Double-head suspension tower crane
Download PDF

Info

Publication number
CN102344090A
CN102344090ACN2010102414681ACN201010241468ACN102344090ACN 102344090 ACN102344090 ACN 102344090ACN 2010102414681 ACN2010102414681 ACN 2010102414681ACN 201010241468 ACN201010241468 ACN 201010241468ACN 102344090 ACN102344090 ACN 102344090A
Authority
CN
China
Prior art keywords
crane
tower
crane arm
crane boom
arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010102414681A
Other languages
Chinese (zh)
Inventor
周杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IndividualfiledCriticalIndividual
Priority to CN2010102414681ApriorityCriticalpatent/CN102344090A/en
Publication of CN102344090ApublicationCriticalpatent/CN102344090A/en
Pendinglegal-statusCriticalCurrent

Links

Images

Landscapes

Abstract

The invention discloses a double-head suspension tower crane, which is used for building, water conservancy, electricity, highways, stations, docks, petrifaction, nuclear power stations and other construction sites. The tower crane in the prior art is only provided with one crane boom and one head suspension, so the hoisting efficiency is not high. The observation front side of a cab [16] is parallel to a rotation tower body [9], the cab [16] is installed on an upper base [8], a lifting mechanism [11] which is installed on a crane boom [12] is arranged at the right side of the rotation tower body [9], the crane boom is arranged at the left side of the rotation tower body [9] of the tower crane, one end of a crane boom short drag rod [13] is obliquely arranged on the crane boom, the other end of the crane boom short drag rod [13] is obliquely arranged in the middle of a tower plate, and one end of a crane boom long drag rod [14] is obliquely arranged on the crane boom. Compared with the acknowledged technology, the hoisting efficiency of the tower crane is improved by one time.

Description

Two tower crane formula hoisting crane
One, technical field
Two tower crane formula hoisting crane that use in building sites such as the present invention is used to build, water conservancy, electric power, highway, station, harbour, petrochemical industry, nuclear station.
Two, background technology
Existing technological tower crane has only one of a crane arm to hang, and lifting efficient is not high.
Three, summary of the invention
1. the objective of the invention is to design a kind of two tower crane formula hoisting crane; Tower crane removes equilibrium arm and balance arm brace, and a cover crane arm is installed again, a cover crane arm long draw, a cover crane arm short rod.All there is crane arm on the right side, the slewing tower left side of tower crane.
2. two tower crane formula hoisting crane is characterized in that: there is crane arm on the slewing tower left side of tower crane; Crane arm short rod one end is oblique on crane arm, and crane arm short rod one end is oblique in the middle of column plate, and crane arm long draw one end is oblique on crane arm; Crane arm long draw one end is oblique in the middle of column plate; The root of crane arm has lifting mechanism, and two on the pulley of tower head plate is symmetrical, and driver's cab is observed positive parallel with slewing tower apart.Driver's cab is installed, Yi Bian allow on the crane arm advertising panel is installed on upper bracket.The electrical apparatus control circuit of two tower crane formula hoisting crane is used known electrical apparatus control circuit, and the slewing tower right side also has lifting mechanism, luffing mechanism, suspension hook, the load-carrying dolly installed on the crane arm to be equal to that installed device is the same model and specification on the crane arm on the left side.The installation method of two tower crane formula hoisting crane have with, install the pinnacle of a pagoda after, the slewing tower height is about 22m; Will become splayed to fix with two steel cable wind ropes on the slewing tower, brake swing type mechanism, crane arm installs back (following installation is all pressed existing regulation and installed) by existing standard; Lifting mechanism is installed again; At the crane arm that steel cable wind rope opposite is installed, install with the crane arm of crane lifting, with rising mechanism's pull-up respectively; Crane arm short rod, crane arm long draw are installed, after crane arm, crane arm pull bar install.Steel cable wind rope the crane arm here is installed again, and with rising mechanism's pull-up respectively, crane arm short rod, crane arm long draw are installed, after crane arm, crane arm pull bar install.Dismantle the steel cable wind rope.Unclamp slewing gear brake.After hanging by existing standard mode, test run, examination, use by safety supervision approval back.
3. the present invention compares with known technology, and tower crane lifting efficient doubles, and practices thrift 30% manufacturing cost, practices thrift a body of the tower, practices thrift a basic expense, practices thrift 15% transportation volume.
Four, description of drawings
Accompanying drawing 1 of the present invention is a front view, and accompanying drawing 2 of the present invention is a planar view.
Five, the specific embodiment
Describe in conjunction with accompanying drawing 1,2: foundation for tower crane as prescribed is at the scene built, and base section [3] is upward installed (following installation all has by existing regulation installation) by existing regulation at foundation for tower crane [1], with the fastening base section of nut [2] [3]; Upward installation code joint [4] is with the secondary fastening standard knot [4] of high strength bolt for base section [3], and standard knot [4] is gone up undersetting [7] is installed, the following stock [6] of installing of undersetting [7]; Undersetting is equipped with pivoting support on [7], and upper bracket [8] is installed on the pivoting support, goes up at upper bracket [8] driver's cab [16] is installed; Go up installation slewing tower [9] at upper bracket [8]; Slewing tower [9] go up to be installed pinnacle of a pagoda [10], install pinnacle of a pagoda [10] after, slewing tower [9] height is about 22m; To become splayed to fix with two steel cable wind ropes on the slewing tower [2], brake swing type mechanism.Go up installation lifting mechanism [11], luffing mechanism, load-carrying dolly at crane arm [12].The crane arm [12] on steel cable wind rope opposite is installed; With crane lifting crane arm [12], the otic placode hole of crane arm links to each other with the otic placode hole of bearing pin with slewing tower [2], with rising mechanism [11] pull-up respectively; Crane arm short rod [13], crane arm long draw [14] are installed; The suspension centre hole of crane arm links to each other with the otic placode hole of pull bar with bearing pin, and the otic placode hole of pull bar links to each other with the hole of tower head plate, after crane arm, crane arm pull bar install.Steel cable wind rope the crane arm here is installed again.After connecting into an integral body to crane arm [12] earlier, lifting mechanism [11], luffing mechanism, load-carrying dolly are installed at crane arm [12].Crane arm [12] with crane lifting; With rising mechanism [11] pull-up respectively, crane arm short rod [13], crane arm long draw [14] are installed, and the suspension centre hole of crane arm links to each other with the otic placode hole of pull bar with bearing pin; The otic placode hole of pull bar links to each other with the hole of tower head plate, after crane arm rises, the weighing arm pull bar installs.Also to install the suspension hook on both sides.Allow on the crane arm advertising panel is installed on one side.Dismantle the steel cable wind rope.Unclamp slewing gear brake.After hanging by existing standard mode, test run, examination, use by safety supervision approval back.

Claims (1)

CN2010102414681A2010-07-272010-07-27Double-head suspension tower cranePendingCN102344090A (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN2010102414681ACN102344090A (en)2010-07-272010-07-27Double-head suspension tower crane

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN2010102414681ACN102344090A (en)2010-07-272010-07-27Double-head suspension tower crane

Publications (1)

Publication NumberPublication Date
CN102344090Atrue CN102344090A (en)2012-02-08

Family

ID=45543225

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN2010102414681APendingCN102344090A (en)2010-07-272010-07-27Double-head suspension tower crane

Country Status (1)

CountryLink
CN (1)CN102344090A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN103213907A (en)*2013-04-272013-07-24中联重科股份有限公司Tower crane
CN106185637A (en)*2016-08-182016-12-07无锡石油化工起重机有限公司Tower crane OPS with advertisement peg
CN108190761A (en)*2018-03-082018-06-22浙江虎霸建设机械有限公司A kind of derrick crane

Citations (7)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
FR2273750A1 (en)*1974-06-071976-01-02Grandi ReneTravelling crane with multiple winches - has equal-length opposite jibs slewing on telescopic tower
CN2292782Y (en)*1996-08-231998-09-30建设部长沙建设机械研究院Tower type dual-purpose machine for hoisting and distributing concrete
US20030183594A1 (en)*2002-03-262003-10-02Manuel Torres MartinezCrane for the assembly of wind turbines and assembly procedure
CN1666948A (en)*2005-01-212005-09-14魏纯玉Inside climbing tower crane with multi-hook and deep well winch
CN2858608Y (en)*2006-01-062007-01-17广东省建筑机械厂Folding dual-horizontal-arm self-rising crane
CN201351091Y (en)*2009-02-202009-11-25浙江省建设机械集团有限公司Double-rocker pole
CN201756422U (en)*2010-07-272011-03-09周杨Two-head-suspension tower crane

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
FR2273750A1 (en)*1974-06-071976-01-02Grandi ReneTravelling crane with multiple winches - has equal-length opposite jibs slewing on telescopic tower
CN2292782Y (en)*1996-08-231998-09-30建设部长沙建设机械研究院Tower type dual-purpose machine for hoisting and distributing concrete
US20030183594A1 (en)*2002-03-262003-10-02Manuel Torres MartinezCrane for the assembly of wind turbines and assembly procedure
CN1666948A (en)*2005-01-212005-09-14魏纯玉Inside climbing tower crane with multi-hook and deep well winch
CN2858608Y (en)*2006-01-062007-01-17广东省建筑机械厂Folding dual-horizontal-arm self-rising crane
CN201351091Y (en)*2009-02-202009-11-25浙江省建设机械集团有限公司Double-rocker pole
CN201756422U (en)*2010-07-272011-03-09周杨Two-head-suspension tower crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙在鲁: "《塔式起重机应用技术》", 30 June 2003, 中国建材工业出版社*

Cited By (4)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN103213907A (en)*2013-04-272013-07-24中联重科股份有限公司Tower crane
CN103213907B (en)*2013-04-272015-04-01中联重科股份有限公司Tower crane
CN106185637A (en)*2016-08-182016-12-07无锡石油化工起重机有限公司Tower crane OPS with advertisement peg
CN108190761A (en)*2018-03-082018-06-22浙江虎霸建设机械有限公司A kind of derrick crane

Similar Documents

PublicationPublication DateTitle
CN201381166Y (en)Hanging-point adjustable transverse hanging beam
CN205387439U (en)Mast hoisting accessory
CN202358849U (en)Small-size suspension crane
CN101539478B (en)Tester for testing multifunctional vane
CN104925672B (en)The all-hydraulic self-crawling type two-sided tower crane of suspension
CN102040166A (en)Hoisting tool for equipment on pillar
CN102992203B (en)Simple hoisting device for steel structure bridge installation
CN201756422U (en)Two-head-suspension tower crane
CN202245831U (en)Boom raising device of super-lift mast of crane
CN201334306Y (en)Hoisting machine for upright post member
CN102344090A (en)Double-head suspension tower crane
CN102351129B (en)Super-lifting device for improving lifting performance of crane and crane
CN201102883Y (en)Steel cable sliding and lifting device
CN202390116U (en)High-intensity small-tonnage hoist
CN202967922U (en)Simple hoisting device for mounting steel structural bridge
CN201778531U (en)Fixing base of auxiliary embraced bar
CN203461720U (en)Simple cantilever hoisting machine
CN202829361U (en)Small-size hoisting machine
CN105366559A (en)Small hoisting machine fixed on channel steel framework
CN201397252Y (en)Multifunctional blade testing desk
CN201762053U (en)Simple automatic hoisting rod
CN104291225A (en)Non-dragging independent mast device for hoisting rigid steel pile
CN205312920U (en)Small -size tower machine
CN103806850B (en)Separate type workover rig and using method thereof
CN102030272A (en)Building equipment hoisting device

Legal Events

DateCodeTitleDescription
C06Publication
PB01Publication
C10Entry into substantive examination
SE01Entry into force of request for substantive examination
C02Deemed withdrawal of patent application after publication (patent law 2001)
WD01Invention patent application deemed withdrawn after publication

Application publication date:20120208