VIPER (rover)

From Wikipedia, the free encyclopedia
Planned NASA lunar rover

VIPER
Artist's impression ofVIPER operating in darkness.
NamesVolatiles Investigating Polar Exploration Rover
Mission typeExploration, resource prospecting
OperatorNASA
Websitehttps://www.nasa.gov/viper
Mission duration100 days (planned)[1][2][3]
Spacecraft properties
Spacecraft typeRoboticlunar rover
ManufacturerNASA Lyndon B. Johnson Space Center
Dry mass430 kg (950 lb)[4]
Dimensions2.45 m (8 ft 0 in) in height,
1.53 m (5 ft 0 in) in length and width[5]
Start of mission
Launch date2027 (Planned)
RocketNew Glenn
Launch siteCape Canaveral Space Force Station,LC-36
ContractorBlue Origin
Moon rover
Landing date2027[6]
Landing siteMons Mouton,South pole region[7][2]
Instruments
Neutron Spectrometer System (NSS)
Near InfraRed Volatiles Spectrometer System (NIRVSS)
The Regolith and Ice Drill for Exploring New Terrain (TRIDENT)
Mass Spectrometer Observing Lunar Operations (MSolo)

VIPER (Volatiles Investigating Polar Exploration Rover) is alunar rover developed at the NASAAmes Research Center. The rover would be tasked with prospecting forlunar resources inpermanently shadowed areas oflunar south pole region, especially by mapping the distribution and concentration ofwater ice. The mission built on a previous NASA rover concept, theResource Prospector, which had been cancelled in 2018.[8]

VIPER was to be carried aboard Astrobotic'sGriffin lander as part of NASA'sCommercial Lunar Payload Services (CLPS) initiative.[9]

In 2025, NASA released an Announcement for Partnership Proposal seeking U.S. companies to deliver and operate the completed VIPER rover on the Moon.[10] On September 19, 2025, NASA selectedBlue Origin to carry VIPER to the Moon.[11]

Cancellation in 2024

[edit]
NASA's VIPER assembled at Johnson Space Center, when it was canceled

Amidst cost growth and delays to readiness of the rover and the Griffin lander, the VIPER program was ended in July 2024, with the rover planned to be disassembled and its instruments and components reused for other lunar missions. Before commencing disassembly, NASA announced they would consider "expressions of interest" from industry to use the "VIPER rover system at no cost to the government."[6] At the time of the announcement NASA expected to save $84 million by canceling the mission, which has cost $450 million so far.[12] The budgeted cost to build VIPER was $433.5 million, with $235.6 million budgeted to launch the lander.[13] The agency still plans to support the Griffin lander to arrive on the Moon in fall of 2025, though with Astrolab' FLIP rover in place of the VIPER rover.[14] NASA expects the primary objectives of VIPER to be fulfilled by an array of other missions planned for the next several years, but these may eventually become overshadowed and forgotten over time.[13]

Response to cancellation

[edit]

VIPER's abrupt cancellation was received poorly by the scientific community. At the time of its cancellation, VIPER had been fully assembled and completed vibration testing.[15] In response, a letter opposing the cancellation was circulated and garnered over 2500 signatures by the end of July 2024.[16] In August 2024,The Planetary Society published a statement calling for the program to be reconsidered.[17] On September 6, 2024, theHouse Committee on Science, Space, and Technology published a letter requesting additional information as to why NASA cancelled the mission.[18]

Post-cancellation developments

[edit]

In February 2025, NASA announced a new approach to potentially revive the VIPER mission through an industry partnership. The agency released an Announcement for Partnership Proposal seeking U.S. companies to deliver and operate the completed VIPER rover on the Moon. Under the proposed partnership, NASA would provide the already-built VIPER rover while the selected company would be responsible for the launch, landing, and surface operations, including data collection and dissemination, as well as all mission costs.[10] As of May, 2025, discussions are still ongoing but collapsed.

With the potential cuts from the second Donald Trump administration looming, the future of VIPER remains unclear. It is possible that the VIPER mission could be scrapped, and the team behind it face dismissal, and the VIPER name to be reused in unrelated contexts.

Potential revival

[edit]

On September 19, NASA announced the awarding of aCommercial Lunar Payload Services (CLPS) task order toBlue Origin, a commercial NASA partner that is a part of theArtemis Program[19] using theirBlue Moon MK1 Lander to land at the south pole of the Moon. As a part of this task order, Blue Origin has the option to deliver the rover to the Lunar surface.[20] Both NASA and Blue Origin have expressed eagerness in including VIPER as a part of the mission,[21][22] but it is likely that the ultimate decision to include VIPER relies on the success of thefirst mission of the Blue Moon MK1 Lander, another CLPS mission.[23]

Artist's conception of theVIPER rover on the Moon (Image courtesy of NASA Ames Research Center)

Objectives

[edit]
Orbital survey of the Moon taken by theMoon Mineralogy Mapper instrument onIndia'sChandrayaan-1 orbiter. Blue shows the spectral signature ofhydroxide, green shows the brightness of the surface as measured by reflected infrared radiation from theSun and red shows a mineral calledpyroxene.
The image shows the distribution of surface ice at the Moon's south pole (left) and north pole (right) as viewed by NASA's Moon Mineralogy Mapper (M3) spectrometer onboard India's Chandrayaan-1 orbiter.

TheVIPER rover has a size similar to a golf cart (around 1.4 × 1.4 × 2 m), and would be tasked with prospecting forlunar resources, especially forwater ice, mapping its distribution, and measuring its depth and purity.[1][2] The water distribution and form must be better understood before it can be evaluated as a potential resource within any evolvable lunar or Mars campaign.[24]

Proposed landing site of the Volatiles Investigating Polar Exploration Rover (VIPER)

TheVIPER rover would operate on the western edge ofNobile crater onMons Mouton in the Moon'ssouth pole region.[7][25] The first rover with its own lighting source,[26] it was planned to rove several kilometers, collecting data on different kinds of soil environments affected by light and temperature—those in complete darkness, occasional light and in constant sunlight.[27][2] In permanently shadowed locations, it would operate on battery power alone and would not be able to recharge them until it drives to a sunlit area. Its total operation time was planned to be 100 Earth days.[1][2][3]

Project management

[edit]

TheVIPER rover was part of the Lunar Discovery and Exploration Program managed by theScience Mission Directorate atNASA Headquarters, and was meant to support the crewedArtemis program.[2] NASA'sAmes Research Center was managing the rover project. The hardware for the rover was designed by theJohnson Space Center, while the instruments were provided by Ames, Kennedy, andHoneybee Robotics.[2] The project manager was Daniel Andrews,[2][28] and the project scientist was Anthony Colaprete, who was implementing the technology developed for the now cancelledResource Prospector rover.[29] The estimated cost of the mission was US$250 million in October 2019.[3] NASA said on 3 March 2021 that the new lifecycle cost for the mission was US$433.5 million.[30]

Both the launcher and the lander were competitively provided throughCommercial Lunar Payload Services (CLPS) contractors, with Astrobotic providing the Griffin lander to deliver the rover, and SpaceX providing the Falcon Heavy launch vehicle.[31] NASA was aiming to land the rover in September 2025 until the mission was canceled on 17 July 2024.[6][32]

Rover assembly and preparation for launch

[edit]

In February 2024 the final instrument, the TRIDENT drill, was installed into the rover.[33] Later on 28 February 2024, VIPER Project Manager Dan Andrews announced that all the rover's scientific instruments were installed, and that it was more than 80% built.[34] Further progress was reported in April 2024, remaining on track for launch later in the year.[35] The rover moved to the environmental testing phase in May.[36]

Capabilities

[edit]

At the lunar south pole VIPER will collect images and make neutron measurements while traveling between locations of interest.[37] At those locations the rover will shift to "Prospecting” mode, allowing higher fidelity measurements. The rover will be capable of:

  • operating for 5-6 lunar days
  • drilling 50 samples
  • traversing 20 km (12 mi)
  • driving at 20 cm/s (2,400 ft/h) (max)
  • moving between destinations at 0.8 cm/s (94 ft/h)
  • exploring temperature regimes from 40 to 300 K (−387.7 to 80.3 °F)
  • driving 1.7 km (1.1 mi) in PSRs
  • drilling 5 samples in PSRs

Science background

[edit]
Main articles:Lunar water andLunar resources

Data obtained byLunar Prospector,[38]Lunar Reconnaissance Orbiter,Chandrayaan-1, and theLunar Crater Observation and Sensing Satellite, revealed thatlunar water is present in the form of ice near the lunar poles, especially within permanently shadowed craters in thesouth pole region,[39][40] and present in the form of hydrated minerals in other high-latitude locations.[41]

Water may have been delivered to the Moon over geological timescales by the regular bombardment of water-bearingcomets,asteroids andmeteoroids,[42] or continuously producedin situ by the hydrogen ions (protons) of thesolar wind impacting oxygen-bearing minerals.[38] The physical form of the water ice is unknown, but some studies suggest that it is unlikely to be present in the form of thick, pure ice deposits, and may be a thin coating on soil grains.[43][44][40]

If it is possible to mine and extract the water molecules (H
2
O
) in large amounts, it can be broken down to its elements, namely hydrogen and oxygen, and form molecular hydrogen (H
2
) and molecular oxygen (O
2
) to be used as rocket bi-propellant or produce compounds formetallurgic and chemical production processes.[45] Just the production of propellant, was estimated by a joint panel of industry, government and academic experts, identified a near-term annual demand of 450 metric tons of lunar-derived propellant equating to 2450 metric tons of processed lunar water, generating US$2.4 billion of revenue annually.[46]

Science payload

[edit]
See also:Neutron spectrometer

TheVIPER rover will be equipped with a drill and three analyzers. The Neutron Spectrometer System (NSS), will detect sub-surface water from a distance, then,VIPER will stop at that location and deploy a 1 m (3 ft 3 in) drill called TRIDENT to obtain samples to be analyzed by its two onboardspectrometers, MSolo and NIRVSS.[2][3][47] Previously a TRIDENT drill and MSolo mass spectrometer were incorporated into thePRIME-1 payload of the unsuccessfulIM-2 lunar landing mission.[48]

Instrument nameAbbr.ProviderFunction[49]
Neutron Spectrometer System
NSS
Ames Research Center (NASA)Detect sub-surface hydrogen (potentially water) from a distance, suggesting prime sites for drilling
The Regolith and Ice Drill for Exploring New Terrain
TRIDENT
1-m drill to obtain subsurface samples
Near InfraRed Volatiles Spectrometer System
NIRVSS
Ames Research Center (NASA)Analyze mineral and volatile composition
Mass Spectrometer Observing Lunar Operations
MSolo
Kennedy Space Center (NASA)Analyze mineral and volatile composition

NSS

[edit]

NSS measures the energy released by hydrogen atoms when struck byneutrons. It was developed for the cancelledResource Prospector rover.[24]

TRIDENT

[edit]

The TRIDENT drill contains two temperature sensors, one at the tip and one about 20 cm (7.9 in) up. In addition to drilling and bringing up samples for NIRVSS and MSolo, its temperature sensors can measure the subsurface temperature. Combined with its heater element, TRIDENT can measure the thermal conductivity of the regolith. In addition, measuring the force necessary to drill reveals geotechnical properties of the regolith.[50]: 17 

NIRVSS

[edit]
The NIRVSS instrument

NIRVSS will determine if the hydrogen it encounters belong to water molecules (H2O) or tohydroxyl (OH). Originally developed for theResource Prospector rover.[24]
Sub-systems: Spectrometer Context Imager (a broad-spectrum camera); Longwave Calibration Sensor (measures surface temperature at very small scales).

MSolo

[edit]

MSolo will measure themass-to-charge ratio ofions to elucidate the chemical elements contained in the sample. The instrument was created through a collaboration withINFICON, in which one of their mass commercial spectrometers was modified to make it suitable for spaceflight.[50]: 9 

See also

[edit]

References

[edit]
  1. ^abcColdewey, Devin (25 October 2019)."NASA'sVIPER lunar rover will hunt water on the Moon in 2022".TechCrunch.VIPER is a limited-time mission; operating at the poles means there's no sunlight to harvest with solar panels, so the rover will carry all the power it needs to last 100 days there.
  2. ^abcdefghiLoff, Sarah (25 October 2019)."New VIPER Lunar Rover to Map Water Ice on the Moon".NASA. Archived fromthe original on 6 November 2019. Retrieved26 October 2019.Public Domain This article incorporates text from this source, which is in thepublic domain.
  3. ^abcdBartels, Meghan (25 October 2019)."NASA Will Launch a Lunar VIPER to Hunt Moon Water in 2022". Space.com. Retrieved13 April 2021.
  4. ^Colaprete, Anthony (17 August 2020)."VIPER: A lunar water reconnaissance mission"(PDF). NASA. Archived fromthe original(PDF) on 25 October 2022. Retrieved25 August 2020.Public Domain This article incorporates text from this source, which is in thepublic domain.
  5. ^"NASA's Next Lunar Rover Progresses Toward 2023 Launch". NASA. 24 February 2021. Retrieved5 March 2021.Public Domain This article incorporates text from this source, which is in thepublic domain.
  6. ^abc"NASA Ends VIPER Project, Continues Moon Exploration - NASA". Retrieved17 July 2024.
  7. ^abWright, Ernie; Ladd, David; Colaprete, Anthony; Ladd, David (20 September 2021)."NASA Scientific Visualization Studio".SVS. Retrieved27 October 2023.
  8. ^Bartels, Meghan (16 October 2019)."Moon VIPER: NASA Wants to Send a Water-Sniffing Rover to the Lunar South Pole in 2022". Space.com. Retrieved13 April 2021.
  9. ^"NASA Selects Astrobotic to Fly Water-Hunting Rover to the Moon". NASA. 11 June 2020. Retrieved14 June 2020.Public Domain This article incorporates text from this source, which is in thepublic domain.
  10. ^abJeff Foust (4 February 2025)."NASA requests industry proposals for VIPER lunar rover partnership". SpaceNews. Retrieved22 February 2025.
  11. ^"NASA Selects Blue Origin to Deliver VIPER Rover to Moon's South Pole - NASA".
  12. ^Tingley, Brett (17 July 2024)."NASA cancels $450 million VIPER moon rover due to budget concerns".Space.com.Archived from the original on 17 July 2024. Retrieved17 July 2024.
  13. ^abBoyle, Alan (17 July 2024)."NASA Stops Work on VIPER Moon Rover, Citing Cost and Schedule Issues".Universe Today.Archived from the original on 17 July 2024. Retrieved17 July 2024.
  14. ^FLIP Rover. Astrolab. 5 February 2026. Retrieved8 February 2026.
  15. ^Greshko, Michael."NASA May Spend $800 Million to Not Send This Revolutionary Rover to the Moon".Scientific American. Retrieved7 September 2024.
  16. ^Sykes, Mark."PLANETARY EXPLORATION NEWSLETTER Volume 18, Number 31".
  17. ^"The Planetary Society's Statement on VIPER's Path Forward".The Planetary Society. Retrieved7 September 2024.
  18. ^"Science Committee Leaders Seek Answers Regarding the Cancellation of NASA's VIPER Project".House Committee on Science Space & Tech - Republicans. 6 September 2024. Retrieved7 September 2024.
  19. ^"NASA Selects Blue Origin as Second Artemis Lunar Lander Provider - NASA". Retrieved20 September 2025.
  20. ^"NASA Selects Blue Origin to Deliver VIPER Rover to Moon's South Pole - NASA". Retrieved24 September 2025.
  21. ^Dave Limp [@davill] (19 September 2025)."Looking forward to partnering with @NASA to prepare VIPER for flight on our second MK1 lunar lander. VIPER is incredibly important, including instruments to help search for resources like ice. This includes our Honeybee Robotics TRIDENT drill, designed to penetrate up to 3 ft, or 1m, below the lunar surface. Weighing around 44 lbs, or 20 kg, the drill uses a jackhammer mode to cut through hard rocks and cryogenic ice" (Tweet) – viaTwitter.
  22. ^@NASAScience_ (19 September 2025)."After exploring innovative and cost-effective approaches, @NASA has selected @blueorigin to deliver the VIPER rover to the Moon! VIPER will search for vital resources like water ice to support a long-term human presence on the lunar surface. !" (Tweet) – viaTwitter.
  23. ^"NASA resurrects its VIPER moon rover for a 2027 mission with Blue Origin".Yahoo Tech. 21 September 2025. Retrieved24 September 2025.
  24. ^abcElphic, Richard; Colaprete, Anthony; Andrews, Daniel (2018)."Resource Prospector: Evaluating the ISRU potential of the lunar poles".42nd COSPAR Scientific Assembly.42.Bibcode:2018cosp...42E.981E.
  25. ^"NASA's Artemis Rover to Land Near Nobile Region of Moon's South Pole". NASA. 20 September 2021. Retrieved20 September 2021.Public Domain This article incorporates text from this source, which is in thepublic domain.
  26. ^"NASA Replans CLPS Delivery of VIPER to 2024 to Reduce Risk".NASA. 18 July 2022.Archived from the original on 17 July 2024. Retrieved18 July 2022.
  27. ^Hautaluoma, Grey; Johnson, Alana (28 October 2019)."New VIPER lunar rover to map water ice on the moon".PhysOrg.
  28. ^Moon, Mariella (26 October 2019)."NASA's VIPER rover will look for water ice on the Moon".ENGADGET.
  29. ^Foust, Jeff (27 October 2019)."NASA confirms plans to send prospecting rover to the moon".SpaceNews.
  30. ^"VIPER lunar rover mission cost increases". SpaceNews. 3 March 2021. Retrieved5 March 2021.
  31. ^Foust, Jeff (13 April 2021)."Astrobotic selects Falcon Heavy to launch NASA's VIPER lunar rover". SpaceNews. Retrieved13 April 2021.
  32. ^Harris, Rainier (17 July 2024)."NASA Cancels Rover Mission Set to Search for Ice on Moon".Bloomberg.com. Retrieved18 July 2024.
  33. ^"TRIDENT Drill Integrated into NASA's VIPER Rover, Completing its Scientific Arsenal". February 2024.
  34. ^Lea, Robert (3 March 2024)."NASA's ice-hunting VIPER moon rover getting ready to slither to the launch pad".Space.com. Retrieved4 March 2024.
  35. ^"NASA's VIPER Gets Its Head and Neck – NASA". Retrieved18 April 2024.
  36. ^"Mission Manager Update: VIPER Rover Approved to Move into Environmental Testing! - NASA". 14 May 2024. Retrieved15 May 2024.
  37. ^Fong, Terry (24 April 2025).VIPER Rover Design and Mission Operations. Lunar Autonomy Mobility Pathfinder Workshop. NASA.
  38. ^ab"NASA – Lunar Prospector". lunar.arc.nasa.gov. Archived fromthe original on 14 September 2016. Retrieved25 May 2015.Public Domain This article incorporates text from this source, which is in thepublic domain.
  39. ^"NASA Looking to Mine Water on the Moon and Mars".Soderman NASA's Solar System Exploration Research Virtual Institute.Public Domain This article incorporates text from this source, which is in thepublic domain.
  40. ^abNeish, C. D.; Bussey, D. B. J.; Spudis, P.; Marshall, W.; Thomson, B. J.; Patterson, G. W.; Carter, L. M. (13 January 2011)."The nature of lunar volatiles as revealed by Mini-RF observations of the LCROSS impact site".Journal of Geophysical Research: Planets.116 (E01005): 8.Bibcode:2011JGRE..116.1005N.doi:10.1029/2010JE003647.
  41. ^Pieters, C. M.; Goswami, J. N.; Clark, R. N.; Annadurai, M.; Boardman, J.; Buratti, B.; Combe, J.-P.; Dyar, M. D.; Green, R.; Head, J. W.; Hibbitts, C.; Hicks, M.; Isaacson, P.; Klima, R.; Kramer, G.; Kumar, S.; Livo, E.; Lundeen, S.; Malaret, E.; McCord, T.; Mustard, J.; Nettles, J.; Petro, N.; Runyon, C.; Staid, M.; Sunshine, J.; Taylor, L. A.; Tompkins, S.; Varanasi, P. (2009)."Character and Spatial Distribution of OH/H2O on the Surface of the Moon Seen by M3 on Chandrayaan-1".Science.326 (5952):568–572.Bibcode:2009Sci...326..568P.doi:10.1126/science.1178658.PMID 19779151.S2CID 447133.Public Domain This article incorporates text from this source, which is in thepublic domain.
  42. ^Elston, D. P. (1971)."Character and Geologic Habitat of Potential Deposits of Water, Carbon and Rare Gases on the Moon".Geological Problems in Lunar and Planetary Research: 441.Bibcode:1971gplp.conf..441E.
  43. ^Jozwiak, L. M.; Patterson, G. W.; Perkins, R. (2019)."Mini-RF Monostatic Radar Observations of Permanently Shadowed Crater Floors".Lunar ISRU 2019 – Developing a New Space Economy Through Lunar Resources and Their Utilization.2152: 5079.Bibcode:2019LPICo2152.5079J.ISSN 0161-5297.
  44. ^Nozette, Stewart; Spudis, Paul; Bussey, Ben; Jensen, Robert; Raney, Keith (January 2010). "The Lunar Reconnaissance Orbiter Miniature Radio Frequency (Mini-RF) Technology Demonstration".Space Science Reviews.150 (1–4):285–302.Bibcode:2010SSRv..150..285N.doi:10.1007/s11214-009-9607-5.S2CID 54041415.
  45. ^Anand, M.; Crawford, I. A.; Balat-Pichelin, M.; Abanades, S.; van Westrenen, W.; Péraudeau, G.; Jaumann, R.; Seboldt, W. (2012). "A brief review of chemical and mineralogical resources on the Moon and likely initial in situ resource utilization (ISRU) applications".Planetary and Space Science.74 (1):42–48.Bibcode:2012P&SS...74...42A.doi:10.1016/j.pss.2012.08.012.
  46. ^David, Leonard (15 March 2019)."Moon Mining Could Actually Work, with the Right Approach".Space.com.
  47. ^"Lunar Exploration Science Objectives"(PDF). NASA. 15 August 2019. Retrieved22 September 2021.Public Domain This article incorporates text from this source, which is in thepublic domain.
  48. ^"Intuitive Machines 2 (PRIME 1)".nssdc.gsfc.nasa.gov.NASA.Archived from the original on 24 May 2022. Retrieved9 May 2024.Public Domain This article incorporates text from this source, which is in thepublic domain.
  49. ^"Where's the Water? Two Resource-Hunting Tools for the Moon's Surface".NASA. 10 March 2019.Public Domain This article incorporates text from this source, which is in thepublic domain.
  50. ^ab"NASA VIPER Oral History Project - Anthony Colaprete"(PDF). 8 September 2022.
Missions
Uncrewed
Crewed
Emblem of the Artemis program
Agencies
Facilities
Rockets
Crewed spacecraft
Robotic spacecraft
Policy and history
History
(creation)
General
Human spaceflight
programs
Past
Current
Robotic programs
Past
Current
Individual featured
missions
(human and robotic)
Past
Currently
operating
Future
Communications
and navigation
NASA lists
NASA images
and artwork
Related
Exploration
programs
Active
missions
Orbiters
Landers
Rovers
Past
missions
Crewed landings
Orbiters
Impactors
Landers
Rovers
Sample return
Failed landings
Flybys
Planned
missions
Artemis
CLPS
Luna-Glob
CLEP
Chandrayaan
KLEP
ESA
Others
Proposed
missions
Robotic
Crewed
Cancelled /
concepts
Related
  • Missions are ordered by launch date. Crewed missions are initalics.
Active
Past
Lunokhod
Apollo
CLEP
Chandrayaan
Rashid
CLPS
JAXA
Ispace Inc.
Planned
Proposed
Cancelled
Related
Missions are ordered by launch date. Sign indicates failure en route or before intended mission data returned.
Retrieved from "https://en.wikipedia.org/w/index.php?title=VIPER_(rover)&oldid=1337306138"
Categories:
Hidden categories:

[8]ページ先頭

©2009-2026 Movatter.jp