The city integrated piping lane construction total management system of cast-in-place structuralTechnical field
Applied the present invention relates to Urban Underground pipe gallery technical field of construction, more particularly to the city integrated piping lane of cast-in-place structuralWork total management system, it is adaptable to the work progress management of the cast-in-place pipe gallery in city and similar long range underground engineering.
Background technology
Urban Underground pipe gallery project has been studied mainly for piping lane at present in the existing certain hour of China's developmentPlanning, design, operation, delivery phase, for the work progress of city integrated piping lane, at present still in the incipient stage.ExistingDuring some pipe galleries are built, administrative staff are mainly original and are engaged in municipal administration, the administrative staff of architectural engineering, for pipe galleryConstruction, still continue to use municipal administration, the management method of architectural engineering, be not particularly suited for the construction of underground pipe gallery, particularly the duration compared withTightly, in the case that operating personnel, construction machinery, material input amount are huge, conventional progress, quality, safety, store keeping method withoutMethod meets the demand of field management.In this case it is desirable to propose a kind of new management process, a set of new management body is set upSystem, to adapt to the construction of Urban Underground pipe gallery, reduces management cost, improves management quality.
The content of the invention
The problem that the purpose of the present invention exists aiming at prior art, there is provided the city integrated piping lane construction of cast-in-place structural is comprehensiveManagement system is closed, by clear and definite procedure, the management method of standardization, progress, matter in pipe gallery work progress is overcomeThe extensive shortcoming of amount, management of safe operation, efficiently succinct completion piping lane work progress management work.
The object of the present invention is achieved like this:The city integrated piping lane construction total management system of cast-in-place structural, including it is comprehensiveClose Pipe rack to decompose, Planning of construction periods typing, the analysis of required resource quantity, typing, issue construction plan, daily condition of construction withTrack, typing, duration early warning, resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;SecondThe structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not completeInto the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation peopleMember, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progressManagement, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing systemSystem;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustmentIn the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Compared with prior art, it is an advantage of the invention that:Live progress, quality, safety management efficiency are effectively improved, is reducedConstruction cost.
Brief description of the drawings
Fig. 1:The city integrated piping lane construction total management system flow chart of cast-in-place structural
Flow is made according to Task-decomposing, schedule requirement, operating procedure in figure.
Specific embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As described in Figure, the city integrated piping lane construction total management system of cast-in-place structural, including comprehensive pipe gallery structure is decomposed, workPhase plans typing, and construction plan is issued in required resource quantity analysis, typing, and daily condition of construction is tracked, typing, duration early warning,Resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;SecondThe structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not completeInto the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation peopleMember, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progressManagement, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing systemSystem;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustmentIn the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Lanzhou new district underground pipe gallery project, using management process of the invention, is assisted using computer software, is realizedLess administrative staff manage large-scale piping lane engineering.Using the present invention, live progress, quality, safety management effect can be effectively improvedRate, advantageously reduces construction cost, with good economic benefit and social benefit.