CN104481398A - Three-dimensional (3D) horizontal well drilling construction method - Google Patents

Three-dimensional (3D) horizontal well drilling construction method
Download PDF

Info

Publication number
CN104481398A
CN104481398ACN201410758293.XACN201410758293ACN104481398ACN 104481398 ACN104481398 ACN 104481398ACN 201410758293 ACN201410758293 ACN 201410758293ACN 104481398 ACN104481398 ACN 104481398A
Authority
CN
China
Prior art keywords
well
drilling
section
drill
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410758293.XA
Other languages
Chinese (zh)
Other versions
CN104481398B (en
Inventor
闫吉曾
胡冠
邓红琳
屈玉凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Engineering Technology Research Institute Of North China Branch china Petroleum & Chemical Corp
China Petroleum and Chemical Corp
Original Assignee
Engineering Technology Research Institute Of North China Branch china Petroleum & Chemical Corp
China Petroleum and Chemical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Engineering Technology Research Institute Of North China Branch china Petroleum & Chemical Corp, China Petroleum and Chemical CorpfiledCriticalEngineering Technology Research Institute Of North China Branch china Petroleum & Chemical Corp
Priority to CN201410758293.XApriorityCriticalpatent/CN104481398B/en
Publication of CN104481398ApublicationCriticalpatent/CN104481398A/en
Application grantedgrantedCritical
Publication of CN104481398BpublicationCriticalpatent/CN104481398B/en
Activelegal-statusCriticalCurrent
Anticipated expirationlegal-statusCritical

Links

Classifications

Landscapes

Abstract

The invention discloses a three-dimensional (3D) horizontal well drilling construction method, and belongs to the technical field of oil and gas well drilling. According to the method, a directional inclined well section is four sectioned; the 3D angle building variable-azimuth well section drilling build-up rate of a second section and the two-dimensional angle building variable-azimuth well section drilling build-up rates of a first section and a fourth section are identical, so that the technical shortages that tool build-up rates need to be adjusted usually for the reason that build-up rates in the traditional construction method are changed continuously and pulling out of a hole and drilling down are performed frequently are overcome; meanwhile, the angle building variable-azimuth well section turning direction tool face angle of the second section is a constant all the time, and the time and construction amount to put a tool face are saved. By the construction method disclosed by the invention, well drilling and directional construction are performed conveniently; the heterogeneous reservoir shooting probability is improved; the traditional drilling tool equipment is used, the construction time in the same case can be shorted by above 25%; the construction efficiency is greatly improved; the construction difficulty is reduced; the construction costs are reduced by above 17%; the costs are greatly reduced; the construction method is suitable for actual production.

Description

A kind of three-dimensional horizontal well drilling construction method
Technical field
The invention belongs to oil natural gas drilling technology field, be specifically related to a kind of three-dimensional horizontal well drilling construction method.
Background technology
In petroleum gas technical field; in order to improve reservoir development degree; save well site land area, protection of the environment and reduce drilling cost; sometimes three-dimensional well rail drill well construction is carried out; in platform cluster horizontal well deployment, in order to improve individual well draining (gas) area, each individual well horizontal segment is parallel to each other; this just needs to carry out three-dimensional well track construction, and difficulty of construction is large.And for the oil gas field that the deposition of effluent runner as DaNiuDi gas field, oil field, Red River and Jing He oil field is formed, reservoir heterogeneity is strong, A target spot accurately lands difficulty, and its difficulty of construction is extremely difficult especially.
At present a set of more successful construction method also be there is no for the three-dimensional borehole track of heterogeneous reservoir horizontal well, the experience with on-the-spot drilling engineer mostly, be mainly manifested in several aspect: (1) borehole track is generally according to inclined plane method or cylinder helix method design, tool face azimuth is in real time in change, and pendulum tool-face consumes plenty of time and energy; (2) instrument build angle rate constantly changes along with the change of hole angle, constantly adjusts instrument build angle rate, makes a trip often, drilling well timeliness is low, easily borehole well instability occurs; (3) due to the non-homogeneity of reservoir, " feel unsure of " in landing mission, in work progress, there is blindness, easily cause missing the target; (4) in the directed work progress of kickoff point (KOP), directional bearing generally based on experience value, is turned round orientation to follow-up three-dimensional and is caused extreme difficulties.
From North China branch company Ordos Basin drilling practice, the traditional third generation deviating and directing tool system of current employing completes construction well depth about the 2500m of the three-dimensional borehole track of heterogeneous reservoir horizontal well, extended horizontal depth 600 ~ 800m, roughly need more than 30 days, engineering time is long, and construction works amount is large; Adopt forth generation orientation system, i.e. rotary steerable drilling system, construction realizes real-time inspection and control, and the engineering time is short, but only this every day, construction expended more than 20 ten thousand yuan, cost is high, be unfavorable for the actual use of oil field at home oil (gas) drilling well, and adopt third generation phasing tools system, orientation expended and was only about 20,000 yuan day every day, be only about 1/10th of forth generation orientation system, therefore study card and develop a kind of employing conventional drilling equipment.The three-dimensional horizontal well drilling construction method of tradition directional orientation tool system, is significant to the development of China's oil gas extraction technology.
Summary of the invention
In order to overcome the defect of prior art, the object of the present invention is to provide a kind of three-dimensional horizontal well drilling construction method based on conventional drilling equipment, traditional directional orientation tool system, realize constructing safely and fast, saving construction works amount, raising time availability, and cost-saving in a large number, enter under subsequent casings, completion pressure break and oil recovery provide qualified well.
To achieve these goals, the technical solution used in the present invention is as follows:
A kind of three-dimensional horizontal well drilling construction method, comprises following operating procedure:
1) straight well section drilling well;
2) deviated directional drilling section drilling well, its sequence of construction is: the drilling well of first paragraph two dimension build section, the drilling well of second segment three-dimensional increasing hole angle variable-azimuth well section, the 3rd section of steady lower curved section drilling well of two dimension, the 4th section of two-dimentional build section drilling well; Wherein second segment three-dimensional increasing hole angle variable-azimuth well section drilling well build angle rate, first paragraph two dimension build section drilling well build angle rate, the 4th section of two-dimentional build section build angle rate are all identical; Second segment increasing hole angle variable-azimuth well section is turned round tool face azimuth, orientation and is remained constant;
3) directed horizontal segment drilling well.
The outside diameter that described straight well section wellbore construction adopts is of a size of 311.2mm.
The outside diameter that described deviated directional drilling section wellbore construction and directed horizontal segment wellbore construction adopt is of a size of 215.9mm.
Short of 100 ~ 150m is often crept into next time, circulating fluid, until return out landwaste content lower than 0.2% in described deviated directional drilling section wellbore construction process.
Short of 200 ~ 250m is often crept into next time, circulating fluid, until return out landwaste content lower than 0.2% in described directed horizontal segment wellbore construction process.
During described first paragraph two dimension increasing hole angle section wellbore construction, according to initial drift azimuth and the tool-face angle swing tool-face of design, control drill speed 45 ~ 55r/min larger than screw speed, discharge capacity is 29 ~ 31L/s, add the pressure of the drill 2 ~ 4 tons, after creeping into 1 post, increasing the pressure of the drill is 14 ~ 16 tons, stop boring until creep into the maximum hole angle place of two-dimentional borehole track, maximum hole angle controls between 10 ~ 45 °.
The mode that described first paragraph two dimension increasing hole angle section wellbore construction adopts oriented sliding drilling well to combine with combined drilling.
During described second segment three-dimensional increasing hole angle variable-azimuth well section wellbore construction, according to design tool face angle swing tool-face, control drill speed 35 ~ 45r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, add the pressure of the drill 14 ~ 16 tons, creep into and terminate to turning round orientation, at the end of turning round orientation, maximum hole angle is between 45 ~ 85 °.
Further, during the section construction of described second segment three-dimensional increasing hole angle variable-azimuth well, a deviational survey is often crept into once.
During described 3rd section of two-dimentional steady tilted section wellbore construction, control drill speed 50 ~ 60r/min larger than screw speed, discharge capacity is 30 ~ 33L/s, adds the pressure of the drill 14 ~ 16 tons.
During described 3rd section of two-dimentional steady tilted section wellbore construction, the vertical depth according to the First terminal point of logging data real-time estimate borehole track changes, and determines steady tilted section segment length, carries out steady tilted section wellbore construction.
During described 4th section of two-dimentional increasing hole angle section wellbore construction, control drill speed 45 ~ 55r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, adds the pressure of the drill 6 ~ 8 tons, until borehole track A target spot place, control errors vertical skew 0 ~ 1 meter, crosstrall 0 ~ 10 meter.
Described A target spot is the horizontal segment starting point of borehole track.
The drilling well of described straight well section comprise following operating procedure:
1) dig the round well of dark 2.5 ~ 3m, diameter 2 ~ 2.5m, under enter a circular metal bucket, annular space sealing;
2) the top drilling well of straight well section is carried out;
3) drilling well of straight well pars infrasegmentalis is carried out.
At least large than the well control equipment external diameter 0.3m of described circular metal bucket internal diameter.
During described straight well section top wellbore construction, control drill speed is 90 ~ 95r/min, and discharge capacity is 40L/s, add the pressure of the drill 2 ~ 4 tons, creep into one and offer meter well depth, stop creeping into, well-flushing, layer sleeve pipe stays 0.5 ~ 1m pocket and carries out cementing operation, and cementing operation terminates rear Hou Ning 8 ~ 13h.
Described one opens as the top drilling well of straight well section.
Above-mentioned well-flushing maintains wellbore stability for adding weighted cement, and circulation well cleanup is to returning out without obvious particle.
During described straight well pars infrasegmentalis wellbore construction, control drill speed 55r/min larger than screw speed, discharge capacity is 30 ~ 35L/s, and when brill cement and stratum interface, the pressure of the drill controls at 2 ~ 3 tons, after drill collar or heavy weight drill pipe all enter new stratum, the pressure of the drill controls at 6 ~ 8 tons, until kickoff point (KOP).
Further, during above-mentioned straight well pars infrasegmentalis wellbore construction, each post tilts once, if hole deviation and horizontal well displacement are within the scope of designing requirement, continue drilling well to kickoff point (KOP), if hole deviation and horizontal well displacement be not within the scope of designing requirement, carry out well straightening drilling well to kickoff point (KOP).
Described directed horizontal segment wellbore construction is for carry out directed two-dimensional level section wellbore construction until borehole track second terminal from borehole track First terminal point, control drill speed 40 ~ 45r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, add the pressure of the drill 6 ~ 8 tons, well track dog-leg degree is no more than 3 °/30m; Control drilling fluid dehydration < 5ml, drilling liquid flow sex index is 0.4 ~ 0.7, and ratio of dynamic shear force/yield value to plastic viscosity is 0.36 ~ 0.55, coefficient of viscosity < 0.06.
Drilling assembly used in above-mentioned work progress is PDC drill bit+single bend PDM+non magnetic drill collar+measurement while drilling instrument+centralizer+drill collar+heavy weight drill pipe+common drilling rod.
Described PDC drill bit wing >=5; Centralizer external diameter is outside diameter extremely when young 3mm comparatively; Drilling rod and heavy weight drill pipe newly spend for one-level and more than.
The three-dimensional horizontal well drilling construction method of the present invention, deviated directional drilling section adopts four sections of systems, second segment three-dimensional increasing hole angle variable-azimuth well section drilling well build angle rate, first paragraph two dimension build section drilling well build angle rate, the 4th section of two-dimentional build section build angle rate are all identical, overcome build angle rate in conventional construction method process constantly to change, constantly adjust instrument build angle rate, the technological deficiency made a trip often; Meanwhile, second segment increasing hole angle variable-azimuth well section is turned round tool face azimuth, orientation and is remained constant, avoids pendulum time of expending of tool-face and construction works amount.Construction method of the present invention, drilling well and directed easy construction, improve target probability in heterogeneous reservoir, adopt traditional drilling tool equipment, construction can be completed at about 20 days, significantly improve efficiency of construction, reduce difficulty of construction, construction can be saved and expend 70 ~ 900,000 yuan, substantial saving in cost, be suitable for actual production and use.
The three-dimensional horizontal well drilling construction method of the present invention, is particularly useful for horizontal segment and adopts Ф 81/2 " the three-dimensional horizontal well construction of secondary casing programme.
Accompanying drawing explanation
Fig. 1 is the vertical planing surface schematic diagram of embodiment 1 borehole track;
Fig. 2 is embodiment 1 and conventional two-dimensional level well rate of penetration comparison diagram;
Fig. 3 is embodiment 1 and conventional two-dimensional level well drilling period comparison diagram;
Fig. 4 is the present embodiment 1 drilling period distribution map.
Detailed description of the invention
Below in conjunction with specific embodiment, the present invention is described in further detail, but does not form any limitation of the invention.
Embodiment 1
The present embodiment is with the three-dimensional horizontal well of Jing He oil field a bite heterogeneous reservoir for construction object, and adopt ZJ40 rig, drive without top, as shown in Figure 1, wherein A target spot is the horizontal segment starting point of borehole track to the vertical planing surface figure of borehole track; B target spot is the end point of borehole track, and drilling assembly is " PDC drill bit+single bend PDM+non magnetic drill collar+measurement while drilling instrument+centralizer+drill collar+heavy weight drill pipe+common drilling rod ".
The three-dimensional horizontal well construction method of the present embodiment is: concrete operation step is:
1) correct rotating disk, overhead traveling crane, well head three central point on same plumb line, error is less than 5 millimeters;
2) dig what a dark 2.8 meters, the round well of diameter 3.2 meters, under enter a circular metal bucket, annular space cement concrete carries out sealing;
3) one dimension straight well section top wellbore construction is carried out, outside diameter is of a size of 311.2mm, control drill speed is 90 ~ 95r/min, and discharge capacity is 40L/s, adds the pressure of the drill 2 ~ 4 tons, drill the soft layer of Quaternary system loess and enter diagenesis stratum vertical depth 100 meters, well depth 351.6m, stop creeping into and maintaining wellbore stability with weighted mud, circulation well cleanup is till vibrosieve returns out without obvious solid phase particles, setting of casing also carries out cementing operation, and cement slurry 22.1m is used in well cementation3, for slurry 12.9m3, cement paste proportion average out to 1.83, cement paste returns out ground cementing operation to be terminated, Hou Ning 13 hours, and pressure testing is qualified;
4) one dimension straight well pars infrasegmentalis wellbore construction is carried out, outside diameter is of a size of 215.9mm, control drill speed 55r/min larger than screw speed, discharge capacity is 30 ~ 35L/s, when brill cement and stratum interface, the pressure of the drill controls at 2 ~ 3 tons, the pressure of the drill is all entered behind new stratum at 6 ~ 8 tons until drill collar, each root deviational survey once, if hole deviation and horizontal movement are within the scope of designing requirement, continue to creep into kickoff point (KOP), if hole deviation and horizontal well displacement be not within the scope of designing requirement, carrying out well straightening creeps into until kickoff point (KOP), kickoff point (KOP) place hole angle is less than 2 degree, kickoff point (KOP) well depth 929m,
5) the first paragraph two dimension build section wellbore construction of deviated directional drilling section is carried out, outside diameter is of a size of 215.9mm, according to initial orientation drift azimuth and tool-face angle swing tool-face, tool face azimuth error is within ± 1 degree, then rotating disk is locked, spud in well pump, control drill speed 45 ~ 55r/min larger than screw speed, discharge capacity is 29 ~ 31L/s, add the pressure of the drill 2 ~ 4 tons, after drilling well 1 post, increasing the pressure of the drill is 14 ~ 16 tons, oriented sliding drilling well is adopted to combine with combined drilling, stop boring until creep into the maximum hole angle place of two-dimentional borehole track, vertical depth 1183.01m, maximum hole angle is 37.75 °.
6) second segment carrying out deviated directional drilling section is three-dimensional increasing hole angle variable-azimuth well section wellbore construction, first carry out circulation of drilling fluid and remove landwaste, after termination of pumping, according to design tool face angle swing tool-face, tool face azimuth error is within ± 1 degree, locking rotating disk slipping drilling, build angle rate is identical with second segment two dimension build section, outside diameter is of a size of 215.9mm, according to design tool face angle swing tool-face, locking rotating disk slipping drilling, control drill speed 35 ~ 45r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, add the pressure of the drill 14 ~ 16 tons, often creep into single stopping and drill through MWD measurement depth, hole angle and azimuth, creep into and terminate to turning round orientation, at the end of turning round orientation, maximum hole angle is 65.13 °, well depth 1522m.
7) carry out the 3rd section of deviated directional drilling section for the steady lower curved section wellbore construction of two dimension, the vertical depth change according to logging data real-time estimate A target spot is carried out, and determines steady tilted section segment length 136m, carries out steady tilted section construction, well depth 1658.2m at the end of construction; Outside diameter is of a size of 215.9mm, and control drill speed 50 ~ 60r/min larger than screw speed, discharge capacity is 30 ~ 33L/s, adds the pressure of the drill 14 ~ 16 tons.
8) carry out the 4th section of deviated directional drilling section for two-dimentional build section wellbore construction, bit contour is of a size of 215.9mm, and control drill speed 45 ~ 55r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, adds the pressure of the drill 6 ~ 8 tons, until A target spot; Control errors is vertical skew 0 ~ 1 meter, and crosstrall 0 ~ 10 meter, A target spot is dark 1845m tiltedly, hole deviation 90.24 °, 358.96 °, azimuth, vertical depth 1476.84m, and closed apart from 596.36m, direction of closure 16.38m, transfer 3.70m, advance 0.02m, target center is apart from 3.70m.
9) two-dimensional level section wellbore construction is carried out, until creep into B target spot, pull out of hole, outside diameter is of a size of 215.9mm, and control drill speed 40 ~ 45r/min larger than screw speed, discharge capacity is 28 ~ 30L/s, adds the pressure of the drill 6 ~ 8 tons; B target spot is dark 2604m, vertical depth 1466.23m tiltedly, horizontal segment length 750m, hole deviation 89.87 °, 0 °, azimuth, and closed apart from 1332.93m, advance 0.72m, transfer 0.46m, target center is apart from 0.86m; The dog-leg degree of well track is no more than 3 °/30m.
Embodiment 1 drilling well 21 days consuming time to the whole work progress of B target spot, as shown in Figure 4, and the dark 2280m of a bite drilling well adopting conventional construction method to construct, the three-dimensional horizontal well of horizontal segment length 550m, the engineering time needs 28.5 days, therefore compares traditional three-dimensional horizontal well drilling method, the inventive method shortens drilling period 7.5 days, improve wellbore construction efficiency, take saving 52.5 ten thousand yuan rig day, significantly reduce construction cost.
Contrast river, footpath in 2014 two-dimensional level well well data, as shown in Figures 2 and 3, two-dimensional level well average well depth 2160.01m is implemented in oil field, river, footpath in 2014, average rate of penetration 8.87m/h, average drilling period 30.26 days, embodiment 1 is comparing two-dimensional level well many drilling depths 443.99m, and three-dimensional horizontal well construction difficulty comparatively two-dimensional level well is more in situation, rate of penetration is 11.09m/h, improves 25.03%, drilling period 21 days, shortens 30.60%.
It should be noted last that: above embodiment is the non-limiting technical scheme of the present invention in order to explanation only, although with reference to above-described embodiment to invention has been detailed description, those of ordinary skill in the art is to be understood that; Still can modify to the present invention or equivalent replacement, and not depart from any modification or partial replacement of the spirit and scope of the present invention, it all should be encompassed in the middle of right of the present invention.

Claims (10)

2) deviated directional drilling section drilling well, its sequence of construction is: the drilling well of first paragraph two dimension build section, the drilling well of second segment three-dimensional increasing hole angle variable-azimuth well section, the 3rd section of steady lower curved section drilling well of two dimension, the 4th section of two-dimentional build section drilling well; Wherein second segment three-dimensional increasing hole angle variable-azimuth well section drilling well build angle rate, first paragraph two dimension build section drilling well build angle rate, the 4th section of two-dimentional build section build angle rate are all identical; Second segment increasing hole angle variable-azimuth well section is turned round tool face azimuth, orientation and is remained constant;
CN201410758293.XA2014-12-102014-12-10A kind of three-dimensional horizontal well drilling construction methodActiveCN104481398B (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN201410758293.XACN104481398B (en)2014-12-102014-12-10A kind of three-dimensional horizontal well drilling construction method

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN201410758293.XACN104481398B (en)2014-12-102014-12-10A kind of three-dimensional horizontal well drilling construction method

Publications (2)

Publication NumberPublication Date
CN104481398Atrue CN104481398A (en)2015-04-01
CN104481398B CN104481398B (en)2016-08-24

Family

ID=52755990

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN201410758293.XAActiveCN104481398B (en)2014-12-102014-12-10A kind of three-dimensional horizontal well drilling construction method

Country Status (1)

CountryLink
CN (1)CN104481398B (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN105550412A (en)*2015-12-082016-05-04中国石油化工股份有限公司Coincidence rate determining method and system of really drilled well and designed well
CN105625944A (en)*2016-02-152016-06-01中国石油天然气股份有限公司Drilling method for sidetracking horizontal well with same diameter as original well shaft
CN106285479A (en)*2016-10-202017-01-04中国石油化工股份有限公司A kind of track control method based on three-dimension GIS technology
CN108166927A (en)*2017-12-212018-06-15中国石油集团川庆钻探工程有限公司长庆钻井总公司A kind of appraisal procedure for being used to judge horizontal well construction mode
CN108661557A (en)*2017-03-272018-10-16中国石油化工股份有限公司A kind of anti-gas cut boring method and control system for fractured-cavernous reservoir
CN108756746A (en)*2018-05-082018-11-06中国石油集团渤海钻探工程有限公司A kind of barefoot laterally drilling ultra-short radius controllable levels well boring method
CN108798515A (en)*2017-05-042018-11-13中国石油天然气股份有限公司Directional drilling process for mudstone section
CN109812256A (en)*2019-03-282019-05-28陕西延长石油(集团)有限责任公司研究院 A horizontal well structure and drilling method for low permeability shallow oil reservoir
CN109902890A (en)*2017-12-072019-06-18中国石油化工股份有限公司华北油气分公司石油工程技术研究院A kind of horizontal well land in target evaluation method and system
CN109915018A (en)*2017-12-072019-06-21中国石油化工股份有限公司华北油气分公司石油工程技术研究院The determination method of tool face azimuth in a kind of control of three dimensional hole trajectory
CN111395975A (en)*2020-04-162020-07-10中国石油天然气集团有限公司Two-opening one-trip drilling tool combination suitable for construction of oil well horizontal well and construction method thereof
CN111550185A (en)*2020-05-152020-08-18洲际海峡能源科技有限公司Drilling method using screw and rotary steering tool combination system
CN111594131A (en)*2020-05-142020-08-28广东石油化工学院T-shaped well group and method for exploiting non-diagenetic natural gas hydrate
CN112418650A (en)*2020-11-192021-02-26中国石油天然气集团有限公司Method and device for determining petroleum drilling construction progress
CN113868951A (en)*2021-09-282021-12-31西南石油大学 A method of intelligently judging the best timing for drilling short trips
CN114909119A (en)*2022-04-292022-08-16大庆辰平钻井技术服务有限公司Drilling method for converting original vertical well or inclined well into U-shaped geothermal well with ultra-short radius
CN116335535A (en)*2021-12-242023-06-27中国石油天然气股份有限公司 A speed-increasing method and speed-increasing system for compound drilling in long stable and inclined sections
CN116341045A (en)*2021-12-232023-06-27中国石油天然气股份有限公司 Three-dimensional target horizontal well trajectory design method
CN116971724A (en)*2023-09-212023-10-31中国煤炭地质总局勘查研究总院Composite multi-branch drilling method for geological carbon dioxide sequestration and monitoring

Citations (3)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
US4945994A (en)*1987-12-171990-08-07Standard Alaska Production CompanyInverted wellbore completion
CN201184130Y (en)*2008-04-172009-01-21中国石油天然气股份有限公司Oil gas well overflow and leakage experimental device
CN102392601A (en)*2011-10-092012-03-28中国石油化工股份有限公司Method for determining hole trajectory of multi-target horizontal well

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
US4945994A (en)*1987-12-171990-08-07Standard Alaska Production CompanyInverted wellbore completion
CN201184130Y (en)*2008-04-172009-01-21中国石油天然气股份有限公司Oil gas well overflow and leakage experimental device
CN102392601A (en)*2011-10-092012-03-28中国石油化工股份有限公司Method for determining hole trajectory of multi-target horizontal well

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李克智: "红河油田水平井钻井提速难点与技术对策", 《石油钻探技术》, vol. 42, no. 2, 25 March 2014 (2014-03-25), pages 117 - 122*
闫吉曾: "镇泾油田HH37P1水平井钻完井技术", 《探矿工程(岩土钻掘工程)》, vol. 39, no. 6, 25 June 2012 (2012-06-25), pages 31 - 34*

Cited By (26)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN105550412B (en)*2015-12-082018-09-28中国石油化工股份有限公司A kind of determination method and system of reality drilling well and planned well coincidence rate
CN105550412A (en)*2015-12-082016-05-04中国石油化工股份有限公司Coincidence rate determining method and system of really drilled well and designed well
CN105625944A (en)*2016-02-152016-06-01中国石油天然气股份有限公司Drilling method for sidetracking horizontal well with same diameter as original well shaft
CN106285479A (en)*2016-10-202017-01-04中国石油化工股份有限公司A kind of track control method based on three-dimension GIS technology
CN108661557A (en)*2017-03-272018-10-16中国石油化工股份有限公司A kind of anti-gas cut boring method and control system for fractured-cavernous reservoir
CN108661557B (en)*2017-03-272022-11-25中国石油化工股份有限公司Gas invasion prevention drilling method and control system for fracture-cavity gas reservoir
CN108798515B (en)*2017-05-042020-05-08中国石油天然气股份有限公司Directional drilling process for mudstone section
CN108798515A (en)*2017-05-042018-11-13中国石油天然气股份有限公司Directional drilling process for mudstone section
CN109902890A (en)*2017-12-072019-06-18中国石油化工股份有限公司华北油气分公司石油工程技术研究院A kind of horizontal well land in target evaluation method and system
CN109915018A (en)*2017-12-072019-06-21中国石油化工股份有限公司华北油气分公司石油工程技术研究院The determination method of tool face azimuth in a kind of control of three dimensional hole trajectory
CN108166927A (en)*2017-12-212018-06-15中国石油集团川庆钻探工程有限公司长庆钻井总公司A kind of appraisal procedure for being used to judge horizontal well construction mode
CN108166927B (en)*2017-12-212019-06-04中国石油集团川庆钻探工程有限公司长庆钻井总公司It is a kind of for determining the appraisal procedure of horizontal well construction mode
CN108756746A (en)*2018-05-082018-11-06中国石油集团渤海钻探工程有限公司A kind of barefoot laterally drilling ultra-short radius controllable levels well boring method
CN109812256A (en)*2019-03-282019-05-28陕西延长石油(集团)有限责任公司研究院 A horizontal well structure and drilling method for low permeability shallow oil reservoir
CN111395975A (en)*2020-04-162020-07-10中国石油天然气集团有限公司Two-opening one-trip drilling tool combination suitable for construction of oil well horizontal well and construction method thereof
CN111594131A (en)*2020-05-142020-08-28广东石油化工学院T-shaped well group and method for exploiting non-diagenetic natural gas hydrate
CN111550185A (en)*2020-05-152020-08-18洲际海峡能源科技有限公司Drilling method using screw and rotary steering tool combination system
CN111550185B (en)*2020-05-152022-06-07洲际海峡能源科技有限公司Drilling method using screw and rotary steering tool combination system
CN112418650A (en)*2020-11-192021-02-26中国石油天然气集团有限公司Method and device for determining petroleum drilling construction progress
CN113868951A (en)*2021-09-282021-12-31西南石油大学 A method of intelligently judging the best timing for drilling short trips
CN113868951B (en)*2021-09-282024-12-10西南石油大学 A method for intelligently judging the best time for drilling short start
CN116341045A (en)*2021-12-232023-06-27中国石油天然气股份有限公司 Three-dimensional target horizontal well trajectory design method
CN116335535A (en)*2021-12-242023-06-27中国石油天然气股份有限公司 A speed-increasing method and speed-increasing system for compound drilling in long stable and inclined sections
CN114909119A (en)*2022-04-292022-08-16大庆辰平钻井技术服务有限公司Drilling method for converting original vertical well or inclined well into U-shaped geothermal well with ultra-short radius
CN116971724A (en)*2023-09-212023-10-31中国煤炭地质总局勘查研究总院Composite multi-branch drilling method for geological carbon dioxide sequestration and monitoring
CN116971724B (en)*2023-09-212024-01-12中国煤炭地质总局勘查研究总院 Composite multi-branch drilling method for carbon dioxide geological storage and monitoring

Also Published As

Publication numberPublication date
CN104481398B (en)2016-08-24

Similar Documents

PublicationPublication DateTitle
CN104481398B (en)A kind of three-dimensional horizontal well drilling construction method
CN104481400B (en)A kind of three-dimensional horizontal well track control method
CN103850711B (en)Salt hole air reserved storeroom twin-well banking process
CN104265270B (en)A kind of carbonate rock fractured cave wellbore trace design and control method
CN105114059B (en)A kind of three-dimensional orientation well Trajectory Design and control parameter method of discrimination
CN110147588A (en)One kind is based on the shortest three-dimensional Study on Optimum Design of Horizontal Well Path of drilling time
CN106285617A (en)Gas water horizontal well completion method
CN104832119A (en)Window opening and sidetrack drilling short-radius horizontal well and reverse circulation well cementing and water plugging method
CN109915018B (en)Method for determining tool face angle in three-dimensional borehole trajectory control
CN110513043B (en) A control method for inclination correction in vertical drilling process based on automatic steerable drilling tools
CN111441718A (en)Construction method, system and application for high-precision pilot shaft excavation of large-section steep slope long inclined shaft
CN105888549B (en)A kind of boring BHA of km depth L-type pre grouting from the surface and bore process
CN107060642B (en) Wellbore Trajectory Control Method for Multi-connected Horizontal Wells in Trona Deep and Thin Layers
CN103883255A (en)Horizontal well landing path control method based on continuously-oriented well drilling
CN102094580A (en)Coal engineering hole directional drilling method
CN112081528A (en)Horizontal section efficient support-free oscillating drilling tool combination and method
CN103422813B (en)Individual well eye multi-lateral horizontal well system for coal bed gas and boring method
CN103993829B (en)Apart from the middle major radius track of horizontal well before the little target of a kind of two dimension
CN212428580U (en)Horizontal section efficient non-support oscillation drilling tool
CN103510855B (en)A kind of horizontal well logging guide track optimization method
CN103993830B (en)A kind of method determining the front middle major radius track apart from horizontal well of two-dimentional little target
CN109711023B (en) Two-dimensional two-dimensional trajectory optimization method for dealing with three-dimensional obstacle-circling wells
CN116084838B (en) A method for determining the horizontal trajectory of a horizontal well in the roof of a surface coal seam
Xi et al.Control technique on navigating path of intersection between two horizontal wells
CN105625944A (en)Drilling method for sidetracking horizontal well with same diameter as original well shaft

Legal Events

DateCodeTitleDescription
C06Publication
PB01Publication
C10Entry into substantive examination
SE01Entry into force of request for substantive examination
C14Grant of patent or utility model
GR01Patent grant

[8]ページ先頭

©2009-2025 Movatter.jp