A kind of embankment transverse drainage construction method
Download PDF

Info

Publication number
CN105256684B
CN105256684BCN201510565242.XACN201510565242ACN105256684BCN 105256684 BCN105256684 BCN 105256684BCN 201510565242 ACN201510565242 ACN 201510565242ACN 105256684 BCN105256684 BCN 105256684B
Authority
CN
China
Prior art keywords
moisture content
soakaway trench
embankment
construction
rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510565242.XA
Other languages
Chinese (zh)
Other versions
CN105256684A (en
Inventor
马玉伟
苗双全
徐春广
喻慧
贾长海
秦敬敏
汪志彬
党小红
李丽
任亚军
王光涛
姜帅
温丽娜
夏青
李红旗
赵路遥
陈锐
张彩丽
魏娟
周小飞
盛云超
吴强
刘长红
陈伟
李冶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Wanli Transportation Technology Group Co., Ltd.
Original Assignee
Henan Wanli Road&bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Wanli Road&bridge Group Co LtdfiledCriticalHenan Wanli Road&bridge Group Co Ltd
Priority to CN201510565242.XApriorityCriticalpatent/CN105256684B/en
Publication of CN105256684ApublicationCriticalpatent/CN105256684A/en
Application grantedgrantedCritical
Publication of CN105256684BpublicationCriticalpatent/CN105256684B/en
Activelegal-statusCriticalCurrent
Anticipated expirationlegal-statusCritical

Links

Landscapes

Abstract

The present invention relates to embankment drainage system field, specifically related to there is pit in highway pavement, cracking, differential settlement, rainwater in fracture and embankment, during the phenomenons such as the rainwater that capillary water and median strip can not be drained completely, a kind of embankment transverse drainage construction method without excavating and can be recycled, according to embankment moisture content and degree of disease, determine soakaway trench position, soakaway trench is installed in drilling, three-dimensional porous resin filter element is set in soakaway trench, hole mouthful is sealed, site clearing after construction, embankment moisture content is monitored after a period of time again, method of the present invention easy construction, cycle is short, engineering cost is low.

Description

A kind of embankment transverse drainage construction method
Technical field
The present invention relates to embankment drainage system field, and in particular to highway pavement occur pit, cracking, differential settlement,It is a kind of without excavating during the phenomenons such as the rainwater that fracture and the rainwater in embankment, capillary water and median strip can not be drained completelyAnd the embankment transverse drainage construction method that can be recycled.
Background technology
With the fast development continued to develop with traffic science technology of communication, the quality and quantity of highway is all being carriedHeight, while also increasingly pay attention to the drainage works of highway, the also more and more higher of the requirement to it.And traditional roadbed transverse drainageFacility, is the setting transverse drainage duct at roadbed top, to discharge the infiltration of median strip collected, this drainage pattern withoutMethod solves to pass through the moisture that median strip, earth shoulder, side slope etc. have been seeped into inside embankment, can not also discharge wet soft section roadCapillary water in dike;Also there is the push pipe mode using no-dig technique to construct now, draining effect duration after draining, but its constructionShort, often the water after the time of 1 year or so in drainpipe just can not discharge the drainpipe, it is necessary to more renew, cost due to blockingIt can therewith increase, also increase the workload of road maintenance workman.
The content of the invention
There is provided a kind of without excavating and recyclable making it is an object of the invention to overcome the deficiencies in the prior artEmbankment transverse drainage construction method.
The technical proposal of the invention is realized in this way:
A kind of embankment transverse drainage construction method, it is characterised in that construction method is as follows:
Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling branch frame railRoad, drill bit, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, according toCheck evaluation criterion, is detected to construction material, carries out aperture record, is bored before PVC-U pipes move into job site thereonGo out the hole of " product " font or " rice " font, aperture is 2.5mm, and infiltration is played in whole work progress;Wherein, described inspectionThe qualified examining report and ocular estimate that the third party for testing evaluation criteria to be provided by manufacturer goes out evidence are examined, and described three-dimensional is moreHole resin filter element is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, the moisture content of analysis embankment isThe no optimum moisture content regional higher than detection and " disease " degree for observing road surface, described optimum moisture content represent soil in maximumIts corresponding moisture content during dry density, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, uses percentage tableShow;Described road surface " disease " is seriously road surface long-term existence frost boiling phenomenon or 0.5cm~1cm crack, pit occurs;
Step 3), positioning:According to step one)The analysis of middle embankment moisture content and the observation of road surface " disease ", it is determined that constructionLocation, the position of soakaway trench, if embankment moisture content is higher than 60% -75% and the road surface " disease " of the optimum moisture content in detection areaSeriously, then soakaway trench every setting horizontal 20m together;If embankment moisture content higher than the regional optimum moisture content of detection 60%-75% and without road surface " disease ", then soakaway trench every setting horizontal 30m -50m together;
Step 4), it is in place:Construction machinery needed for construction is stopped in place, the mechanical car that will be loaded with hanging device stopsThe construction point determined is leaned against, mechanical kickstand is fixed, starts loop wheel machine, rig traveling bracket track is lifted to the road chosenRoadside Po Chu, and rigging up traveling bracket track, the horizontal fix bar of rig traveling bracket track are pinned with latch closure, in rig rowThe both sides for entering bracket track hit real upper silk with drill rod screw rod, prevent that rig traveling work progress medium-height trestle track from occurring tilting, shakingIt is dynamic, finally with horizon rule to rig traveling bracket track it is horizontal, vertically carry out leveling;
Rig lays steady in place, and the drilling rod used by rig arranges placement, soakaway trench, three-dimensional porous resin filter element by numberIt is smooth to place, meanwhile, generating set, drill bit, the supporting placement of drilling rod of numbering, borehole trajectory are fixed;
Step 5), drilling:Drill bit is installed, drilling rod in order of numbers is installed, starter-generator group trial operation rig,Rig normal operation then starts in construction, work progress every 5min-10min cleanings once miscellaneous soil, and tight in work progressTaboo is added water, it is to avoid roadbed is soaked by water, and structure is destroyed, wherein described drill bit is D90mm drill bit;
Step 6), soakaway trench, three-dimensional porous resin filter element configuration:According to soakaway trench selected in advance from three-dimensional porousResin filter element, internal diameter small 10mm-20mm of the diameter than soakaway trench of three-dimensional porous resin filter element, three-dimensional porous resin filter element is includedIn in soakaway trench, and length is identical with infiltration length of tube;
Step 7), install soakaway trench, three-dimensional porous resin filter element:Soakaway trench, three-dimensional are selected into hole length according to drilling rodPorous resin filter core, installs the soakaway trench of a caliber caliber bigger than soakaway trench at away from hole mouthful 0.5m, wherein, described infiltrationThe pipe for D90mm or D110mm is managed, the pipe of a corresponding big caliber is D100mm or D120mm pipe, the pipe work of a big caliberFor the sealer between hole and soakaway trench, by soakaway trench jacking hole;
Step 8), closing:Hole is made into Seal treatment with mortar or C15 concretes;Wherein, the proportioning of every cube of mortar isCement:Sand:Water=242:1655:270, the proportioning of every cube of C15 concretes is cement:Sand:Water:Stone=185:247:768:1200;
Step 9), cleaning job site:After hole closing terminates, the construction rubbish of cleaning job site, dismounting machinery,Bracket track, is moved to next hole position and continues to construct;
Step 10), embankment moisture content is detected after two weeks to one month again, such as moisture content is less than the optimal of detection area and containedWater rate, then engineering terminate;Optimum moisture content such as moisture content higher than detection area, then according to step 2)Again continue with.
Step one)Described in medium grained sand for particle diameter be more than 0.25mm granular mass exceed gross mass 50% sand.
Step one)Described in mixing water be drinking water.
The positive effect of the present invention is:1st, have a wide range of application, filled out suitable for Expressway Embankment, median strip and heightThe national highway and provincial highway of side;
2nd, easy construction, the cycle is short;Traditional drainage construction, which sets up support with steel pipe, needs 2h, and bracket track integration is onlyNeed 55min;Total engineering time shortens 1.5h than conventional construction method;
3rd, traffic will not be blocked, greenery patches vegetation is not destroyed;
4th, engineering cost is low, and three-dimensional porous resin filter element can filter the impurity in draining, reaches permanence operation, whenBetween longer cost advantage it is more obvious;And in traditional drainage and construction method, the steel pipe for setting up support weares and teares meeting constantly for a long timeReduce, the congestion of tubing all can be cost increase.
Brief description of the drawings
Fig. 1 is the process chart of the present invention.
Embodiment
As shown in figure 1, a kind of embankment transverse drainage construction method, it is characterised in that construction method is as follows:
Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling branch frame railRoad, drill bit, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, mixIt is drinking water with water, medium grained sand is 50% sand of the granular mass more than gross mass that particle diameter is more than 0.25mm, according to test evaluationStandard, is detected to construction material, carries out aperture record, and " product " word is got out thereon before PVC-U pipes move into job siteThe hole of type or " rice " font, aperture is 2.5mm, and infiltration is played in whole work progress;Wherein, described test evaluation markStandard is examined for the qualified examining report and ocular estimate that the third party that is provided by manufacturer goes out evidence, and described three-dimensional porous resin is filteredCore is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, the moisture content of analysis embankment isThe no optimum moisture content regional higher than detection and " disease " degree for observing road surface, described optimum moisture content represent soil in maximumIts corresponding moisture content during dry density, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, uses percentage tableShow;Described road surface " disease " is seriously road surface long-term existence frost boiling phenomenon or 0.5cm~1cm crack, pit occurs;
Step 3), positioning:According to step one)The analysis of middle embankment moisture content and the observation of road surface " disease ", it is determined that constructionLocation, the position of soakaway trench, if embankment moisture content is tight higher than 60% -75% and the road surface " disease " of the regional optimum moisture content of detectionWeight, then soakaway trench is every one of setting horizontal 20m;If 60% -75% of embankment moisture content higher than the regional optimum moisture content of detectionAnd without road surface " disease ", then soakaway trench is every one of setting horizontal 30m -50m;
Step 4), it is in place:Construction machinery needed for construction is stopped in place, the mechanical car that will be loaded with hanging device stopsThe construction point determined is leaned against, mechanical kickstand is fixed, starts loop wheel machine, rig traveling bracket track is lifted to the road chosenRoadside Po Chu, and rigging up traveling bracket track, the horizontal fix bar of rig traveling bracket track are pinned with latch closure, in rig rowThe both sides for entering bracket track hit real upper silk with drill rod screw rod, prevent that rig traveling work progress medium-height trestle track from occurring tilting, shakingIt is dynamic, finally with horizon rule to rig traveling bracket track it is horizontal, vertically carry out leveling;
Rig lays steady in place, and the drilling rod used by rig arranges placement, soakaway trench, three-dimensional porous resin filter element by numberIt is smooth to place, meanwhile, generating set, drill bit, the supporting placement of drilling rod of numbering, borehole trajectory are fixed;
Step 5), drilling:Drill bit is installed, drilling rod in order of numbers is installed, starter-generator group trial operation rig,Rig normal operation then starts in construction, work progress every 5min-10min cleanings once miscellaneous soil, and tight in work progressTaboo is added water, it is to avoid roadbed is soaked by water, and structure is destroyed, wherein described drill bit is D90mm drill bit;
Step 6), soakaway trench, three-dimensional porous resin filter element configuration:According to soakaway trench selected in advance from three-dimensional porousResin filter element, internal diameter small 10mm-20mm of the diameter than soakaway trench of three-dimensional porous resin filter element, three-dimensional porous resin filter element is includedIn in soakaway trench, and length is identical with infiltration length of tube;
Step 7), install soakaway trench, three-dimensional porous resin filter element:Soakaway trench, three-dimensional are selected into hole length according to drilling rodPorous resin filter core, installs the pipe of a caliber caliber bigger than soakaway trench at away from hole mouthful 0.5m, wherein, described soakaway trench isD90mm or D110mm pipe, the pipe of a corresponding big caliber is D100mm or D120mm pipe, and the pipe of a big caliber is used as holeSealer between hole and soakaway trench, by soakaway trench jacking hole;
Step 8), closing:Hole is made into Seal treatment with mortar or C15 concretes;Wherein, the proportioning of every cube of mortar isCement:Sand:Water=242:1655:270, the proportioning of every cube of C15 concretes is cement:Sand:Water:Stone=185:247:768:1200;
Step 9), cleaning job site:After hole closing terminates, the construction rubbish of cleaning job site, dismounting machinery,Bracket track, is moved to next hole position and continues to construct;
Step 10), embankment moisture content is detected after two weeks to one month again, such as moisture content is less than the optimal of detection area and containedWater rate, then engineering terminate;Optimum moisture content such as moisture content higher than detection area, then according to step 2)Again continue with.

Claims (3)

Step one), construction material prepare:Construction machinery includes dry drilling machine, generating set, rig traveling bracket track, brillHead, auger stem, soakaway trench, three-dimensional porous resin filter element, mixing water, PC32.5 bagged cements, medium grained sand, are commented according to inspectionCalibration is accurate, and construction material is detected, carries out aperture record, is got out before PVC-U drainpipes move into job site thereonThe hole of " product " font or " rice " font, aperture is 2.5mm, and infiltration is played in whole construction;Wherein, described test evaluationStandard is examined for the qualified examining report and ocular estimate that the third party that is provided by manufacturer goes out evidence, described three-dimensional porous resinFilter core is made up of plastic core body outer wrap filter cloth and has filtering function;
Step 2), the inspection of the scene of a crime:The inspection of the scene of a crime is carried out before construction, embankment moisture content is detected, whether the moisture content for analyzing embankment is highIn detection area optimum moisture content and observe " disease " degree on road surface, described optimum moisture content represents that soil is close in maximum dryIts corresponding moisture content when spending, is the ratio of the weight with the weight of moisture in soil Yu dry ground particle, is expressed as a percentage;InstituteIt is seriously road that " disease " degree on the road surface stated, which includes road surface " disease " serious without road surface " disease " and road surface " disease ", described,There is 0.5cm~1cm crack, pit in face long-term existence frost boiling phenomenon;
CN201510565242.XA2015-09-082015-09-08A kind of embankment transverse drainage construction methodActiveCN105256684B (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN201510565242.XACN105256684B (en)2015-09-082015-09-08A kind of embankment transverse drainage construction method

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN201510565242.XACN105256684B (en)2015-09-082015-09-08A kind of embankment transverse drainage construction method

Publications (2)

Publication NumberPublication Date
CN105256684A CN105256684A (en)2016-01-20
CN105256684Btrue CN105256684B (en)2017-07-11

Family

ID=55096600

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN201510565242.XAActiveCN105256684B (en)2015-09-082015-09-08A kind of embankment transverse drainage construction method

Country Status (1)

CountryLink
CN (1)CN105256684B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN108978502A (en)*2018-08-132018-12-11朱晓颖A kind of induction type roadbed transverse drainage construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
DE4313221C2 (en)*1993-04-221995-08-17Flowtex Service Ges Fuer Horiz Process for laying underground collecting pipes for liquids and gases, in particular for building horizontal filter wells and drainage pipes, and tools for carrying out the process
JP2001172951A (en)*1999-12-212001-06-26Nippon Concrete Ind Co LtdSeepage water drainage structure and its construction method
JP2006194044A (en)*2005-01-172006-07-27Ohbayashi CorpInstallation method for water drain pipe in toe of slope on back of levee body, water draining method for seepage water on back of levee body, and water drain structure for seepage water
CN101748734A (en)*2008-12-042010-06-23中国二十冶建设有限公司Foundation pit side slope sandy soil drainage method
CN204510192U (en)*2014-12-302015-07-29重庆市永川区老科学技术工作者协会Double-level Reticulated eye gutter
CN104727319B (en)*2015-04-072016-05-11兰州理工大学A kind of side slope is from drainage anchor rod and construction method

Also Published As

Publication numberPublication date
CN105256684A (en)2016-01-20

Similar Documents

PublicationPublication DateTitle
CN109881694A (en)A kind of constructing structure blocked for foundation pit substrate Sand and method
Zhou et al.Engineering issues on karst
CN103410564B (en)A kind of Tunnel Gushing treatment structures and construction method thereof
CN107761495A (en)A kind of pre-buried expanding bag compensation subgrade settlement construction method
Ou et al.Hydrogeological analysis and remediation strategies for water inrush hazards in highway karst tunnels
CN105220590A (en)Many karst collapses roadbed injecting treatment method
CN105908588A (en)Permeable pavement system for weakly-permeable soil regions
CN111424702A (en)Integrated water drainage pipe structure and construction method
CN116377780A (en) Construction Method of High Fill Subgrade in Mountainous Highway
Luo et al.Investigation on evolution mechanism and treatment of invert damage in operating railway tunnels under heavy rainfall
CN113235340A (en)Method for treating bump at bridge head by expanding and jacking transverse lead hole
CN210238157U (en)Plateau permafrost region high-speed railway roadbed structure
CN208982109U (en) A tunnel structure with anti-seepage and drainage function
CN105256684B (en)A kind of embankment transverse drainage construction method
CN119711520A (en) A method for supporting thick soft rock slope in open pit mine
Chopra et al.Construction and maintenance assessment of pervious concrete pavements
CN206859091U (en)A kind of coarse-grained soil high-fill roadbed discharge structure
Chopra et al.Pervious pavement systems in Florida—Research results
CN106703013A (en)Water-proof curtain for treating built loess roadbed subsidence damages
JP4060497B2 (en) Roadbed material and roadbed structure with excellent strength and water permeability
Kropp et al.Field wetting tests on a collapsible soil fill
CN110924380A (en)Mountain area high-speed pavement accumulated water treatment construction method based on anchor rod drilling technology
Liu et al.Rainfall Infiltration under Various Building Layouts Using Concrete Microseepage Wells
AhmadkhaniInvestigation of movement of rain water in railway track ballast and subballast layers
CN115030165B (en)Under-penetration highway structure for ultra-shallow buried tunnel and construction method

Legal Events

DateCodeTitleDescription
C06Publication
PB01Publication
C10Entry into substantive examination
SE01Entry into force of request for substantive examination
CB03Change of inventor or designer information

Inventor after:Ma Yuwei

Inventor after:Ren Yajun

Inventor after:Wang Guangtao

Inventor after:Jiang Shuai

Inventor after:Wen Lina

Inventor after:Xia Qing

Inventor after:Li Hongqi

Inventor after:Zhao Luyao

Inventor after:Chen Rui

Inventor after:Zhang Caili

Inventor after:Wei Juan

Inventor after:Miao Shuangquan

Inventor after:Zhou Xiaofei

Inventor after:Sheng Yunchao

Inventor after:Wu Qiang

Inventor after:Liu Changhong

Inventor after:Chen Wei

Inventor after:Li Ye

Inventor after:Xu Chunguang

Inventor after:Yu Hui

Inventor after:Jia Changhai

Inventor after:Qin Jingmin

Inventor after:Wang Zhibin

Inventor after:Dang Xiaohong

Inventor after:Li Li

Inventor before:Ma Yuwei

Inventor before:Li Li

Inventor before:Ren Yajun

Inventor before:Wang Guangtao

Inventor before:Jiang Shuai

Inventor before:Wen Lina

Inventor before:Xia Qing

Inventor before:Li Hongqi

Inventor before:Zhao Luyao

Inventor before:Chen Rui

Inventor before:Zhang Caili

Inventor before:Miao Shuangquan

Inventor before:Wei Juan

Inventor before:Zhou Xiaofei

Inventor before:Sheng Yunchao

Inventor before:Wu Qiang

Inventor before:Miao Zhijie

Inventor before:Xia Junjie

Inventor before:Xu Chunguang

Inventor before:Yu Hui

Inventor before:Jia Changhai

Inventor before:Qin Jingmin

Inventor before:Ding Yifei

Inventor before:Dang Xiaohong

CB03Change of inventor or designer information
GR01Patent grant
GR01Patent grant
CP03Change of name, title or address

Address after:461000 Yongchang West Road, Xuchang City, Henan Province

Patentee after:Henan Wanli Transportation Technology Group Co., Ltd.

Address before:461000 Lunan, East Section of North Ring West Road, Xuchang City, Henan Province

Patentee before:HENAN WANLI ROAD&BRIDGE GROUP CO., LTD.

CP03Change of name, title or address

[8]ページ先頭

©2009-2025 Movatter.jp