Movatterモバイル変換


[0]ホーム

URL:


CN101463924B - Heavy caliber pipe-jacking butt joint technique - Google Patents

Heavy caliber pipe-jacking butt joint technique
Download PDF

Info

Publication number
CN101463924B
CN101463924BCN2007100945881ACN200710094588ACN101463924BCN 101463924 BCN101463924 BCN 101463924BCN 2007100945881 ACN2007100945881 ACN 2007100945881ACN 200710094588 ACN200710094588 ACN 200710094588ACN 101463924 BCN101463924 BCN 101463924B
Authority
CN
China
Prior art keywords
pipe
tool
butt joint
tool pipe
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2007100945881A
Other languages
Chinese (zh)
Other versions
CN101463924A (en
Inventor
刘鸿鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
SHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FOUNDATION ENGINEERING Co LtdfiledCriticalSHANGHAI FOUNDATION ENGINEERING Co Ltd
Priority to CN2007100945881ApriorityCriticalpatent/CN101463924B/en
Publication of CN101463924ApublicationCriticalpatent/CN101463924A/en
Application grantedgrantedCritical
Publication of CN101463924BpublicationCriticalpatent/CN101463924B/en
Activelegal-statusCriticalCurrent
Anticipated expirationlegal-statusCritical

Links

Images

Landscapes

Abstract

The invention relates to a large-diameter jacking pipe butting process. The process comprises the following steps: reconstructing large-diameter jacking pipe tool pipe by improving soil mass of a butting area; performing plugging construction of the butting area by air pressure; and finishing butting of the large-diameter jacking pipes. The process can satisfy the requirement for large-diameter pipe jacking construction in a restricted area such as a traffic main artery, a bottleneck position of a regional junction or an area in which pipelines can not be avoided, and satisfy the requirement of shortening a long-distance pipe jacking construction period. The large-diameter jacking pipe butting process produces hardly any effect on road traffic, surrounding pipelines, lives of people, and has good social benefit. The large-diameter jacking pipe butting process can realize a plurality of impossible things in the process of underground pipeline construction, and has the advantages of low engineering cost, low risk and wide market prospect.

Description

Heavy caliber pipe-jacking butt joint technology
Technical field
The present invention relates to a kind of under ground piping jacking pipe construction process, especially a kind of heavy caliber pipe-jacking engineering that is used for can solve jacking construction and the push pipe butt joint construction process of use in the long-distance pipe jacking engineering under complicated or the restricted condition.
Background technique
Along with the extensive utilization of under ground piping, make the underground complicated pipeline traffic that formed at aspects such as traffic, the energy, environmental improvement, electric power transportation, municipal drainages.Therefore when implementing new pipework, especially in areas such as traffic main artery, regional hinges, underground utility complexity, buried depth differ, and construction has brought difficulty to heavy caliber pipe-jacking, many bottlenecks position does not even possess execution conditions, makes pipeline construction face the problem of underground butt joint.
On the other hand, trans-regional, city even transnational long-distance pipe engineering continue to bring out, and the increase of duct length makes engineering risk, also constantly rises at double, and the duration increases etc., and these factors have also limited the development of long-distance pipe jacking.
Summary of the invention
The present invention will solve the heavy caliber pipe-jacking construction in areas such as traffic main artery, regional hinges, and underground utility complexity, buried depth differ needs the technical problem of butt joint, and a kind of heavy caliber pipe-jacking butt joint technology is provided.
The technological scheme that the present invention solves the problems of the technologies described above is:
Heavy caliber pipe-jacking butt joint technology, its step is as follows:
1, the regional soil body of improvement butt joint
A kind of method that adopts deep layer to stir in dress, high-pressure rotary jet grouting pile, the freezing improves docking the regional soil body; Its improvement zone length is determined with the tool pipe leading portion+cutterhead width+butt joint gap of rectifying a deviation; Improvement regional depth and width should be done to extend up and down with segment length before the tool pipe with top power range of scatter value;
2, transform the push pipe tool pipe
When carrying out the heavy caliber pipe-jacking butt joint, two tool pipes are done the transformation of the demand of adaptation push pipe butt joint:
A. the transformation of tool pipe
1) increases filling system
The shrouding place sets up injected hole outside push pipe tool pipe cutterhead front portion, Tu Cang, Tu Cang, makes the slurries can be by injected hole to push pipe the place ahead, spray on every side;
2) remove the cutterhead front cone
3) set up steel plate behind the cutter
At the tool pipe head plate that a plurality of length are 50cm is set, when tool pipe arrived docking location, the set plate of two tool pipes extend out to another tool pipe and contacts, and played the effect of retaining soil, prevented occurrence of large-area landslide and seepage when butt joint;
B. the transformation of tool pipe inside before the butt joint:
With equipment complete removal in the tool pipe, and the big bearing of removal tool pipe, as serious leakage is arranged in demolishing process, sealing is carried out carrying out operation again behind the grouting and reinforcing to the native storehouse soil body immediately; The cutting plastron is removed the soil body in the native storehouse, and is fixed cutterhead outer and instrument shell, uses the gap between arc round steel shutoff cutterhead and the frame, and with steel plate cutterhead sealed;
3, docking area air pressure shutoff construction
Cabin in two butt joint push pipe tool pipes is provided with shrouding as an air pressure storehouse at the tool pipe tail, makes to form an airtight pressure work environment in two tool pipes, carry out full air pressure shutoff construction;
(1) air pressure construction process:
A. closed conduct is installed a full airlock;
B. pipeline and transfer chamber are detected, just can carry out next step construction after meeting the demands;
C. be replaced with the sealed cover of band injected hole at following soil outlet cover plate of air pressure, under normal pressure, inert slurry injected in the tool head front portion then;
D. under air pressure, open be unearthed hole and manhole, with obstacle in device clears such as electric hammer, pulley, the high pressure water gun soil storehouse;
E. soil excavation in the native from top to bottom storehouse, and in time weld shutoff with steel plate;
(2) air pressure shutoff construction
After slurries solidify, cutting off the tool pipe plastron observes, as do not have infiltration, continue cutting operation, otherwise reinforce with δ=20 gussets, in tool pipe, outwards carry out slip casting, determining do not have to go out work surface clearly under the seepage situation, seal two tool pipe gaps with δ 6 steel plates after, again plastron in the 2# tool pipe and cutterhead vertically hung scroll are cut off, press fixed two tool pipes of circumference five equilibrium with δ=8 of 25 steel plates at last;
4, push pipe joint tube coupling is made
After two tool pipe faggings, baffle plate disposed, two tool pipes connected in aggregates with δ=6mm steel plate, build steel concrete at the tool pipe inwall then, or adopt and spray concrete, make the tool pipe internal diameter consistent, guarantee that pipeline is straight, play preservative efficacy simultaneously with sewage concrete pipe internal diameter.
The invention has the beneficial effects as follows:, finish the heavy caliber pipe-jacking butt joint by transforming heavy caliber pipe-jacking tool pipe, the improvement docking area soil body and docking area air pressure shutoff construction.The requirement of heavy caliber pipe-jacking construction is carried out in the restricted areas such as zone that the present invention not only can satisfy on the traffic main artery, regional hinge bottleneck position or underground existence can not be dodged pipeline, and can satisfy the requirement of shortening the long-distance pipe jacking construction period.In the heavy caliber pipe-jacking docking operation,, has good social benefit to the almost not influence of road traffic, peripheral pipeline, people's lives.The present invention can make many can not coming true in the underground pipeline construction process, and the cost and the risk of engineering are low, have vast market prospect.
Description of drawings
Fig. 1, the 2nd, docking area soil body improvement area schematic;
Fig. 3 is two tool pipe schematic representation;
Fig. 4 is that the outer shrouding place of push pipe tool pipe cutterhead front portion, Tu Cang, Tu Cang sets up the injected hole schematic representation;
Fig. 5 sets up the steel plate schematic representation after the tool pipe head is removed cutterhead front cone and cutter;
Fig. 6 is the view after the 1# tool pipe is handled.
Embodiment
Below in conjunction with specific embodiment, further set forth patent of the present invention.Should be understood that these embodiments only to be used to the written or printed documents patent of invention is described and be not used in the restriction patent of the present invention scope.Should be understood that in addition those skilled in the art can make various changes or modifications the present invention after the content of having read patent instruction of the present invention, these equivalent form of values fall within the application's appended claims institute restricted portion equally.
Heavy caliber pipe-jacking butt joint technology of the present invention, its step is as follows:
1, the regional soil body improvement of butt joint (Fig. 1,2)
For guaranteeing that push pipe docks smoothly, should limit to some extent two push pipe tool pipe positions, prevent that tool pipe from producing unnecessary Side movement in docking operation, simultaneously for guaranteeing the stagnant water effect in butt joint zone, be necessary the soil body that docks the zone is improved.
The measure of improvement mainly contains deep layer and stirs dress, high-pressure rotary jet grouting pile, freezing etc.
The improvement zone length is determined with the tool pipe leading portion+cutterhead width+butt joint gap of rectifying a deviation.
Improvement regional depth and width should be done to extend up and down with segment length before the tool pipe with top power range of scatter value.
2, the transformation of push pipe tool pipe (Fig. 3)
When carrying out the heavy caliber pipe-jacking butt joint, two instruments are made corresponding transformation fully, so that adapt to the demand of push pipe butt joint.(1# tool pipe and 2# tool pipe)
A. the transformation of tool pipe
Tool pipe is newly-increased following function on original pipe jacking equipment:
(1) filling system (Fig. 4)
The shrouding place sets up injectedhole 9 outside push pipe tool pipe cutterhead front portion, Tu Cang, Tu Cang; make slurries by slip casting, improve the intensity of soil by injected hole to push pipe the place ahead, injection on every side to surrounding soil; increase the butt joint safety of construction, protection surrounding enviroment and pipeline etc.
(2) remove cutterhead front cone (Fig. 5)
The Security in the butt joint construction is improved, so removal tool pipe cutterhead the place aheadcone cutterhead 10 in the slit of two tool pipes when reducing to dock.
(3) set up steel plate (Fig. 5) behind the cutter
At the tool pipe head someplates 11 are set, the about 50cm of length, when tool pipe arrived docking location, the set plate of two tool pipes extend out to another tool pipe and contacts, and played the effect of retaining soil, prevented occurrence of large-area landslide and seepage when butt joint.
B. the transformation (Fig. 6) of tool pipe inside before the butt joint:
With equipment complete removal in the tool pipe (tool pipe correction jack is not temporarily torn open), and the big bearing of removal tool pipe, as serious leakage is arranged in demolishing process, sealing is carried out carrying out operation again behind the grouting and reinforcing to the native storehouse soil body 8 immediately; Cutting plastron 2 is removed the soil body in the native storehouse 3, and is fixed cutterhead outer 6 and tool pipe shell 1, uses the gap between arc round steel 5 shutoff cutterhead limbs 7 and the shell 1, and with steel plate cutterhead sealed.
3, docking area air pressure shutoff construction
Can provide a stable working surface for ensureing in the shutoff process, reduce construction risk, decision utilizes two interior cabins of butt joint push pipe tool pipes as an air pressure storehouse, at the tool pipe tail shrouding is set, make to form an airtight pressure work environment in two tool pipes, carry out full air pressure shutoff construction.
(1) air pressure construction process
A. closed conduct is installed a full airlock.
B. pipeline and transfer chamber are detected, just can carry out next step construction after meeting the demands.
C. be replaced with the sealed cover of band injected hole at following soil outlet cover plate of air pressure, under normal pressure, inert slurry injected in the tool head front portion then.
D. under air pressure, open be unearthed hole and manhole, with obstacle in device clears such as electric hammer, pulley, the high pressure water gun soil storehouse.
E. soil excavation in the native from top to bottom storehouse, and in time weld shutoff with steel plate.
(2) air pressure shutoff construction
After slurries solidify, cutting off tool pipe plastron 2 observes, as do not have infiltration, continue cutting operation, otherwise reinforce with δ=20 gussets 4, in tool pipe, outwards carry out slip casting, determining do not have to go out work surface clearly under the seepage situation, seal two tool pipe gaps with δ 6 steel plates after, again plastron 2 in the 2# tool pipe and cutterhead vertically hung scroll are cut off, press fixed two tool pipes of circumference five equilibrium with δ=8 of 25 steel plates at last.4, push pipe joint tube coupling is made
After two tool pipe faggings, baffle plate disposed, two tool pipes connected in aggregates with δ=6mm steel plate, build steel concrete at the tool pipe inwall then, or adopt and spray concrete, make the tool pipe internal diameter consistent, guarantee that pipeline is straight, play preservative efficacy simultaneously with sewage concrete pipe internal diameter.

Claims (1)

CN2007100945881A2007-12-202007-12-20Heavy caliber pipe-jacking butt joint techniqueActiveCN101463924B (en)

Priority Applications (1)

Application NumberPriority DateFiling DateTitle
CN2007100945881ACN101463924B (en)2007-12-202007-12-20Heavy caliber pipe-jacking butt joint technique

Applications Claiming Priority (1)

Application NumberPriority DateFiling DateTitle
CN2007100945881ACN101463924B (en)2007-12-202007-12-20Heavy caliber pipe-jacking butt joint technique

Publications (2)

Publication NumberPublication Date
CN101463924A CN101463924A (en)2009-06-24
CN101463924Btrue CN101463924B (en)2010-09-29

Family

ID=40804636

Family Applications (1)

Application NumberTitlePriority DateFiling Date
CN2007100945881AActiveCN101463924B (en)2007-12-202007-12-20Heavy caliber pipe-jacking butt joint technique

Country Status (1)

CountryLink
CN (1)CN101463924B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN102518873B (en)*2011-12-292013-05-15中铁上海工程局市政工程有限公司Method for paving large-diameter pipeline in soft soil in jacking and pulling combined manner
CN103604000B (en)*2013-11-192016-03-23厦门水务集团有限公司River sea bottom steel push pipe docking method of construction
CN103807504B (en)*2014-02-282017-04-12中冶天工上海十三冶建设有限公司Construction method of reinforced concrete jacked pipe underground T-shaped butt joint
SE538242C2 (en)*2014-10-082016-04-12Kjell Åke Olsson Förvaltnings Ab Method and apparatus for centering and temporary fixing of fittings.
CN104806816B (en)*2015-05-082017-07-25淄博华润燃气有限公司A kind of construction method of push pipe bilayer PE pipes push pipe into cast iron pipe
CN105909634B (en)*2016-06-282018-06-26上海锅炉厂有限公司A kind of pipe docks swelling device
CN107344129B (en)*2017-08-312022-07-22中国科学院金属研究所 A universal sample ampoule for space on-orbit material science experiments
CN110387940A (en)*2019-07-222019-10-29广东天濠建设工程有限公司Municipal subsoil drain pipeline construction method
CN110421332B (en)*2019-08-082021-06-11上海矩顶工程科技有限公司Steel pipe butt joint device with protective structure for pipe jacking construction
CN112303333B (en)*2020-11-182022-04-01郑州一建集团有限公司Construction method of bell and spigot concrete pipe
CN112576813B (en)*2020-11-302022-05-24山东时维九月能源科技有限公司Natural gas pipeline laying system
CN112555504B (en)*2020-11-302022-07-08珠海市荣泰市政工程有限公司Natural gas pipeline laying construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN1331394A (en)*2000-06-272002-01-16韩国电气通信公社Method for structure duct in ground
CN2594465Y (en)*2002-06-072003-12-24北京市市政工程研究院Pipe jacking apparatus with balanced earth pressure by supplying mud
CN1687538A (en)*2005-04-222005-10-26上海隧道工程股份有限公司Telescope feed type manipulator in backhoe digging, and application in tunnel shield machine and pipe pushing jack
CN1786417A (en)*2005-12-192006-06-14余彬泉Method for construction by coupling pipe joint type shield

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication numberPriority datePublication dateAssigneeTitle
CN1331394A (en)*2000-06-272002-01-16韩国电气通信公社Method for structure duct in ground
CN2594465Y (en)*2002-06-072003-12-24北京市市政工程研究院Pipe jacking apparatus with balanced earth pressure by supplying mud
CN1687538A (en)*2005-04-222005-10-26上海隧道工程股份有限公司Telescope feed type manipulator in backhoe digging, and application in tunnel shield machine and pipe pushing jack
CN1786417A (en)*2005-12-192006-06-14余彬泉Method for construction by coupling pipe joint type shield

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
余彬泉、陈传灿.顶管施工技术.人民交通出版社,1998,28.*

Also Published As

Publication numberPublication date
CN101463924A (en)2009-06-24

Similar Documents

PublicationPublication DateTitle
CN101463924B (en)Heavy caliber pipe-jacking butt joint technique
CN101424189B (en) Water-stopping device and method for excavating machine out of starting shaft or entering into receiving shaft
CN108049878B (en)A kind of powder land floor shield cuts the construction method that stake is crossed the river
CN101660419B (en)Construction method for putting tunnel shield into hole in special stratum
CN106812540B (en)Shield initial plain wall sealing water-stopping reinforcing structure and construction process
CN110778272A (en)Non-excavation laying construction method for large-diameter heat supply network pipeline
CN206592136U (en)A kind of plain wall closing water sealing consolidation structure of shield launching
CN203924137U (en)Serious seepage block structure of underground continuous wall
CN202250100U (en) A shield machine advanced grouting equipment
CN103741691A (en)Device and method for dismantling offshore pile pipe through reversed pulling under pressure
CN103556623A (en)Construction method for continuous wall of crossing deep-buried large-sized municipal pipeline
CN103628892A (en)Shield machine starting device with adjustable seal
CN201581902U (en)Sand layer pipe jacking shield machine
CN208998775U (en)A kind of pipe settlement deformation monitoring device
CN110173274A (en)A kind of head is removed obstacles method
CN103032629A (en)Pushing device of self-compaction reinforcing and anti-seepage pilot pipe and use method thereof
CN110863473A (en)Combined water blocking structure of embedded pressure steel pipe
CN204099720U (en)The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used
CN208058113U (en)A kind of amendment construction system of construction push pipe
CN212389380U (en)Tunnel advanced exploratory hole karst high-pressure water burst plugging device
CN203175568U (en)Internal sludge feeding and discharging control mechanism of pipe-jacking heading machine for cable tunnel
CN219933156U (en)Push type slurry outlet pipe jacking machine
CN218265952U (en) Water stop device for shield tunnel well joint
CN107975127A (en)The outer antipriming of vertical jacking
CN114370286B (en)Safety hole entering method of shield machine for open caisson structure

Legal Events

DateCodeTitleDescription
C06Publication
PB01Publication
C10Entry into substantive examination
SE01Entry into force of request for substantive examination
C14Grant of patent or utility model
GR01Patent grant
C56Change in the name or address of the patentee

Owner name:SHANGHAI FOUNDATION ENGINEERING GROUP CO., LTD.

Free format text:FORMER NAME: SHANGHAI FOUNDATION ENGINEERING CO., LTD.

CP01Change in the name or title of a patent holder

Address after:200433 Yangpu District, Shanghai Star Road, No. 231

Patentee after:Shanghai Foundation Engineering Group Co., Ltd.

Address before:200433 Yangpu District, Shanghai Star Road, No. 231

Patentee before:Shanghai Foundation Engineering Co., Ltd.


[8]ページ先頭

©2009-2025 Movatter.jp