Development Process

Haoqun Jiang edited this pageFeb 27, 2020 ·3 revisions

Roadmap

The team has a 6-12 months high-levelRoadmap, which defines high-level themes and features to be addressed in this timeframe.

Iterations

We work on a roughly six-week iteration schedule. That means, a new minor/major release every six weeks if everything goes as expected.

The six-week-cycle is commonly adopted in the web development ecosystem. E.g., the two major browser vendors,Chrome andFirefox, both promoted a six-week release schedule. It is alsorecommended by the Basecamp team.

Inside an Iteration

We work in weekly segments:

  • Week 1-2:
    • Address critical issues uncovered in the previous iteration
    • Reduce debt introduced during the last iteration
    • Plan the next iteration
  • Week 3-5: Work according to the plan
  • Final Week: Endgame
    • The team tests the new features according to a test plan and updates the documentation.- We make a pre-release available on the ‘next’ channel and invite users to help us test the pre-release.
  • Week 1 (next iteration):- monitoring the pre-release and fixing critical issues.- publish the release to the ‘latest’ channel, sometime midweek, after 24 hours with no changes to the pre-release.

For edits please submit a PRhere. For documentation, please visitcli.vuejs.org.