrative of the technical solution of the present invention, rather than its limitations;Although referring to aforementioned realityApplying example, invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned eachTechnical solution documented by embodiment is modified or equivalent replacement of some of the technical features;And these are modifiedOr replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution should allIt is included within protection scope of the present invention.