This articleneeds additional citations forverification. Please helpimprove this article byadding citations to reliable sources. Unsourced material may be challenged and removed. Find sources: "Offshore construction" – news ·newspapers ·books ·scholar ·JSTOR(March 2010) (Learn how and when to remove this message) |


Offshore construction is the installation of structures and facilities in a marine environment, usually for the production and transmission of electricity, oil, gas and other resources. It is also calledmaritime engineering.
Construction and pre-commissioning is typically performed as much as possible onshore. To optimize the costs and risks of installing large offshore platforms, different construction strategies have been developed.[1]
One strategy is to fully construct the offshore facility onshore, and tow the installation to site floating on its own buoyancy. Bottom founded structure are lowered to the seabed by de-ballasting (see for instanceCondeep orCranefree), whilstfloating structures are held in position with substantialmooring systems.[1]
The size of offshore lifts can be reduced by making the construction modular, with each module being constructedonshore and then lifted using acrane vessel into place onto the platform.[1] A number of very large crane vessels were built in the 1970s which allow very large single modules weighing up to 14,000 tonnes to be fabricated and then lifted into place.[citation needed]
Specialist floating hotel vessels known asflotels or accommodation rigs are used to accommodate workers during the construction and hook-up phases. This is a high cost activity due to the limited space and access to materials.[clarification needed]
Oil platforms are key fixed installations from which drilling and production activity is carried out.Drilling rigs are either floating vessels for deeper water orjack-up designs which are a barge with liftable legs.[2] Both of these types of vessel are constructed in marine yards but are often involved during the construction phase to pre-drill some production wells.
Other key factors in offshore construction are theweather windows which define periods of relatively light weather during which continuous construction or other offshore activity can take place.Safety of personnel is another key construction parameter, an obvious hazard being a fall into the sea from which speedy recovery in cold waters is essential.Environmental issues are also often a major concern, andenvironmental impact assessment may be required during planning.
The main types of vessels used forpipe laying are the "derrick barge (DB)", the "pipelay barge (LB)" and the "derrick/lay barge (DLB)" combination.Closed diving bells in offshore construction are mainly used forsaturation diving in water depths greater than 120 feet (40 m), less than that, the surface oriented divers are transported through the water in awet bell ordiving stage (basket), a suspended platform deployed from alaunch and recovery system (LARS, or "A" frame) on the deck of the rig or adiving support vessel. The basket is lowered to the working depth and recovered at a controlled rate for decompression.Closed bells can go to 1,500 feet (460 m), but are normally used at 400 to 800 feet (120 to 240 m).[3]
Offshore construction includesfoundations engineering, structural design, construction, and/or repair of offshore structures, both commercial and military.[1]