CN101793154A - Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes - Google Patents

Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
Download PDF

Info

Publication number
CN101793154A
CN101793154ACN 201010133687CN201010133687ACN101793154ACN 101793154 ACN101793154 ACN 101793154ACN 201010133687CN201010133687CN 201010133687CN 201010133687 ACN201010133687 ACN 201010133687ACN 101793154 ACN101793154 ACN 101793154A
Authority
CN
China
Prior art keywords
hole
water
crack
tunnel
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010133687
Other languages
Chinese (zh)
Inventor
郑保才
程文斌
孟庆明
何超
辛振省
胡国伟
韩磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co LtdfiledCriticalChina Railway No 3 Engineering Group Co Ltd
Priority to CN 201010133687priorityCriticalpatent/CN101793154A/en
Publication of CN101793154ApublicationCriticalpatent/CN101793154A/en
Pendinglegal-statusCriticalCurrent

Links

Images

Landscapes

Abstract

The invention discloses a method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes, and aims to solve the problems that in case of a strong blast of high-pressure crevice in a long and big rich water tunnel as well as concentrated water quantity and high the water pressure, the conventional grouting technique has the serious grout-leaking phenomenon and unobvious blocking effect. The method comprises the following steps of: 1, drilling the relief holes communicated with crevices at the concentrated water burst positions on the whole rock wall within 1 meters away from the concentrated water burst positions of the rock wall; 2, blocking rock crevices around the crevices at the concentrated water burst positions on the surface of the tunnel; 3, drilling grouting holes communicated with the crevices at the concentrated water burst positions at positions which are 5 to 10 meters away from and on both sides of the concentrated water burst positions; 4, performing radial grouting; 5, pouring the grout in the grouting holes; and 6, pouring the grout in the relief holes. In the method, by using the geological conditions and parameters of the tunnel surrounding rocks and reasonably arranging the relief holes and the grout holes, the problems of grout leakage and the like caused by the high-pressure crevice water are solved, the construction cost is obviously lowered, the construction safety is guaranteed, and the effect of blocking a strong blast of high-pressure crevice water is obvious.

Description

Utilize tunnel surrounding geologic parameter and the grouting water blocking method that tap hole is set
Technical field
The present invention relates to constructing tunnel field in the civil engineering, the grouting water blocking method that is specifically related to utilize the tunnel surrounding geologic parameter He tap hole is set.
Background technology
Extensive expansion along with infrastructure constructions such as present domestic railways, it is imperative to build the tunnel of growing up in karst and complicated geology area, and complex geological condition such as karst water, crevice water, weak surrounding rock etc. have become and influences the subject matter that the constructing tunnel quality safety is faced.
At present, slurry injection technique handle some such as underground structure antiseepage, water blockoff, improve aspect such as tunnel surrounding mechanical property and bringing into play huge effect.But because existing slurry injection technique is only paid attention to injecting paste material and slip casting machinery, make and in the rich water tunnel digging process of growing up, have big strand high pressure crevice water, the water yield is concentrated and hydraulic pressure when big, when utilizing existing cement paste, biliquid to starch radially slurry injection technique, exist race slurry phenomenon serious, the unconspicuous problem of plugging effect can not satisfy the field engineering needs, have a strong impact on the constructing tunnel quality safety, and still do not have a kind of desirable grouting water blocking method at present high pressure crevice water.
Summary of the invention
The present invention is the high pressure crevice water that has big thigh at the rich water tunnel of growing up in order to solve, the water yield is concentrated and hydraulic pressure when big, when utilizing existing slurry injection technique slip casting, exist race slurry phenomenon serious, the unconspicuous problem of plugging effect, and a kind of grouting water blocking method that utilizes the tunnel surrounding geologic parameter and tap hole is set is provided.
The present invention is achieved by the following technical solutions:
Utilize tunnel surrounding geologic parameter and the grouting water blocking method that tap hole is set, may further comprise the steps:
(1) is drilled with tap hole: concentrate near the water burst place 1m to be drilled with the tap hole that communicates with crack, concentrated water burst place on interior complete crag at the tunnel crag;
(2) stop up tunnel surface and concentrate permeable rock crack on every side, crack, water burst place;
(3) be drilled with injected hole: measure the angle of cut α that concentrates crack, water burst place and tunnel wall with circumferentor, be drilled with and the injected hole of concentrating crack, water burst place to communicate in the distance of concentrating the both sides 5~10m of water burst place, the position of injected hole is located at the tap hole below, the spacing of adjacent two injected holes is 1~2m, and satisfy H+L>S * V
In the formula:
The H-injected hole degree of depth; L-injected hole and crack intersection point arrive the distance of rock layer surface along the crack;
Institute's injection slurry time of setting in the S-injected hole; The V-water velocity;
(4) radially slip casting: anhydrous place carries out radially slip casting (promptly perpendicular to the slip casting of tunnel wall direction) in the injected hole outside 2~3m farthest of water burst place apart from concentrating at the tunnel axial direction, thereby forms water-stop curtain in both sides, crack, concentrated water burst place;
(5) injected hole slip casting: according to injected hole hole depth H, at first the little injected hole of injected hole hole depth H is carried out slip casting, big to the hole depth H of injected hole then injected hole slip casting;
(6) tap hole slip casting: adopt the high-expansion chemical grout to carry out slip casting.
Further, described tap hole diameter is 0.5~0.9m.
Use the fast expansive cement that coagulates during described blocking surface rock crack.
Described injected hole hole depth is 3~5m.
Orifice tube is installed in described injected hole, tap hole aperture, with sealing agent anchoring orifice tube, by-pass valve control is installed in the orifice tube outer end.
Described injected hole slip casting, during tap hole slip casting, grouting pressure=hydraulic pressure+1.5~3mpa.
The present invention makes full use of the geological conditions and the parameter of tunnel surrounding self, reasonable Arrangement tap hole and injected hole, solve because the problems such as race slurry that high pressure crevice water causes can significantly reduce construction cost and guarantee construction safety, blocking high-pressure thigh shape crevice water effect is obvious.
Description of drawings
Fig. 1 arranges schematic diagram for injected hole
Fig. 2 is for being drilled with tap hole and injected hole schematic diagram
Fig. 3 is the little injected hole slip casting schematic diagram of hole depth
Fig. 4 is the big injected hole slip casting schematic diagram of hole depth
Fig. 5 is a tap hole slip casting schematic diagram
Among the figure: 1-concentrates crack, water burst place, 2-tap hole, 3-injected hole, 4-injected hole.
The specific embodiment
Embodiment 1
Utilize tunnel surrounding geologic parameter and the grouting water blocking method that tap hole is set, may further comprise the steps:
(1) is drilled with tap hole: as shown in Figure 2, concentrate near the water burst place 1m to be drilled with the tap hole that communicates with crack, concentrated water burst place on interior complete crag at crag, tap hole is according to water yield size, diameter is that 50mm (also can be 60mm, 90mm), hole depth 3m (also can be 4m, 5m), orifice tube is installed in the tap hole aperture, orifice tube is selected the steel pipe with the tap hole coupling for use, thread is established in the orifice tube outer end, with numb base one of screw thread is tightly wrapped the jail before orifice tube is installed, and with sledgehammer orifice tube is pounded in the borehole wall, adopt sealing agent anchoring orifice tube, by-pass valve control is installed in the outer end;
(2) stop up tunnel surface permeable rock crack: utilize the fast expansive cement that coagulates to stop up and concentrate fracture surface rock crack, water burst place, reduce the water burst area, the thigh water management in tap hole;
(3) be drilled with injected hole: as depicted in figs. 1 and 2, measure the angle of cut α that concentrates crack, water burst place and tunnel with circumferentor, be drilled with and the injected hole of concentrating crack, water burst place to communicate adjacent injected hole spacing 1m in the distance of concentrating the both sides 5~10m of water burst place, and satisfy H+L>S * V
In the formula:
The H-injected hole degree of depth; L-injected hole and crack intersection point arrive the distance of rock layer surface along the crack;
S-slurries time of setting; The V-water velocity;
Orifice tube is installed in the injected hole aperture, orifice tube is selected the steel pipe with injected hole and tap hole coupling for use, thread is established in the orifice tube outer end, before being installed, orifice tube one of screw thread is tightly wrapped the jail with numb base, with sledgehammer orifice tube is pounded in the borehole wall, adopt sealing agent anchoring orifice tube, by-pass valve control is installed in the outer end;
(4) radially slip casting: (also can be 2.5m, 3m) interior anhydrous place carries out radially slip casting, thereby forms water-stop curtain in both sides, crack, concentrated water burst place apart from concentrating the injected hole outside 2m farthest of water burst place at the tunnel axial direction;
(5) injected hole slip casting: as shown in Figure 3 and Figure 4, according to injected hole hole depth H, at first the little injected hole of injected hole hole depth H is carried out slip casting, big to the hole depth H of injected hole then injected hole slip casting, grouting pressure=hydraulic pressure+1.5~3mpa;
Grouting pipeline and orifice tube are connected, in the slip casting process, open all the other orifice tube ball valves,, when all the other orifice tube pulps, close its ball valve so that observe the slurries spread condition; Beginning slip casting will be used low pressure, then pressurization gradually;
Cement list slurry single hole grouting pressure reaches final pressure, and injection rate is 5L/min, and continuity 20min can finish the slip casting work in this hole;
(6) tap hole slip casting: as shown in Figure 5, adopt the high-expansion chemical grout to carry out slip casting.
Embodiment 2
Mountain, Lvliang City tunnel DK137+100~threaded list road ,+400 left and right sides
Geological condition:
DK137+100~+ 110 places, the rock stratum is more complete, grows a crack of traversing left and right sides line at+110 places, and behind the tunnel excavation, water yield is bigger in the crack.DK137+110~+ 150 places is horizontal stratum, and also there is water outlet in rock stratum bed thickness 0.5~1.0m between bedding; At+150 places, grow fillibility pipe one place, during excavation, a large amount of yellow mud of exposure; DK137+150~200 section are the joint fissure development belt, and country rock is cut into bulk by joint fissure, and underground water is with flowing out between rock; The crack is grown at the DK137+200 place; DK137+200~+ 230 places are for being horizontal stratum, and also there is water outlet in rock stratum bed thickness 0.5~1.0m between bedding.Horizontal crack is grown together by the DK137+230 place, and rock is more complete in DK137+230~+ 250 scopes, DK137+250~+ 400, and per 3~5m is and grows horizontal crack, and water outlet is all arranged in the crack; This section hydraulic pressure is at 0.8mpa.
The water blockoff scheme:
Behind a, the excavation, carry out the setting-out experiment, measure the angle of cut α that concentrates crack, water burst place and tunnel with circumferentor, according to disclosing the country rock situation, in time measure and draw geologic sketch map, crack, strike are measured one by one, analyze the relation that wall-rock crack and bedding and underground water are grown.
B, according to disclosing the country rock situation, in time adjust supporting parameter, DK137+145~+ 205 are section upright establishes the grid steelframe, crack water outlet place in time sets tap hole, concentrates drained.
C, will stop up tunnel surface then and concentrate permeable rock crack around the crack, water burst place;
D, be drilled with injected hole: be drilled with and the injected hole of concentrating crack, water burst place to communicate in the distance of concentrating the both sides 5~10m of water burst place, the position of injected hole is located at the tap hole below, and the spacing of adjacent two injected holes is 1m, and satisfies H+L>S * V,
In the formula:
The H-injected hole degree of depth; L-injected hole and crack intersection point arrive the distance of rock layer surface along the crack;
Institute's injection slurry time of setting in the S-injected hole; The V-water velocity;
E, water blockoff is carried out as a water blockoff paragraph in DK137+100~+ 250, the water blockoff job placement is after the inverted arch construction.
F, this section are carried out water blockoff by two ends to the centre, upwards carry out water blockoff from inverted arch, and right line carries out water blockoff behind the left line earlier.
G, at first take burst shape water burst improvement method to carry out DK137+100~+ 150, DK137+200~+ 250 section horizontal bedding and the laterally water outlet in crack.Using material mainly is to adopt high-expansion chemical grout, chemical grout, fast setting cement to carry out shutoff;
H, then the radially grouting degree of depth 5~10m (going deep into whole rock stratum 1.5m) of full tunnel section is carried out in DK137+140~+ 150, DK137+200~+ 210 two.Two sections at this paragraph form seal ring, there being the water location to control between them, and the phenomenon of string water before and after also reducing.
I, radially slip casting section is carried out in DK137+150~+ 200, injecting paste material is chosen chemical grout earlier, and pressure injection cement-water glass biliquid slurry replenishes the pressure injection cement grout at last then.Grouting sequence is inverted arch-abutment wall-arch.
Carry out right line slip casting after j, the slip casting of left line water blockoff are finished, grouting method is consistent with right line.
K, adopt the high-expansion chemical grout to carry out slip casting tap hole.
Water plugging effect:
After this section taked this scheme to finish, water plugging effect had reached designing requirement.In the water blockoff process, string regimen condition (when blocking up right line, new EXIT POINT appears in left line RightWall) appears in left and right sides line two places, and string water appears in front and back, and new EXIT POINT appears in two rimalas in DK137+080 place, carries out the slip casting shutoff after the discovery, and plugging effect is good.

Claims (6)

CN 2010101336872010-03-242010-03-24Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holesPendingCN101793154A (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN 201010133687CN101793154A (en)2010-03-242010-03-24Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN 201010133687CN101793154A (en)2010-03-242010-03-24Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes

Publications (1)

Publication NumberPublication Date
CN101793154Atrue CN101793154A (en)2010-08-04

Family

ID=42586045

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN 201010133687PendingCN101793154A (en)2010-03-242010-03-24Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes

Country Status (1)

CountryLink
CN (1)CN101793154A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN103437790A (en)*2013-08-232013-12-11西安建筑科技大学Method for blocking underground water
CN103821544A (en)*2014-02-282014-05-28山东大学Tunnel and underground engineering high-pressure high-flow-rate sudden surging water control method
CN106948846A (en)*2017-05-102017-07-14贵阳市城市轨道交通有限公司Shallow embedding Karst Tunnel gushing water method of disposal
CN108590715A (en)*2018-03-222018-09-28重庆建工第七建筑工程有限责任公司A kind of reserved laccolite tunneling boring radial grouting construction method in prominent water burst tunnel of tunneling
CN110185470A (en)*2019-06-192019-08-30中铁十九局集团第六工程有限公司A kind of tunnel cross formula grouting for water blocking hole structure and its construction method
CN111441819A (en)*2020-04-142020-07-24中国水电顾问集团贵阳勘测设计研究院岩土工程有限公司Tunnel advanced exploratory hole karst high-pressure water burst plugging device and method
CN112198025A (en)*2020-09-292021-01-08中国海洋大学 A test method for plugging rock fractures based on microbial grouting technology
CN113530598A (en)*2021-07-122021-10-22中陕核工业集团二一八大队有限公司Treatment process for uranium overproof tunnel water
CN114439509A (en)*2021-12-282022-05-06山西省交通新技术发展有限公司Grouting water plugging and reinforcing method for water-rich tunnel
CN115163183A (en)*2022-07-182022-10-11浙江省围海建设集团股份有限公司 Tunnel water gushing sealing method
CN116514508A (en)*2023-04-142023-08-01长沙矿山研究院有限责任公司Ultra-high water double-slurry grouting material and grouting process and equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
JPH06323100A (en)*1993-05-171994-11-22Shimizu CorpUnderground water pressure reducing construction method
CN1614158A (en)*2004-11-222005-05-11国家电力公司华东勘测设计研究院Ultrahigh pressure bursting underground flowing water split-flow pressure reduced treatment
CN101638987A (en)*2009-07-242010-02-03中铁二十一局集团有限公司Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
JPH06323100A (en)*1993-05-171994-11-22Shimizu CorpUnderground water pressure reducing construction method
CN1614158A (en)*2004-11-222005-05-11国家电力公司华东勘测设计研究院Ultrahigh pressure bursting underground flowing water split-flow pressure reduced treatment
CN101638987A (en)*2009-07-242010-02-03中铁二十一局集团有限公司Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《地下空间与工程学报》 20060430 邓仁清 高压富水隧道注浆堵水施工技术及应用 263-266、275 1-6 第2卷, 第2期 2*
《施工技术与测量技术》 20080831 马传飞 浅谈隧道高压地下水封堵施工技术 187-188、191 1-6 第28卷, 第4期 2*
《西铁科技》 20080430 孙佳英 吕梁山隧道3#斜井正洞堵水方案 第58页第2.1节至第59页第5.3节 1-6 , 2*

Cited By (16)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN103437790A (en)*2013-08-232013-12-11西安建筑科技大学Method for blocking underground water
CN103821544A (en)*2014-02-282014-05-28山东大学Tunnel and underground engineering high-pressure high-flow-rate sudden surging water control method
CN103821544B (en)*2014-02-282016-04-06山东大学Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN106948846A (en)*2017-05-102017-07-14贵阳市城市轨道交通有限公司Shallow embedding Karst Tunnel gushing water method of disposal
CN106948846B (en)*2017-05-102019-07-09贵阳市城市轨道交通有限公司Shallow embedding Karst Tunnel gushing water method of disposal
CN108590715A (en)*2018-03-222018-09-28重庆建工第七建筑工程有限责任公司A kind of reserved laccolite tunneling boring radial grouting construction method in prominent water burst tunnel of tunneling
CN110185470A (en)*2019-06-192019-08-30中铁十九局集团第六工程有限公司A kind of tunnel cross formula grouting for water blocking hole structure and its construction method
CN111441819A (en)*2020-04-142020-07-24中国水电顾问集团贵阳勘测设计研究院岩土工程有限公司Tunnel advanced exploratory hole karst high-pressure water burst plugging device and method
CN112198025A (en)*2020-09-292021-01-08中国海洋大学 A test method for plugging rock fractures based on microbial grouting technology
CN112198025B (en)*2020-09-292021-12-31中国海洋大学Test method for plugging rock cracks based on microbial grouting technology
CN113530598A (en)*2021-07-122021-10-22中陕核工业集团二一八大队有限公司Treatment process for uranium overproof tunnel water
CN113530598B (en)*2021-07-122023-11-24中陕核工业集团二一八大队有限公司Uranium exceeding tunnel water treatment process
CN114439509A (en)*2021-12-282022-05-06山西省交通新技术发展有限公司Grouting water plugging and reinforcing method for water-rich tunnel
CN115163183A (en)*2022-07-182022-10-11浙江省围海建设集团股份有限公司 Tunnel water gushing sealing method
CN116514508A (en)*2023-04-142023-08-01长沙矿山研究院有限责任公司Ultra-high water double-slurry grouting material and grouting process and equipment
CN116514508B (en)*2023-04-142024-05-28长沙矿山研究院有限责任公司Ultra-high water double-slurry grouting material and grouting process and equipment

Similar Documents

PublicationPublication DateTitle
CN101793154A (en)Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN103089275B (en)Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN108060908B (en)Long-distance horizontal directional drilling and grouting reinforcement process for water-rich sand layer under building group
CN101994513B (en)Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN103334770B (en)One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN110735653A (en) A deep hole retreat grouting water plugging construction method for igneous rock water-rich faults
CN103899323B (en)A kind of construction method of shield crossing rail yard
CN114109442B (en)Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN102705005B (en)Technology for plugging water bursting in mine by directional diversion grouting
CN103510964B (en)A kind of method when using shield formula TBM to construct to beans gravel rockfill grouting
CN109139052B (en) A grouting hole device and construction method based on high-pressure deep hole grouting
CN111119940B (en)Grouting construction treatment method
CN208965598U (en)The Anti-seeping technology structure of grout curtain and underground chamber intersection area
CN207177933U (en)A kind of advanced plugging structure of high-pressure high-flow underground water
CN107339108B (en) Construction method of subway tube shed in sandy area with enriched groundwater
CN103835729A (en)Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN106522981B (en)Pass through the method for protecting support in goaf tunnel
CN105927231A (en)Circulating induction curtain grouting method for inclined shaft to pass through water-rich compact quicksand layer
CN103362117A (en)Full-section grouting method for grouting section
CN103089276A (en)Deep-shallow hole and high-low pressure coupling grouting technology
CN102400694A (en)Method for reinforcing joint of shield tunnel and mine tunnel
CN109763483A (en) A kind of upward segmented grouting technology for thick Quaternary deep buried goaf and broken stratum
CN108590706A (en)One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN110130936A (en)It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN110469332A (en)A kind of advance support consolidation method passing through Debris Flow Deposition body tunnel

Legal Events

DateCodeTitleDescription
C06Publication
PB01Publication
C10Entry into substantive examination
SE01Entry into force of request for substantive examination
C12Rejection of a patent application after its publication
RJ01Rejection of invention patent application after publication

Application publication date:20100804