A kind of information management system of road and bridge highway engineering constructionTechnical field
The present invention relates to project management technique field, especially a kind of information management system of road and bridge highway engineering construction.
Background technique
In Process of Engineering Construction, the information such as a large amount of text, chart can be generated, conventional operation mode be by artificial andOrdinary electronic medium is transmitted and is issued.But large-scale road and bridge engineering is built, such as large bridge, highway, tunnel, theyThe building course of real-time Transmission publication in to(for) information has higher requirements, and the management of traditional approach information in this case can go outExisting information transmission tomography, working efficiency is low, office cost is high, low-quality problem.
Currently, to the access of information, form substantially manually to turn over documents is examined by the way of manual recordIt looks into, a large amount of manpower and time cost can be expended, for large enterprise, workload is bigger, and under conventional information management, enterpriseIndustry high level wants to see the output value situation of each month of the project or week, and the related personnel in project will be from level to level to reported dataIt fills in a form lattice, this complicated and time-consuming work.
Summary of the invention
To solve the above-mentioned problems, the present invention provides a kind of information management system of road and bridge highway engineering construction, Neng GouyouEffect improves the efficiency that resource data is consulted, and obtains information in an orderly manner convenient for each department and each position.
To achieve the goals above, the technical solution adopted by the present invention are as follows:
A kind of information management system of road and bridge highway engineering construction, including very three-dimensional engineering model establish module, BIM three-dimensionalModel building module, GIS three-dimensional land map establish module, data inputting module, Data Analysis Services module, three-dimensional engineering modelDisplay module, login module, management platform, task supplementary module and data server,
The BIM three-dimension modeling module is used to establish by BIM threedimensional model of the software to engineering, and willBIM threedimensional model is divided into multiple engineering components, the engineering component and Practical Project position relative to and be able to carry out componentName, material, belonging positions, project amount, cost data input;
The GIS three-dimensional land map establishes module for site contour data by Smart3D software, to be carried out sky three and addedClose calculating generates point cloud data, passes through the actual landform figure in point cloud data fabrication place;
The very three-dimensional engineering model establish module for by the data of the BIM three-dimension modeling module with it is describedThe data that GIS three-dimensional land map establishes module combine, and generate very three-dimensional engineering model;
The data inputting module includes data inputting submodule and data audit submodule, the data inputting submoduleTyping for front man to task related data information, the data audit submodule are used for senior authorAudit to the data inputting submodule number evidence;
The data of the data inputting module are analyzed and processed by the Data Analysis Services module, and with described true threeDimension engineering model establishes module relation and generates the three-dimensional engineering model display module, makes the data of data server and each instituteState the internal control data information on very three-dimensional engineering model described in the corresponding simultaneously real-time update of engineering component and by the three-dimensional engineeringModel display modules exhibit;
The login module includes identification submodule, information classification submodule and authority distribution submodule, the bodyPart identification submodule is used for the pairing according to the account data in the account data and the data server inputted, and judgesThe affiliated function of login account and position;The information classification submodule is according to algorithm for pattern recognition to the three-dimensional engineering modelThe data of display module are classified, and different departments is made to obtain corresponding information;The authority distribution submodule is used forThe job information of login account is judged according to the identification module, and different operating rights is determined to different positions;
The management platform is used to obtain corresponding information in the three-dimensional engineering model display module according to different departments,And the data of the three-dimensional engineering model display module are divided by work management module, long-range by information submodule of classifyingMonitoring submodule, labor management submodule, meeting submodule, testing inspection module and data submodule;
The task supplementary module obtains the construction of the position, construction member of construction member according to the management platformThe information that project, the information of engineering material situation and engineering test require obtains the attention of the course of work by machine learning algorithmThe information of tool needed for the safety equipment dressed needed for item and work and work, by its information feedback to staff;
The data server is used to that the data of the data inputting module and the management platform to be stored and be sent outIt send;
Further, the GIS three-dimensional land map establishes module and obtains site contour data by unmanned plane technology.
Further, the very three-dimensional engineering model establishes module by the way that the GIS three-dimensional land map is established moduleTerrain information is imported in Lumion software and is combined with the threedimensional model of the BIM three-dimension modeling module, is generated very three-dimensionalEngineering model.
It further, further include supervision module, the supervision module includes video acquisition submodule and identification submoduleBlock, the video acquisition submodule is for work needed for shooting the wearing information of front man's safety equipment before setting out and workingHas information;The identification submodule is used to extract the characteristic image of the video acquisition submodule, by the video acquisitionThe characteristic image of submodule is made comparisons with the information of the task supplementary module, and comparison result is fed back to field workPersonnel and the three-dimensional engineering model display module.
Further, the data inputting module further includes template construct module, and the template construct module is used for instituteState the template that data inputting submodule is established and edits data inputting.
Further, the engineering management includes plan editor module and task obtains module, the plan editorModule is used for formulation or adjustment of the corporate executive to engineering project, and is intended to information function in the three-dimensional engineering model exhibitionShow module;The task obtains module and obtains institute by the three-dimensional engineering model display module for front manState the information of plan editor module;
Further, the engineering component is clicked in the three-dimensional engineering model display module obtain the engineering structureThe relevant information of part.
It further, further include chart generating module, the chart generating module is used for according to the Data Analysis ServicesThe data of module generate chart, and the chart generating module and the very three-dimensional engineering model establish module relation, and byThe related letter chart generation that the engineering component obtains the engineering component is clicked in the three-dimensional engineering model display moduleModule.
Further, included the following steps using the approaches to IM of this system,
S1. BIM threedimensional model is established in the BIM three-dimension modeling module according to Practical Project, by BIM threedimensional modelBe divided into multiple engineering components according to Practical Project position, and to the engineering component carry out component name, material, belonging positions,The data input of project amount, cost;
S2. site contour data are obtained by unmanned plane technology, are established in module in the GIS three-dimensional land map,By site contour data by Smart3D software, carries out empty three computations and generate point cloud data, work is made by point cloud dataThe actual landform figure in journey place;
S3. by terrain information import threedimensional model phase with the BIM three-dimension modeling module in Lumion softwareIn conjunction with, and very three-dimensional engineering model is generated in the three-dimensional engineering model display module;
S4. the information classification submodule is by the data of the three-dimensional engineering model display module according to algorithm for pattern recognitionIt is divided into work management module, long-range monitoring submodule, labor management submodule, meeting submodule, testing inspection module and dataSubmodule, and different departments is made to obtain corresponding information;The authority distribution submodule is according to the identification moduleJudge the job information of login account, and determines different operating rights to different positions;
S5. corporate executive clicks engineering component in three-dimensional engineering model display module 4 by identification submodule 51Relative information is obtained, corporate executive, can be according to big number according to the authority distribution submodule permission obtainedAccording to and the three-dimensional engineering model display module in the plan editor module engineering project is formulated;The plan editorThe information of module is sent to the task and obtains module;
S6. front man clicks work in the three-dimensional engineering model display module by the identification submoduleJourney component obtains the information that the task obtains module, and according to requiring to execute work;Front man is described threeDimension engineering model display module clicks the task supplementary module to obtain needed for the points for attention and work of the course of workThe information of tool needed for the safety equipment of wearing and work, and according to requiring to carry out safety equipment wearing and be carried out to toolPrepare, front man by the video acquisition submodule to safety equipment wearing situation and construction tool preparation intoThe characteristic image of the video acquisition submodule and the task are obtained module by row shooting, the identification submoduleInformation make comparisons, when the identification submodule mismatch when, remind worker safety equip wearing it is undesirableInformation and construction tool lacks or the information of mistake and prompt are re-shoot, and comparison result is fed back into the three-dimensional engineeringModel display module;
S7. in the project and type according to engineering in the template construct module making data inputting template, field workThe content that personnel are filled according to needed for the template construct module in data inputting submodule is to task related data informationThe typing of progress;Senior author is in data audit submodule to the data inputting submodule number according to auditing;It examinesAfter core passes through, the data of the data audit submodule are sent to the three-dimensional stage die by the Data Analysis Services moduleOn the correspondence of the type display module engineering component, the chart generating module is raw by the data of the Data Analysis Services moduleAt chart and act on the correspondence engineering component of the three-dimensional engineering model display module;
S8. corporate executive audits submodule in the data that the three-dimensional engineering model display module obtains corresponding departmentThe information of the information of block and the chart generating module, and engineering project is adjusted in plan editor's submodule according to big dataScheme.
The invention has the advantages that
BIM threedimensional model is divided into multiple engineering components, engineering component and practical work by 1.BIM three-dimension modeling moduleJourney position relative to and be able to carry out the data input of component name, material, belonging positions, project amount, cost, module is to engineering structurePart is decomposed, and each module has the label of oneself, facilitates the statistics of 0# account;GIS three-dimensional land map is established module and is passed throughUnmanned plane technology obtains site contour data, and place graphic data is carried out empty three computations by Smart3D softwarePoint cloud data is generated, the actual landform figure in point cloud data fabrication place is passed through.Very three-dimensional engineering model establishes module will be upperIt states the two and the visual information of corporate executive offer is provided, convenient for the acquisition of information.
2. data inputting module makes typing and senior author of the front man to task related data informationAudit to the data inputting submodule number evidence, Data Analysis Services module carry out the data of data inputting module at analysisReason, and the data of data inputting module are assigned on the engineering component according to different engineering components, realize WBS and BIM mouldType mutually maps, and Data Analysis Services module establishes being associated with for module with very three-dimensional engineering model, passes through convenient for corporate executiveData relevant to engineering component are consulted in three-dimensional engineering model display module.Front man can pass through cell phone or meterTyping of the calculation machine to data realizes and does report daily without front man, and the task and data uploaded can substituteReport.Template construct module is used to establish data inputting submodule and edit the template of data inputting, can be according to engineeringDemand modifies the template of data inputting at any time, convenient for the input of the task information of staff.
3. task supplementary module according to management platform obtain the position of construction member, construction member project under construction,The information that the information and engineering test of engineering material situation require obtains the points for attention of the course of work by machine learning algorithmAnd the information of tool needed for the safety equipment dressed needed for work and work;And identification submodule can be by video acquisitionThe information of submodule is compared with the information of task supplementary module, realizes the note to the course of work of front manTool needed for the safety equipment dressed needed for meaning item and work and work exercises supervision, and avoids front man because of workPreceding preparation is insufficient and job schedule is caused to delay and occur during the work time unexpected.
4. chart generating module is used to generate chart according to the data of Data Analysis Services module, chart generating module and trueThree-dimensional engineering model establishes module relation, automatically generates the ability of chart, dramatically saves the time of staff, improvesWorking efficiency, but also can be convenient for grasp of the corporate executive to internal control data.
5. the data of three-dimensional engineering model display module are divided into work management mould under information classification submodule effectBlock, long-range monitoring submodule, labor management submodule, meeting submodule and data submodule, are sentenced by identification submoduleDisconnected institute's login account belongs to some department and its position, to showing information relevant to the department in three-dimensional engineering model exhibitionShow in module, the information acquisition efficiency of user be provided, to the data more refined, facilitate its understand entire project the case where, andAnd avoid because information it is mixed and disorderly due to make miswork.Authority distribution submodule can obtain login account in identification submoduleJob information, and its permission is determined by the job information, if corporate executive is to the letter in three-dimensional engineering model display moduleThe permission with browsing and editor is ceased, front man has browsing power to the information in three-dimensional engineering model display moduleLimit realizes the management for being convenient for engineering construction.
Detailed description of the invention
Fig. 1 is system structure diagram of the invention.
In figure, the very three-dimensional engineering module of 1- establishes module, 11-BIM three-dimension modeling module, and 12-GIS threedimensional model is builtFormwork erection block, 2- data inputting module, 21- data inputting submodule, 22- data audit submodule, 3- Data Analysis Services module,4- three-dimensional engineering model display module, 5- login module, 51- identification submodule, 52- information classification submodule, 53- permissionDistribution sub module, 6- manage platform, 61- work management module, the long-range monitoring submodule of 62-, 63- labor management submodule, 64-Meeting submodule, 65- testing inspection module, 66- data submodule, 7- database server library module, 71- task auxiliaryModule, 711- video acquisition submodule, 712- identification submodule, 8- data server, 9- chart generating module.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, completeSite preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based onEmbodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every otherEmbodiment shall fall within the protection scope of the present invention.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the inventionThe normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description toolThe purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more phasesAny and all combinations of the listed item of pass.
A kind of information management system of road and bridge highway engineering construction, including very three-dimensional engineering model establish module 1, BIM tri-Dimension module establishes module 11, GIS three-dimensional land map establishes module 12, data inputting module 2, Data Analysis Services module 3, three-dimensionalEngineering model display module 4, login module 5, management platform 6, task supplementary module 7 and data server 8.
BIM three-dimension modeling module 11 by BIM threedimensional model of the software to engineering for being established, and by BIMThreedimensional model is divided into multiple engineering components, engineering component and Practical Project position relative to and be able to carry out component name, material,The data input of belonging positions, project amount, cost.In the present embodiment, BIM three-dimension modeling module 11 by Revit orPerson's CATIA software establishes the BIM threedimensional model of engineering.
GIS three-dimensional land map establishes module 12 for site contour data by Smart3D software, to be carried out sky three and encryptedIt calculates and generates point cloud data, pass through the actual landform figure in point cloud data fabrication place.In the present embodiment, GIS is dimensionallyShape figure establishes module 12 and obtains site contour data by unmanned plane technology.
Very three-dimensional engineering model is established module 1 and is used for the data of BIM three-dimension modeling module 11 and GIS dimensional topographyThe data that figure establishes module 12 combine, and generate very three-dimensional engineering model.In the present embodiment, very three-dimensional engineering model establishes mouldBlock 1 by GIS three-dimensional land map is established module 12 terrain information import lumion or fuzor software in BIM three-dimensional mouldThe threedimensional model that type establishes module 11 combines, and generates very three-dimensional engineering model.
BIM threedimensional model is divided into multiple engineering components, engineering component and practical work by BIM three-dimension modeling module 11Journey position relative to and be able to carry out the data input of component name, material, belonging positions, project amount, cost.GIS dimensional topographyFigure establishes module 12 and obtains site contour data by unmanned plane technology, and place graphic data is passed through Smart3D softwareIt carries out empty three computations and generates point cloud data, pass through the actual landform figure in point cloud data fabrication place.Very three-dimensional engineeringBoth above-mentioned combine is capable of providing visual information by model building module 1, convenient for the acquisition of information.
Data inputting module 2 includes that data inputting submodule 21 and data audit submodule 22, data inputting submodule 21Typing for front man to task related data information, data audit submodule 22 and are used for senior author coupleThe audit of 21 data of data inputting submodule.The data of front man institute typing need to audit by senior authorThe process that just can be carried out next step avoids causing because of input error, and data generate biggish difference, avoids top management peopleMember obtains the information of inaccuracy, increases the workload of corporate executive indirectly.Template construct module 23 is used for data inputtingModule 21 is established and the template of editor's data inputting.Template construct module 23 can modify at any time data record according to the demand of engineeringThe template entered, convenient for the input of the task information of staff.
In the present embodiment, front man and senior author can carry out data by cell phone or computerTyping or data audit realize that front man and senior author can outdoors or indoor carry out data making a report on or countingAccording to examination & approval, increase the flexibility of system, improve working efficiency, realize and do report daily without front man,The task and data of upload can substitute report.
The data of data inputting module 2 are analyzed and processed by Data Analysis Services module 3, and with very three-dimensional engineering modelIt establishes the association of module 1 and generates three-dimensional engineering model display module 4, keep the data of data server 7 corresponding with each engineering componentAnd it data information on the very three-dimensional engineering model of real-time update and is shown by three-dimensional engineering model display module 4.Data analysisProcessing module 3 can position according to engineering component and project, the data of data inputting module 2 are assigned to each engineering componentOn, related data and the field work people of engineering component are obtained in three-dimensional engineering model display module 4 convenient for corporate executiveMember obtains task scheduling information.In the present embodiment, engineering component is clicked in three-dimensional engineering model display module 4 obtain the workThe relevant information of journey component realizes the visualization of data.
Login module 5 includes identification submodule 51, information classification submodule 52 and authority distribution submodule 53, identityIdentification submodule 51 is used for the pairing according to the account data in the account data and data server 7 inputted, and judges to step onRecord affiliated function and the position of account;Information classification submodule 52 is according to algorithm for pattern recognition to three-dimensional engineering model display module4 data are classified, and different departments is made to obtain corresponding information;Authority distribution submodule 53 according to identity for knowingOther module 51 judges the job information of login account, and different operating rights is determined to different positions.
Management platform 6 is used to obtain corresponding information in three-dimensional engineering model display module 4 according to different departments, and passes throughThe data of three-dimensional engineering model display module 4 are divided into work management module 61, remotely monitor submodule by information classification submodule 52Block 62, labor management submodule 63, meeting submodule 64, testing inspection module 65 and data submodule 66.
Data server 8 is used to that the data of data recording module 2 and management platform 6 to be stored and be sent.
In the present embodiment, engineering management 61 includes plan editor module 62 and task obtains module 63, and plan is compiledIt collects module 62 and is used for formulation or adjustment of the corporate executive to engineering project, and be intended to information function in three-dimensional engineering model exhibitionShow module 4;Task obtains module 63 and is compiled for front man by three-dimensional 4 acquisition plan of engineering model display moduleCollect the information of module 62.
Long-range monitoring submodule 62 by scene of the camera to engineering construction for being monitored, by clicking engineering structureLong-range monitoring submodule 62 in part can be monitored the field condition of corresponding engineering component, and corporate executive is made to implement the palmThe case where holding construction site.
Labor management submodule 63 passes through the letter of 2 module of data inputting module in reception data server 8 for Human Resources DepartmentBreath, to obtain the working condition of front man and tension management person, thus according to the information pair of 2 module of data inputting moduleFront man and tension management person carry out attendance.
Meeting submodule 64 passes through multimedia equipment and carries out video conference.
Testing inspection module 65 obtains relevant information data for experiment position.
For data submodule 66 for the information in called data server 8, corporate executive can be from immediate data server 8The basic information of called data recording module 2, it is not necessary to relevant information be understood by multilayer relationship, be enable to understand in timeWith solution relevant issues.
In the case where information classification submodule 52 acts on, the data of three-dimensional engineering model display module 4 are divided into work management mouldBlock 61, long-range monitoring submodule 62, labor management submodule 63, meeting submodule 64,65 data submodule of testing inspection module66, judge that institute's login account belongs to some department and its position by identification submodule 52, thus will be related to the departmentInformation be shown in three-dimensional engineering model display module 4, the information acquisition efficiency of user is provided, to the data more refined,Facilitate its understand entire project the case where, and avoid because information it is mixed and disorderly due to make miswork.53 energy of authority distribution submoduleIt is enough to obtain the job information of login account in identification submodule 51, and its permission is determined by the job information, such as high-rise pipeReason person has the permission of browsing and editor to the information in three-dimensional engineering model display module, and front man is to three-dimensional workInformation in journey model display module has browse right, realizes the management for being convenient for engineering construction.
Task supplementary module 7 according to management platform 6 obtain the position of construction member, construction member project under construction,The information that the information and engineering test of engineering material situation require obtains the points for attention of the course of work by machine learning algorithmAnd the information of tool needed for the safety equipment dressed needed for work and work, by its information feedback to staff.
It further include supervision module 71, supervision module 71 includes video acquisition submodule 711 and identification submodule 712,Video acquisition submodule 711 is for shooting the wearing information of front man's safety equipment before setting out and work outfit letterBreath;Identification submodule 712 is used to extract the characteristic image of video acquisition submodule 711, by video acquisition submodule 711Characteristic image is made comparisons with the information of task supplementary module 7, and comparison result is fed back to front man and three-dimensionalEngineering model display module 4
Task supplementary module 7 obtains the position of construction member, the project under construction of construction member, work according to management platformThe information that the information and engineering test of journey material context require by the points for attention of the machine learning algorithm acquisition course of work andThe information of tool needed for the safety equipment dressed needed for work and work;And identification submodule 712 can adopt videoThe information of collection submodule 711 is compared with the information of task supplementary module 7, is realized to the worked of front manTool needed for the safety equipment dressed needed for the points for attention and work of journey and work exercises supervision, and avoids front manBefore work preparation it is insufficient due to cause job schedule to delay and occur during the work time unexpected.
Before front man's work, according to information provided by task supplementary module 7, dress needed for workTool needed for safety equipment and carrying work, passes through video acquisition submodule 711 respectively, and identification submodule 712 extractsThe characteristic image of video acquisition submodule 711 is simultaneously made comparisons with the information of task supplementary module 7, when it fails to match, prisonIt superintends and directs module 71 and issues prompt information to front man, and front man is required to shoot again to this information,The information that it fails to match is sent three-dimensional engineering model display module 4 by supervision module 7 simultaneously, so that corporate executive understands oneThe case where preparing before Workers work, to formulate suitable Managed Solution according to the information of preparation before working.
Chart generating module 9 be used for according to the data of Data Analysis Services module 3 generate chart, chart generating module 9 withVery three-dimensional engineering model establishes the association of module 1, and should by clicking engineering component acquisition in three-dimensional engineering model display module 4The related letter chart generating module 8 of engineering component.Chart generating module 8 is established module 1 with very three-dimensional engineering model and is associated with, fromThe dynamic ability for generating chart, dramatically saves the time of staff, improves work efficiency, but also can be convenient for high levelGrasp of the manager to data.
Included the following steps using the approaches to IM of this system,
S1. BIM threedimensional model is established in BIM three-dimension modeling module 11 according to Practical Project, by BIM threedimensional model rootFactually engineering position in border is divided into multiple engineering components, and to engineering component carry out component name, material, belonging positions, project amount,The data input of cost;
S2. site contour data are obtained by unmanned plane technology, is established in module 12 in GIS three-dimensional land map, it willSite contour data carry out empty three computations and generate point cloud data, pass through point cloud data fabrication by Smart3D softwareThe actual landform figure in place;
S3. by terrain information import in Lumion software and mutually tied with the threedimensional model of BIM three-dimension modeling module 11It closes, and generates very three-dimensional engineering model in three-dimensional engineering model display module 4;
S4. the data of three-dimensional engineering model display module 4 are divided by information classification submodule 52 according to algorithm for pattern recognitionWork management module 61, long-range monitoring submodule 62, labor management submodule 63, meeting submodule 64, testing inspection module 65And data submodule 66, and different departments is made to obtain corresponding information;Authority distribution submodule 53 is according to identification mouldBlock 51 judges the job information of login account, and different operating rights is determined to different positions;
S5. corporate executive clicks engineering component in three-dimensional engineering model display module 4 by identification submodule 51Relative information is obtained, corporate executive, can be according to big data according to the permission obtained of authority distribution submodule 53And three-dimensional engineering model display module 4 formulates engineering project in plan editor module 62;Plan the letter of editor module 62Breath is sent to task and obtains module 63;
S6. front man clicks engineering structure in three-dimensional engineering model display module 4 by identification submodule 51Part obtain task obtain module 63 information, and according to require execute work;Front man is in three-dimensional engineering modelDisplay module 4 clicks task supplementary module 7 to obtain the safety dress dressed needed for the points for attention of the course of work and workThe information of tool needed for standby and work, and dress and tool is prepared, a line work according to requiring to carry out safety equipmentMake personnel and safety equipment wearing situation and construction tool preparation are shot by video acquisition submodule 711, identifiesComparative sub-module 712 makes comparisons the characteristic image of video acquisition submodule 711 with the information that task obtains module 63, whenWhen identification submodule 712 mismatches, reminds worker safety to equip and dress undesirable information and construction toolLack or the information of mistake and prompt are re-shoot, and comparison result is fed back into three-dimensional engineering model display module 4;
S7. data inputting template, field work people are being made in template construct module 23 according to the project and type of engineeringThe content that member is filled according to needed for template construct module 23 in data inputting submodule 21 to task related data information intoCapable typing;Senior author audits 21 data of data inputting submodule in data audit submodule 22;Audit passes throughAfterwards, the data of data audit submodule 22 are sent to pair of three-dimensional engineering model display module 4 by Data Analysis Services module 3It answers on engineering component, the data of Data Analysis Services module 3 are generated chart and act on three-dimensional stage die by chart generating module 9On the corresponding engineering component of type display module 4;
S8. corporate executive obtains the data audit submodule 22 of corresponding department in three-dimensional engineering model display module 4The information of information and chart generating module 9, and engineering project scheme is adjusted in plan editor's submodule 62 according to big data.
In the present invention, front man includes testing crew, store keeping personnel, construction manager.Test peopleDaily test mission progress and test related data are carried out typing by data inputting module 21 by member.Store keeping personnel are logicalIt crosses data inputting module 21 and daily material disengaging situation is subjected to typing.Construction manager will be every by data inputting moduleIt construction speed and associated schedule information carries out typing.
And senior author corresponding with testing crew, store keeping personnel, construction manager passes through upper managementPerson's terminal 221 respectively audits the information of each position front man institute typing.
When audit passes through, the information of 3 called data server 8 of Data Analysis Services module, and with needle three-dimensional stage dieType establishes the association of module 1, and corporate executive can be obtained in three-dimensional engineering model display module 4 by logging in management platform 6The information of corresponding position.Corporate executive is right in plan editor's submodule 612 according to the information of three-dimensional engineering model display module 4Work plan is formulated or is adjusted.Front man obtains module in the task of three-dimensional engineering model display module 4612 obtain related work mission bit stream, thereby executing task.