| HierarchIndex | Name | Start | End | Duration |
|---|---|---|---|---|
| 1 | Rawhide becomes Fedora 33 | Tue 2020-02-11 | Tue 2020-02-11 | 0 |
| 2 | Request "Fedora Change accepted" badge | Wed 2020-04-08 | Tue 2020-04-14 | 6 |
| 3 | Notifications for retirement of packages with security issues | Tue 2020-06-02 | Mon 2020-06-29 | 27 |
| 4 | REMINDER: Change Checkpoint: Proposal submission dealdine (requires infrastructure changes) in one week | Wed 2020-06-10 | Wed 2020-06-10 | 0 |
| 5 | Reduced capacity infrastructure | Mon 2020-06-15 | Fri 2020-07-10 | 25 |
| 6 | REMINDER: Change Checkpoint: Proposal submission deadline (System Wide Changes) in two weeks | Tue 2020-06-16 | Tue 2020-06-16 | 0 |
| 7 | REMINDER: Change Checkpoint: Proposal submission dealdine (requires infrastructure changes) in one week | Wed 2020-06-17 | Wed 2020-06-17 | 0 |
| 8 | REMINDER: Change Checkpoint: Proposals requiring mass rebuild submission deadline in one week | Tue 2020-06-23 | Tue 2020-06-23 | 0 |
| 9 | REMINDER: Change Checkpoint: Proposal submission deadline (System Wide Changes) in one week | Tue 2020-06-23 | Tue 2020-06-23 | 0 |
| 10 | Change Checkpoint: Proposal submission deadline (Changes requiring infrastructure changes) | Wed 2020-06-24 | Wed 2020-06-24 | 0 |
| 11 | Change Checkpoint: Proposal submission deadline (Changes requiring mass rebuild) | Tue 2020-06-30 | Tue 2020-06-30 | 0 |
| 12 | Change Checkpoint: Proposal submission deadline (System Wide Changes) | Tue 2020-06-30 | Tue 2020-06-30 | 0 |
| 13 | Change Checkpoint: Announce proposals requiring mass rebuild submission deadline | Tue 2020-06-30 | Tue 2020-06-30 | 0 |
| 14 | Request Changes Status Updates + Remind Submit Deadline | Tue 2020-06-30 | Tue 2020-06-30 | 0 |
| 15 | Change Checkpoint: Announce proposals submission deadline (System Wide Changes) | Tue 2020-06-30 | Tue 2020-06-30 | 0 |
| 16 | REMINDER: Change Checkpoint: Proposal submission deadline (Self Contained Changes) in one week | Tue 2020-07-14 | Tue 2020-07-14 | 0 |
| 17 | Change Checkpoint: Proposal submission deadline (Self Contained Changes) | Tue 2020-07-21 | Tue 2020-07-21 | 0 |
| 18 | Change Checkpoint: Announce proposal submission deadline (Self Contained Changes) | Tue 2020-07-21 | Tue 2020-07-21 | 0 |
| 19 | REMINDER: Software String Freeze in one week | Tue 2020-07-21 | Tue 2020-07-21 | 0 |
| 20 | REMINDER: Software String Freeze in one week Software String Freeze reminder to be sent to devel@ mailing list | Tue 2020-07-21 | Tue 2020-07-21 | 0 |
| 21 | Mass Rebuild: RPMs first, then modules | Wed 2020-07-22 | Tue 2020-08-11 | 20 |
| 22 | Rawhide Rebase Warning to Package Maintainers | Wed 2020-07-22 | Wed 2020-07-22 | 0 |
| 23 | Keepalive deadline for spins | Wed 2020-07-22 | Wed 2020-07-22 | 0 |
| 24 | Software String Freeze Reached | Tue 2020-07-28 | Tue 2020-07-28 | 0 |
| 25 | Compose tooling completed deadline | Wed 2020-07-29 | Wed 2020-07-29 | 0 |
| 26 | REMINDER: Workstation WG survey maintenance of default apps | Tue 2020-08-04 | Tue 2020-08-04 | 0 |
| 27 | Announce release blocking deliverables | Tue 2020-08-04 | Tue 2020-08-04 | 0 |
| 28 | REMINDER: Beta Wallpapers deadline in two weeks | Fri 2020-08-07 | Fri 2020-08-07 | 0 |
| 29 | Change Checkpoint: Completion deadline (testable) | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 30 | Branch Fedora 33 from Rawhide | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 31 | Rawhide becomes Fedora 34 | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 32 | Post-branch Freeze (end date approximate) | Tue 2020-08-11 | Fri 2020-08-14 | 3 |
| 33 | Change Checkpoint: Announce Completion deadline (testable) | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 34 | Remind not in MODIFIED Changes Owners | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 35 | Reflect supported versions in Bugzilla product description | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 36 | Rebase Rawhide bugs | Tue 2020-08-11 | Tue 2020-08-11 | 0 |
| 37 | Deliver Incomplete Changes to FESCo | Wed 2020-08-12 | Wed 2020-08-12 | 0 |
| 38 | REMINDER: Beta Wallpapers deadline in one week | Fri 2020-08-14 | Fri 2020-08-14 | 0 |
| 39 | Begin sending weekly blocker bug reports | Fri 2020-08-14 | Fri 2020-08-14 | 0 |
| 40 | REMINDER: Change Checkpoint: 100% Code Complete Deadline in 1 week | Tue 2020-08-18 | Tue 2020-08-18 | 0 |
| 41 | REMINDER: Software Translation Deadline in 1 week | Tue 2020-08-18 | Tue 2020-08-18 | 0 |
| 42 | Announce Beta Wallpapers deadline | Fri 2020-08-21 | Fri 2020-08-21 | 0 |
| 43 | Bodhi updates-testing activation point | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 44 | Change Checkpoint: 100% Code Complete Deadline | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 45 | Beta Freeze (starts at 1400 UTC) | Tue 2020-08-25 | Tue 2020-09-29 | 35 |
| 46 | Beta Infrastructure Change Freeze | Tue 2020-08-25 | Tue 2020-09-29 | 35 |
| 47 | REMINDER: WGs to solicit bullet/talking points for Beta release announcement | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 48 | Change Checkpoint: Announce 100% Code Complete Deadline | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 49 | Open ticket to FESCo requesting review of deliverables | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 50 | Software Translation Deadline | Tue 2020-08-25 | Tue 2020-08-25 | 0 |
| 51 | Deliver features < 100% to FESCo | Wed 2020-08-26 | Wed 2020-08-26 | 0 |
| 52 | REMINDER: Beta Release Readiness Meeting in 1 week | Thu 2020-09-03 | Thu 2020-09-03 | 0 |
| 53 | Beta Release Readiness Meeting | Thu 2020-09-10 | Thu 2020-09-10 | 0 |
| 54 | Beta Release Public Availability | Tue 2020-09-15 | Tue 2020-09-29 | 14 |
| 55 | Beta Release (Preferred Target) | Tue 2020-09-15 | Tue 2020-09-15 | 0 |
| 56 | REMINDER: Beta Release Go/No-Go Meeting in 1 week | Thu 2020-09-17 | Thu 2020-09-17 | 0 |
| 57 | Beta Target date #1 | Tue 2020-09-22 | Tue 2020-09-22 | 0 |
| 58 | REMINDER: Packaging of Wallpapers for the Final release in one week | Tue 2020-09-22 | Tue 2020-09-22 | 0 |
| 59 | Beta release Go/No-Go Meeting | Thu 2020-09-24 | Thu 2020-09-24 | 0 |
| 60 | Current Beta Target date | Tue 2020-09-29 | Tue 2020-09-29 | 0 |
| 61 | REMINDER: Packaging of Final Wallpapers starts | Tue 2020-09-29 | Tue 2020-09-29 | 0 |
| 62 | REMINDER: Workstation WG needs to start preparation of Fedora Magazine article "What's New in Fxx Workstation" | Tue 2020-09-29 | Tue 2020-09-29 | 0 |
| 63 | REMINDER: WGs to solicit bullet/talking points for GA release announcement | Tue 2020-09-29 | Tue 2020-09-29 | 0 |
| 64 | Create a ticket requesting import of the Beta release into Beaker | Wed 2020-09-30 | Wed 2020-09-30 | 0 |
| 65 | Final Freeze (starts at 1400 UTC) | Tue 2020-10-06 | Tue 2020-10-27 | 21 |
| 66 | Final Infrastructure Change Freeze | Tue 2020-10-06 | Tue 2020-10-27 | 21 |
| 67 | REMINDER: Final Release Readiness Meeting in 1 week | Thu 2020-10-08 | Thu 2020-10-08 | 0 |
| 68 | REMINDER: Workstation WG needs to finish Fedora Magazine article "What's New in Fxx Workstation" | Tue 2020-10-13 | Tue 2020-10-13 | 0 |
| 69 | REMINDER: Final Release Go/No-Go Meeting in 1 week | Thu 2020-10-15 | Thu 2020-10-15 | 0 |
| 70 | Final Release Readiness Meeting | Thu 2020-10-15 | Thu 2020-10-15 | 0 |
| 71 | Final Release Public Availability (GA) | Tue 2020-10-20 | Tue 2020-10-27 | 7 |
| 72 | Preferred Final Target date | Tue 2020-10-20 | Tue 2020-10-20 | 0 |
| 73 | Final release Go/No-Go Meeting | Thu 2020-10-22 | Thu 2020-10-22 | 0 |
| 74 | Current Final Target date | Tue 2020-10-27 | Tue 2020-10-27 | 0 |
| 75 | Final Target date #1 | Tue 2020-10-27 | Tue 2020-10-27 | 0 |
| 76 | Bugzilla cleanup of tracking bugs | Tue 2020-10-27 | Tue 2020-10-27 | 0 |
| 77 | Reflect supported versions in Bugzilla product description | Tue 2020-10-27 | Tue 2020-10-27 | 0 |
| 78 | Elections | Wed 2020-10-28 | Fri 2020-12-04 | 37 |
| 79 | Selection of questions from Questionnaire | Wed 2020-10-28 | Wed 2020-11-11 | 14 |
| 80 | Selection of questions from Questionnaire - start | Wed 2020-10-28 | Wed 2020-10-28 | 0 |
| 81 | Nomination period | Wed 2020-10-28 | Wed 2020-11-11 | 14 |
| 82 | Nomination period - start | Wed 2020-10-28 | Wed 2020-10-28 | 0 |
| 83 | REMINDER: Send Email About Fedora EOL Activities | Thu 2020-10-29 | Thu 2020-10-29 | 0 |
| 84 | Selection of questions from Questionnaire - end | Wed 2020-11-11 | Wed 2020-11-11 | 0 |
| 85 | Nomination period - end | Wed 2020-11-11 | Wed 2020-11-11 | 0 |
| 86 | Interviews | Wed 2020-11-11 | Wed 2020-11-18 | 7 |
| 87 | Interviews - start | Wed 2020-11-11 | Wed 2020-11-11 | 0 |
| 88 | Interviews - end | Wed 2020-11-18 | Wed 2020-11-18 | 0 |
| 89 | Voting Setup & Validation & Publishing of interviews | Wed 2020-11-18 | Thu 2020-11-19 | 1 |
| 90 | Voting period | Thu 2020-11-19 | Thu 2020-12-03 | 14 |
| 91 | Voting period starts (@ 00:00:00 UTC) | Thu 2020-11-19 | Thu 2020-11-19 | 0 |
| 92 | Fedora 31 EOL auto closure | Tue 2020-11-24 | Tue 2020-11-24 | 0 |
| 93 | Bugzilla Product Description--Fedora 31 EOL | Tue 2020-11-24 | Tue 2020-11-24 | 0 |
| 94 | Bugzilla Version 31 EOL | Tue 2020-11-24 | Tue 2020-11-24 | 0 |
| 95 | Fedora 31 EOL auto closure | Tue 2020-11-24 | Wed 2020-11-25 | 1 |
| 96 | Voting period ends (@ 23:59:59 UTC) | Thu 2020-12-03 | Thu 2020-12-03 | 0 |
| 97 | Result Announcement | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 98 | Request update of permissions on FESCo Pagure instance | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 99 | Request update of permissions on Mindshare Pagure instance | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 100 | Request update of permissions on Council Pagure instance | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 101 | Update of FESCo docs | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 102 | Update of Mindshare docs | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 103 | Update of Council docs | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 104 | Update of history FESCo docs | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 105 | Adjust the Council mailing list subscriptions | Fri 2020-12-04 | Fri 2020-12-04 | 0 |
| 106 | Adjust the Mindshare mailing list subscriptions | Fri 2020-12-04 | Fri 2020-12-04 | 0 |