| MRT Orange Line รถไฟฟ้ามหานคร สายสีส้ม | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Min Buri Station | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Overview | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Status | Structure Complete : OR13Thailand Cultural Centre - OR29Yaek Rom Klao Under Construction : OR02Bang Khun Non - OR13Thailand Cultural Centre Future : OR01Taling Chan - OR02Bang Khun Non | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Owner | Mass Rapid Transit Authority of Thailand | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Locale | Bangkok,Thailand | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Termini |
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Stations | 17(Structure Complete) 11(Under construction) 1(future) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Website | https://www.mrta-orangelineeast.com/en/home | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Service | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Type | Rapid transit | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| System | MRT | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Operator(s) | Bangkok Expressway and Metro | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Depot(s) | Phra Ram 9 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Rolling stock | Siemens 32 three-car trains | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| History | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Commenced | 9 February 2017; 9 years ago (2017-02-09) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Planned opening | 2028 : OR13Thailand Cultural Centre - OR29 Yaek Rom Klao [1]July 2030 : OR02Bang Khun Non - OR13Thailand Cultural Centre [1]TBA : OR01 Taling Chan - OR02Bang Khun Non | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Technical | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Line length | 38.78 km (24.10 mi) Elevated 8.43 km (5.24 mi) Underground: 30.35 km (18.86 mi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Track gauge | 1,435 mm (4 ft 8+1⁄2 in)standard gauge | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Electrification | 750 V DC third rail | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Operating speed | 80 km/h (50 mph) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TheMRT Orange Line (Thai:รถไฟฟ้ามหานคร สายสีส้ม) is an under-constructionrapid transit line of theMass Rapid Transit Authority of Thailand (MRTA) in theBangkok Metropolitan Area,Thailand. When fully completed, the MRT Orange line will be 35.9 km (22.3 mi) long with 29stations (7 stations will be elevated for 8.9 km (5.5 mi) and 22 will be underground for 27 km (16.8 mi)), including an interchange with the currentThailand Cultural Centre Station ofMRT Blue Line).
The MRT Orange Line is divided into two sections: the 22.5 km (14.0 mi) Eastern Section, running from Yaek Rom Klao to Thailand Cultural Centre,[2][3] and the 13.4 km (8.3 mi) Western Section, extending from Thailand Cultural Centre to Bang Khun Non.
Construction of the Eastern Section commenced in June 2017, and civil works were completed 100% as of June 2023.[4] However, delays in awarding contracts for the signaling systems and rolling stock postponed the line’s opening. In December 2024, Bangkok Expressway and Metro Public Company Limited (BEM) signed a contract with Siemens Mobility and its consortium partners to supply rolling stock and signaling systems for both sections of the line. On August 6, 2025 the MRTA announced that the Eastern Section is projected to open to the public in late-2027[5] earlier than the previously announced opening date of 2028.[1]
Construction of the Western Section began in July 2024. As of the end of July 2025, civil construction had progressed to 14.06%.[6] This section is expected to require approximately six years for completion, with an anticipated opening in July 2030.[1]
The MRT Orange Line will travel along a mostly east-west axis from Bangkok's eastern suburbs, passing through the city center andKo Rattanakosin, before servingThonburi on the west bank of theChao Phraya River.
The initial phase of the Orange Line will travel along an elevated structure above Ramkhamkhaeng Road from Yaek Rom Klao station, near the Ramkhamhaeng-Suwinthawong Junction inMin Buri District, to Ban Ma Junction inBang Kapi District for 7.5 km (4.7 mi) before transitioning underground. The line will continue to travel southwest under Ramkhamhaeng Road until its intersection with Rama IX Road, whence it will proceed westward under Rama IX Road before terminating atThailand Cultural Centre.
Interchanges for this segment will be available toMRT Pink Line atMin Buri,MRT Yellow Line atYaek Lam Sali, and theMRT Blue Line atThailand Cultural Centre.
The western section of the MRT Orange Lin will travel west fromThailand Cultural Centre Station via Din Daeng housing estates and Bangkok City Hall 2 toVibhavadi Rangsit Road, Sam Liam Din Daeng Junction. It will follow Ratchaprarop Road towardsPratunam before following Phetchaburi Road and Lan Luang Road as the alignment approachesKo Rattanakosin. The line will travel underRatchadamnoen Avenue to serveSanam Luang andBanglamphu before crossing theChao Phraya River nearPhra Pinklao Bridge. Once inThonburi, the line will follow theBangkok Noi spur line of theSRT commuter train before terminating at Bang Khun Non, located at Charan Sanitwong road, where there will be an interchange with theMRT Blue Line.
In addition to interchanging with theMRT Blue Line, the western segment will also include an interchange to theAirport Rail Link atRatchaprarop station, the BTSSukhumvit Line atRatchathewi Station, theMRT Purple Line at the futureDemocracy Monument station. A further extension toTaling Chan railway station is envisioned.
The original plan of the MRT Orange Line aimed to serve travel demand between the northwestern area ofThonburi, at Bang Bamru Railway Station inBang Phlat District, and the east ofBangkok inBang Kapi District. It was planned to run along Ramkhamhaeng Road andRatchawithi Road, passing many public places likeHua Mak Stadium,Dusit Zoo andVictory Monument, and provide access to universities includingRamkhamhaeng University, Suan Sunandha and Suan DusitRajabhat University and many government offices. In the 1990s proposal for the Orange Line, it indicates a route length of 27.3 kilometers from Bang Kapi toRat Burana District, while the planned extensions are to Ban Na for 16.4 kilometers and finally toMin Buri District for 10 kilometers.[7]
In 2009, OTP proposed that the original MRT Brown line plan from Bang Kapi District elevated along Ram Khamhaeng Road to the eastern suburbs inSaphan Sung District andMin Buri District, be merged with the Orange Line and updated Bangkok's mass rapid transit master plan accordingly.[8] In July 2011, the section from Bang Khun Non to Taling Chan was finally scrapped in favour of theSRT Light Red Line spur line which duplicates the same route.[9] In 2012, there were further notable changes made to the central and western sections of the Orange Line. The section fromDin Daeng District to Bang Bamru was rerouted away from Victory Monument and Ratchawithi road route to further run south toPratunam and then west along Petchaburi Road and Larn Luang Road. Continuing farther west alongRatchadamnoen Klang Road andSanam Luang before passing under theChao Praya river and finally terminating at Bang Khun Non to interchange with theMRT Blue Line extension.
The MRT Orange line Eastern section was originally planned to be tendered by the end of 2013. However, due to protests by residents regarding station footprint and compulsory land acquisition around stations at Pratunam, Ratchaprarop, Pracha Songkhro and Soesim stations the MRTA needed another 12 months to redesign sections of the line.[10] Subsequently, political protests against the Thai government led to the metro transport funding bill lapsing when parliament was dissolved in December 2013. On 9 December 2015, Cabinet finally approved the Orange Line. On 19 April 2016, the Cabinet further approved a budget of 82.9 billion baht for Phase 1 Eastern section to build 17 stations and 22.5 km (14.0 mi) of rail from the Thailand Cultural Centre to Minburi, of which 12.2 km (7.6 mi) will be underground and 9 km (5.6 mi) will be elevated.[11] The consultation was led by MHPM for project implementation services to Chotjinda Consultant for construction supervision and to MAA Consultant, also for project management and construction.[12]
On 3 July 2020, the MRTA released the tender for the design and construction of the Western extension.[13] However in late August 2020, the tender submission deadline was subsequently delayed.[14] and the MRTA amended the tender assessment criteria resulting in a lawsuit and an injunction suspending the tender decision.[15] The tender was subsequently cancelled by the MRTA in February 2021 given ongoing litigation by the BTSC.[16] After approval by the Administrative Court given ongoing litigation, a new tender issued in October has a deadline for bids of January 2022.[17]
The Criminal Court - Corruption and Malfeasance Division hearing into the cancelled tender process was conducted in late December 2021 which further delayed the reissued tender timeframe.[18] Subject to court approval, the MRTA planned to review tender bids for a period of 3 months before seeking Cabinet approval for a reissued tender in April or May 2022. The MRTA reissued the new tender on 24 May 2022 with tender packages available for purchase until 10 June.[19] Fourteen different companies purchased the auction envelopes.[20]
The 141 billion baht western extension consists of 86 billion baht for civil works, 14 billion for land appropriation and 31 billion for systems installation, rolling stock and maintenance. The winning bidder was announced by the MRTA on 9 September 2022 with BEM winning the right to build and run the extension over the ITD consortium.[21] However, continued litigation by the BTSC into 2023 has delayed the start of construction.
In November 2024,AECOM has been chosen by CH. Karnchang Plc (CK) is the lead designer for the western section, whileEgis is to offer project management and supervision services on a section.[22][23] EPC consultancy services were handled by Dorsch Gruppe and its Asian subsidiary, along with China Railway No. 2 Engineering Group Co., Ltd.[24]
Construction contracts were signed on 9 February 2017 between the MRTA and CKST Joint Venture consortium.[25] Construction finally started in June 2017 with a 1980 day construction period with a scheduled opening in October 2022.[26]
At the end of the year, 31 December 2017, progress of civil works construction was at 4.66% according to the MRTA.[27] By the end of July 2018, overall construction progress was 13.57%. By 30 September 2018, overall construction had progressed to 18.33%.[28] At the end of March 2019, construction had progressed to 32.12%.[29] At the end of July 2019, civil construction was at 42.27%.[30] At the end of October 2019, construction had progressed to 49.05%.[31]
At the end of January 2020, construction had progressed to 54.93%.[32] By the end of May 2020, construction had progressed to 62.42%.[33] On 5 October 2020, TBM number 2 finished tunneling and reached Ramkhamhaeng 12 station box as part of contract 2.[34] At the end of September 2020, was at 69.82%.[35]
At the end of January 2021, construction had progressed to 76.09%.[36] Construction progress was 81.03% by the end of April 2021.[37] Construction progress was 87.24% by the end of October 2021.[38] By the end of March 2022, construction progress was at 92.69%.[39] By the end of May 2022, construction had progressed to 94.51%.[40] As of March 23 2023, construction had progressed to 99.00%[41]
By the end of June 2023, construction had progressed to 100.00%.[42]
| Contract | Notes | Contractor(s) | Kilometre | Cost |
|---|---|---|---|---|
| E1 | OR13 Thailand Cultural Centre toOR16 Ramkhamhaeng 12 | CKST Joint Venture | 6.29 | ฿20,633.00 million |
| E2 | OR16 Ramkhamhaeng 12 toOR19 Hua Mak | 3.44 | ฿21,507.00 million | |
| E3 | OR19 Hua Mak toOR22 Klong Ban Ma | Italian-Thai Development | 4.04 | ฿18,570.00 million |
| E4 | OR22 Klong Ban Ma toOR29 Yaek Rom Klao | Unique Construction and Engineering | 8.8 | ฿9,990.00 million |
| E5 | Depot and Park & Ride | CKST Joint Venture | ฿4,831.24 million | |
| E6 | Track and Electrical | Unique Construction and Engineering | ฿3,690.00 million | |
| Total Budget | ฿79,221.24 million | |||
The Phase 2 Western extension of the Orange line will run from Thailand Cultural Centre to Bang Khun Non via Pratunam. The 13.4 km (8.3 mi) western section will run underground with 12 stations.
The Thai Cabinet was expected to approve the 121 billion baht budget for the Western extension in mid 2017 with a tender due for the 2nd half of 2017.[43] However, this decision was delayed until 2018 as Cabinet requested options to be considered for a joint public and private investment proposal.[44] There were further delays into 2019, but the MRTA finalised a joint PPP plan for Cabinet to approve in mid 2019.[45] On 28 January 2020, the Cabinet approved the 142 billion baht extension. It was originally expected to open in February 2026 and serve 439,000 passengers daily.[46][47]
On 3 July 2020, the MRTA released the tender for the design, construction and operation of the Western extension as a Public-Private Partnership project on a 30 year lease.[13] The tender deadline was 23 September 2020 with the successful bidder to be announced in early October 2020. The tender specified a construction period of three and a half years.
There were 10 tenderers that purchased the request for proposal (RFP) form with two major consortiums that submitted final bids:
However, in late August 2020 the tender submission deadline was subsequently delayed by the MRTA.[14] Thereafter, the MRTA amended the tender assessment criteria resulting in a lawsuit being lodged by the BTSC in the Administrative Court on 17 September 2020 with the Court imposing an injunction suspending the tender decision.[15] The tender was subsequently cancelled by the MRTA in February 2021 due to litigation by the BTSC.[16] After approval by the Administrative Court given ongoing litigation, a new tender issued in October has a deadline for bids of January 2022.[17]
The Criminal Court Corruption and Malfeasance division hearings into the cancelled tender process were conducted from 14 to 24 December 2021 and have delayed the reissued tender timeframe.[48] Subject to court approval, the MRTA planned to review all tender bids for a period of 3 months before seeking final Cabinet approval of the winning bid in April 2022. However, there are also construction budget concerns for the extension as steel prices have increased by 40% since the previous budget was approved.[49] The EIA for the western extension was also updated in December 2021 as Din Daeng station was moved north by 500m, Pracha Songkhro station was moved east by 450m and Yommarat station was redesigned.[citation needed]
The MRTA reissued the new tender auction on 24 May 2022 with tender packages available for purchase until 10 June.[19] The 141 billion baht western extension consists of 86 billion baht for civil works, 14 billion for land appropriation and 31 billion for systems installation, rolling stock and maintenance. The winning bidder was announced by the MRTA on 9 September 2022 with BEM winning the right to build and run the extension over the ITD consortium.[21]
On 18 July 2024, construction contracts were signed at the MRTA office. The Minister of Transport,Suriya Juangroongruangkit, instructedMRTA andBEM, the concession holder, to expedite the track and electrical works on the Orange Line's eastern section from theThailand Cultural Centre to Yaek Rom Klao for completion as soon as possible. The primary objective is to open the eastern section by early 2028, with the western section set to be completed ahead of schedule by November 2028. It was confirmed that the Orange Line’s maximum fare will be capped at 20 Baht or with a flat rate of 20 Baht for the entire route.[50]
| Contract | Notes | Contractor(s) | Kilometre (km) | Progress (June 2025) | Cost |
|---|---|---|---|---|---|
| 1 | OR02 Bang Khun Non toOR13 Thailand Cultural Centre | CKST-OL Consortium (consisting ofCH. Karnchang and STECON Group) | 13.1 | 11.87% | ฿82,501.869 million |
| 2 | M&E Works and Rolling Stocks | 5.61% | ฿26,714.000 million | ||
| Total Budget | 11.15%[citation needed] | ฿109,215.869 million | |||
On March 18, 2025, archaeologists made a remarkable discovery during an excavation at the construction site of Siriraj Station. Over 70 human skeletons were unearthed beneath the Arun Amarin Bridge, oppositeWat Amarin, along with a large ceramic jar containing cremated bone fragments. This discovery, made as part of a mandated archaeological survey by theFine Arts Department prior to theSiriraj hospital expansion, has drawn significant attention from historians and researchers.
The burials show unique and previously unrecorded characteristics in Thai archaeology: bodies were laid in an extended position with slightly bent legs, heads oriented westward, and faces tilted southward. Some of the remains were found in alarming postures with hands and feet bound behind their backs, suggesting possiblemass execution.
Preliminary assessments date the remains to approximately 200–500 years ago, potentially linking them to theThonburi period. Experts speculate that this site may be tied to mass executions during the turbulent years before the establishment ofBangkok as the capital in 1782. However, further bone dating and DNA testing are required to confirm the period and possible links to pre-Rattanakosin communities.
The site itself lies within a historically significant area once part of Wang Lang Palace , built around 200 years ago, and may overlap with an ancient settlement dating back 2,000–3,000 years. The discovery of numerous cremation jars alongside the skeletons suggests complex and varied mortuary practices, indicating cultural and ritual significance.
TheMass Rapid Transit Authority of Thailand has confirmed the site is under continued investigation by theFine Arts Department. If further research verifies early historical connections, the discovery could significantly reshape the understanding ofThonburi’s andBangkok’s origins.[51]
The tender for operation of the line and purchase of rolling stock for both the eastern and western sections was issued in May 2022, along with the construction of the western section.[52] However, it was delayed due to the ongoing litigation regarding the western extension, and the tender was suspended. In July 2024, it was announced at the signing ceremony of the joint investment contract for the Orange Line that they planned to have 32 electric trains, each with three carriages.[53]
In October 2024,BEM has concluded its selection by choosingSiemens as the manufacturer for the Orange Line trains.[54] The turnkey contract was announced on December 18, 2024. A consortium consisting of Siemens,Bozankaya, andST Engineering Thailand won a contract from Ch. Karnchang. The contract includes the supply of 32Siemens three-car trains, with the configuration and design same as the EMU-BLE fleet used on theMRT Blue Line in Bangkok. These trains will be manufactured at the Bozankaya Factory in Ankara,Turkey. Siemens and ST Engineering will supply the bogies, traction, braking, auxiliary systems, and SCADA system for the project, and will be responsible for project management, development, construction, and commissioning. Siemens will also provide service and maintenance for 10 years.[55]
| Code | Station Name | Opened | Platform Type | Position | Park &Ride | Transfer | Notes | |
|---|---|---|---|---|---|---|---|---|
| English | Thai | |||||||
| Taling Chan - Bang Khun Non: 4.54 km(Future) | ||||||||
| OR01 | Taling Chan | ตลิ่งชัน | TBA | Island | Underground | - | Connecting station to; • BTS (1 km walking distance;future)• SRT •SRT Southern Line | Appeared on the 2022 Final Reports.[56] |
| Bang Khun Non - Thailand Cultural Centre: 13.2 km(Under construction) | ||||||||
| OR02 | Bang Khun Non | บางขุนนนท์ | November 2030; 4 years' time (2030-11) | Island | Underground | - | Connecting station to; • MRT • SRT (future) | |
| OR03 | Siriraj | ศิริราช | Stacked | - | Connecting station with SRT (future) | Exit toSiriraj Hospital. | ||
| OR04 | Sanam Luang | สนามหลวง | Island | - | Exit to: •Sanam Luang •The Grand Palace •Khaosan Road •National Theatre | |||
| OR05 | Democracy Monument | อนุสาวรีย์ประชาธิปไตย | Island | - | Interchange station to MRT (under construction) | Exit to: • Mahakan fort • Rattanakosin Exhibition Hall •Queen Sirikit Gallery • Royal Pavilion Mahajetsadabadin •Wat Saket. | ||
| OR06 | Lan Luang | หลานหลวง | Island | - | ||||
| OR07 | Yommarat | ยมราช | Island | - | Connecting station to SRT (future) | |||
| OR08 | Ratchathewi | ราชเทวี | Island | - | Connecting station to BTS | |||
| OR09 | Pratunam | ประตูน้ำ | Stacked | - | Exit to: •Embassy of Indonesia •Pratunam • Platinum Fashion Mall. | |||
| OR10 | Ratchaprarop | ราชปรารภ | Stacked | - | Connecting station to • • SRT (future) •SRT Eastern Line | Exit to: •Pratunam Market • Indra Square •Baiyoke Tower. The station site has been moved 300 meters north to replace Rangnam station.[56] | ||
| OR11 | Din Daeng | ดินแดง | Island | - | Exit to Bangkok City Hall 2. | |||
| OR12 | Pracha Songkhro | ประชาสงเคราะห์ | Side | - | Connecting station to MRL (future) | |||
| Thailand Cultural Centre - Yaek Rom Klao: 21.04 km(Structure Complete) | ||||||||
| OR13 | Thailand Cultural Centre | ศูนย์วัฒนธรรมแห่งประเทศไทย | May 2028; 2 years' time (2028-05) | Side | Underground | √ | Interchange station to MRT | Exit to: • The One Ratchada Market • Esplanade Ratchada • The Street Ratchada • China Cultural Centre •Thailand Cultural Centre. |
| OR14 | MRTA | รฟม. | Island | - | Exit toRoyal City Avenue (RCA). | |||
| OR15 | Wat Phra Ram 9 | วัดพระราม 9 | Stacked | - | Connecting station to MRL (future) | Formerly Pradit Manutham. | ||
| OR16 | Ramkhamhaeng 12 | รามคำแหง 12 | Stacked | - | Exit toThe Mall Ramkhamhaeng. | |||
| OR17 | Ramkhamhaeng University | มหาวิทยาลัยรามคำแหง | Stacked | - | Exit toRamkhamhaeng University. Formerly Ramkhamhaeng. | |||
| OR18 | SAT | กกท. | Island | - | Exit to: • Hua Mak Sports Complex (which includes the head office of SAT (Sports Authority of Thailand) ,Rajamangala Stadium andIndoor Stadium Huamark) | |||
| OR19 | Ramkhamhaeng 40 | รามคำแหง 40 | Island | - | Formerly Hua Mak and Ramkhamhaeng 34.[57] | |||
| OR20 | Yaek Lam Sali | แยกลำสาลี | Island | - | Connecting station to; • MRT • MRT (future) | Formerly Lam Sali. | ||
| OR21 | Si Burapha | ศรีบูรพา | Island | - | ||||
| OR22 | Khlong Ban Ma | คลองบ้านม้า | Side | √ | ||||
| OR23 | Sammakorn | สัมมากร | Side | Elevated | - | |||
| OR24 | Nom Klao | น้อมเกล้า | Side | - | ||||
| OR25 | Rat Phatthana | ราษฎร์พัฒนา | Side | - | ||||
| OR26 | Min Phatthana | มีนพัฒนา | Side | - | ||||
| OR27 | Kheha Ramkhamhaeng | เคหะรามคำแหง | Side | - | ||||
| OR28 | Min Buri | มีนบุรี | Side | √ | Interchange station with MRT | |||
| OR29 | Yaek Rom Klao | แยกร่มเกล้า | Side | - | Formerly Suwinthawong. | |||
Note: In February 2020, the MRTA changed the names of 3 stationsOR19,OR20, andOR29.[58]
On 19 May 2025, a 50-year-old construction worker died after falling into a 19-metre-deep excavation shaft at the Lan Luang Station construction site in Bangkok. His body was recovered on 24 May, following five days of continuous search and recovery operations. The incident prompted an official investigation by the Mass Rapid Transit Authority of Thailand (MRTA) and reignited public concern over occupational safety and regulatory oversight on large-scale infrastructure projects.[59][60][61]