CN106875159A - The city integrated piping lane construction total management system of cast-in-place structural - Google Patents

The city integrated piping lane construction total management system of cast-in-place structural
Download PDF

Info

Publication number
CN106875159A
CN106875159ACN201710085131.8ACN201710085131ACN106875159ACN 106875159 ACN106875159 ACN 106875159ACN 201710085131 ACN201710085131 ACN 201710085131ACN 106875159 ACN106875159 ACN 106875159A
Authority
CN
China
Prior art keywords
construction
typing
resource
duration
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710085131.8A
Other languages
Chinese (zh)
Inventor
吴建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co LtdfiledCriticalChina MCC17 Group Co Ltd
Priority to CN201710085131.8ApriorityCriticalpatent/CN106875159A/en
Publication of CN106875159ApublicationCriticalpatent/CN106875159A/en
Pendinglegal-statusCriticalCurrent

Links

Classifications

Landscapes

Abstract

The invention discloses the city integrated piping lane construction total management system of cast-in-place structural, decomposed including comprehensive pipe gallery structure, Planning of construction periods typing, required resource quantity analysis, typing, issue construction plan, daily condition of construction tracking, typing, duration early warning, resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:1), comprehensive pipe gallery structure is decomposed;2), Planning of construction periods typing;3), required resource quantity analysis, typing;4) construction plan, is issued;5), daily condition of construction tracking, typing;6), duration early warning;7), resource adjustment, node time limit modification;8), closed loop, summary.It is an advantage of the invention that effectively improving live progress, quality, safety management efficiency, construction cost is reduced.

Description

The city integrated piping lane construction total management system of cast-in-place structural
Technical field
Applied the present invention relates to Urban Underground pipe gallery technical field of construction, more particularly to the city integrated piping lane of cast-in-place structuralWork total management system, it is adaptable to the work progress management of the cast-in-place pipe gallery in city and similar long range underground engineering.
Background technology
Urban Underground pipe gallery project has been studied mainly for piping lane at present in the existing certain hour of China's developmentPlanning, design, operation, delivery phase, for the work progress of city integrated piping lane, at present still in the incipient stage.ExistingDuring some pipe galleries are built, administrative staff are mainly original and are engaged in municipal administration, the administrative staff of architectural engineering, for pipe galleryConstruction, still continue to use municipal administration, the management method of architectural engineering, be not particularly suited for the construction of underground pipe gallery, particularly the duration compared withTightly, in the case that operating personnel, construction machinery, material input amount are huge, conventional progress, quality, safety, store keeping method withoutMethod meets the demand of field management.In this case it is desirable to propose a kind of new management process, a set of new management body is set upSystem, to adapt to the construction of Urban Underground pipe gallery, reduces management cost, improves management quality.
The content of the invention
The problem that the purpose of the present invention exists aiming at prior art, there is provided the city integrated piping lane construction of cast-in-place structural is comprehensiveManagement system is closed, by clear and definite procedure, the management method of standardization, progress, matter in pipe gallery work progress is overcomeThe extensive shortcoming of amount, management of safe operation, efficiently succinct completion piping lane work progress management work.
The object of the present invention is achieved like this:The city integrated piping lane construction total management system of cast-in-place structural, including it is comprehensiveClose Pipe rack to decompose, Planning of construction periods typing, the analysis of required resource quantity, typing, issue construction plan, daily condition of construction withTrack, typing, duration early warning, resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;SecondThe structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not completeInto the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation peopleMember, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progressManagement, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing systemSystem;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustmentIn the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Compared with prior art, it is an advantage of the invention that:Live progress, quality, safety management efficiency are effectively improved, is reducedConstruction cost.
Brief description of the drawings
Fig. 1:The city integrated piping lane construction total management system flow chart of cast-in-place structural
Flow is made according to Task-decomposing, schedule requirement, operating procedure in figure.
Specific embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As described in Figure, the city integrated piping lane construction total management system of cast-in-place structural, including comprehensive pipe gallery structure is decomposed, workPhase plans typing, and construction plan is issued in required resource quantity analysis, typing, and daily condition of construction is tracked, typing, duration early warning,Resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;SecondThe structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not completeInto the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation peopleMember, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progressManagement, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing systemSystem;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustmentIn the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Lanzhou new district underground pipe gallery project, using management process of the invention, is assisted using computer software, is realizedLess administrative staff manage large-scale piping lane engineering.Using the present invention, live progress, quality, safety management effect can be effectively improvedRate, advantageously reduces construction cost, with good economic benefit and social benefit.

Claims (1)

CN201710085131.8A2017-02-172017-02-17The city integrated piping lane construction total management system of cast-in-place structuralPendingCN106875159A (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN201710085131.8ACN106875159A (en)2017-02-172017-02-17The city integrated piping lane construction total management system of cast-in-place structural

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN201710085131.8ACN106875159A (en)2017-02-172017-02-17The city integrated piping lane construction total management system of cast-in-place structural

Publications (1)

Publication NumberPublication Date
CN106875159Atrue CN106875159A (en)2017-06-20

Family

ID=59166117

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN201710085131.8APendingCN106875159A (en)2017-02-172017-02-17The city integrated piping lane construction total management system of cast-in-place structural

Country Status (1)

CountryLink
CN (1)CN106875159A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN108755757A (en)*2018-06-292018-11-06上海二十冶建设有限公司Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery
CN109299924A (en)*2018-10-192019-02-01杭州数建科技有限公司Fining and intelligent project management method based on multistage control
CN109636675A (en)*2018-12-122019-04-16上海荷福人工智能科技(集团)有限公司A kind of management method and system of the construction site based on artificial intelligence
CN109741090A (en)*2018-12-182019-05-10刘雨昆It is a kind of based on multifactor distribution engineering material needing forecasting method
CN110443480A (en)*2019-07-262019-11-12中铁四局集团第一工程有限公司Construction progress monitoring and early warning method and system
CN110766292A (en)*2019-09-292020-02-07广船国际有限公司 A scheduling method, device, equipment and storage medium for ship segmented resources
CN110930044A (en)*2019-11-292020-03-27伍知行Construction organization resource rapid configuration method and system
CN111027803A (en)*2019-11-012020-04-17国艺天成建设工程技术有限公司Construction management method and construction management system
CN112541742A (en)*2020-12-212021-03-23宁良武Building construction progress management method
CN113935853A (en)*2021-10-292022-01-14广东三扬网络科技有限公司Production progress tracking management method, module, system and storage medium
CN116128273A (en)*2023-04-172023-05-16清云小筑(北京)创新技术有限公司Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint
CN117196161A (en)*2022-01-052023-12-08陕西克林维尔信息科技有限公司Municipal engineering management method, municipal engineering management device, computer readable storage medium and server

Citations (4)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN104484524A (en)*2014-12-092015-04-01张家驰Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN104766182A (en)*2015-04-302015-07-08北京宁晖兴业科技有限公司Intelligent monitoring system for building design construction based on BIM
CN105512822A (en)*2015-12-142016-04-20国家电网公司Construction progress management method based on visualization technology
CN106339490A (en)*2016-08-312017-01-18铁道第三勘察设计院集团有限公司System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN104484524A (en)*2014-12-092015-04-01张家驰Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN104766182A (en)*2015-04-302015-07-08北京宁晖兴业科技有限公司Intelligent monitoring system for building design construction based on BIM
CN105512822A (en)*2015-12-142016-04-20国家电网公司Construction progress management method based on visualization technology
CN106339490A (en)*2016-08-312017-01-18铁道第三勘察设计院集团有限公司System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨峰: "城市地下市政综合管廊施工方法初步探讨与分析", 《安徽建筑》*

Cited By (13)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN108755757A (en)*2018-06-292018-11-06上海二十冶建设有限公司Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery
CN109299924A (en)*2018-10-192019-02-01杭州数建科技有限公司Fining and intelligent project management method based on multistage control
CN109636675A (en)*2018-12-122019-04-16上海荷福人工智能科技(集团)有限公司A kind of management method and system of the construction site based on artificial intelligence
CN109741090A (en)*2018-12-182019-05-10刘雨昆It is a kind of based on multifactor distribution engineering material needing forecasting method
CN110443480B (en)*2019-07-262023-10-27中铁四局集团第一工程有限公司Construction progress monitoring and early warning method and system
CN110443480A (en)*2019-07-262019-11-12中铁四局集团第一工程有限公司Construction progress monitoring and early warning method and system
CN110766292A (en)*2019-09-292020-02-07广船国际有限公司 A scheduling method, device, equipment and storage medium for ship segmented resources
CN111027803A (en)*2019-11-012020-04-17国艺天成建设工程技术有限公司Construction management method and construction management system
CN110930044A (en)*2019-11-292020-03-27伍知行Construction organization resource rapid configuration method and system
CN112541742A (en)*2020-12-212021-03-23宁良武Building construction progress management method
CN113935853A (en)*2021-10-292022-01-14广东三扬网络科技有限公司Production progress tracking management method, module, system and storage medium
CN117196161A (en)*2022-01-052023-12-08陕西克林维尔信息科技有限公司Municipal engineering management method, municipal engineering management device, computer readable storage medium and server
CN116128273A (en)*2023-04-172023-05-16清云小筑(北京)创新技术有限公司Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint

Similar Documents

PublicationPublication DateTitle
CN106875159A (en)The city integrated piping lane construction total management system of cast-in-place structural
CN109710990B (en)BIM technology-based roller compacted concrete dam construction progress-cost cooperative control method
CN103136612A (en)Development method of zero-coding component-based flow business
CN104573892A (en)Whole process visual project management system for engineering construction
CN105989419A (en)Investment correction and optimization method for engineering project of intelligent power distribution network
CN116562802A (en)Intelligent construction application platform of track traffic based on BIM
Belyakova et al.Management strategy for regional labor market (case of the Krasnoyarsk krai)
CN104331779A (en)Development area construction project management system and method
He et al.Visual-language reasoning segmentation (LARSE) of function-level building footprint across Yangtze River Economic Belt of China
CN110083989B (en)Safety data monitoring method in pipe gallery underground excavation engineering based on BIM technology
CN111476697A (en)Wisdom road network integrated management platform
Kenley et al.Location Breakdown Structure (LBS): a solution for construction project management data redundancy
Shivasami et al.Early implementation of BIM in large infrastructure projects to manage complex interfaces in a dense urban environment
Jia et al.Setting scheduled trip time based on AVL data
CN110232469A (en)A kind of all kinds of minimum optimization methods of project organization plan resource of critical path method
Cameron et al.An environmental impact assessment for hydropower development in China
Liu et al.Application practice of code mapping technology in hydropower project construction management system
Ma et al.A dynamic programming model for bus signal priority with multiple requests
Park et al.A study on the Information for the Schedule Management of the Construction based BIM
Cai et al.Applying Deep Learning and High-Resolution Data to Predict Crashes for Transportation Safety Planning
Song et al.A Research on Enhancing Aviation Safety Culture by Building the Level of Safety Awareness
Kośmieja et al.Flexible designing of a road infrastructure example
He et al.Reflection on Intelligent Construction Based on BIM: Take a Residential Building as an Example
KrechetovThe IIIrd international innovative mining symposium at TF Gorbachev kuzbass state technical university as a step to closer cooperation of science, education and business in the mining region
Yao et al.Hybrid Cycle-Based Volume Estimation Method for Signalized Intersections Based on Sampled Trajectory Data

Legal Events

DateCodeTitleDescription
PB01Publication
PB01Publication
SE01Entry into force of request for substantive examination
SE01Entry into force of request for substantive examination
RJ01Rejection of invention patent application after publication

Application publication date:20170620