High Speed 2 (HS2) is ahigh-speed railway which has been under construction in England since 2019. The planned route of the line is betweenHandsacre, in southernStaffordshire, andLondon, with abranch toBirmingham. HS2 is to be Britain's second purpose-builthigh-speed railway afterHigh Speed 1, which connects London to theChannel Tunnel. London and Birmingham are to be served directly by new high-speed track, and services toGlasgow,Liverpool andManchester are to use a mix of new high-speed track and the existingWest Coast Main Line. The majority of the project was planned to be completed by 2033, but this was delayed in 2025 with no new completion date given.
The new track is being constructed betweenLondon Euston and Handsacre, nearLichfield in southern Staffordshire, where a junction will connect HS2 to the West Coast Main Line. New stations are planned atOld Oak Common in northwest London,Birmingham Interchange nearSolihull, andBirmingham city centre.The trains are being designed to reach a maximum speed of 360 km/h (220 mph) when operating on HS2 track, dropping to 200 km/h (125 mph) on conventional track.
The length of the new track has been reduced substantially since it was first announced in 2013. It was originally to split into eastern and western branches north of Birmingham Interchange. The eastern branch would have connected to theMidland Main Line atClay Cross inDerbyshire and theEast Coast Main Line south ofYork, with a branch to a terminus inLeeds. The western branch would have connected to the West Coast Main Line at Crewe and south ofWigan, with a branch to a terminus in Manchester. Between November 2021 and October 2023 the project was progressively cut until only the London to Handsacre and Birmingham section remained. Work on the section between Birmingham and Handsacre was deferred for four years in October 2025, as part of the project's reset.
The project has bothsupporters andopponents. Supporters believe that the additional capacity provided will accommodate passenger numbers rising to pre-COVID-19 levels while driving a furthermodal shift to rail. Opponents believe that the project is neither environmentally nor financially sustainable.

In 2003 modernhigh-speed rail arrived in the United Kingdom with the opening of the first part ofHigh Speed 1 (HS1), then known as the 67-mile-long (108 km) Channel Tunnel Rail Link between London and theChannel Tunnel. In 2009 theDepartment for Transport (DfT) under theBrown ministry proposed to assess the case for a second high-speed line, which was to be developed by a new company,High Speed Two Limited (HS2 Ltd).[7]
In December 2010, following a review by theConservative–Liberal Democrat coalition,[8] a route was proposed, subject to public consultation,[9][10] based on a Y-shaped route from London toBirmingham with branches toLeeds andManchester, as originally put forward by the previous Labour government,[11] with alterations designed to minimise the visual, noise, and other environmental impacts of the line.[9]
In January 2012 theSecretary of State for Transport announced that HS2 would go ahead in two phases and the legislative process would be achieved through twohybrid bills.[12][13] TheHigh Speed Rail (London - West Midlands) Act 2017, authorising the construction of Phase 1, passed both Houses of Parliament and received Royal Assent in February 2017.[14] A Phase 2aHigh Speed Rail (West Midlands - Crewe) Bill, seeking the power to construct Phase 2 as far as Crewe and to make decisions on the remainder of the Phase 2b route, was introduced in July 2017.[15] Phase 2a received royal assent in February 2021.[16] TheHigh Speed Rail (Crewe - Manchester) Bill forPhase 2b was paused under theSunak ministry.[17]
One of the stated aims of the project is to increase the capacity of the railway network. It is envisaged that the introduction of HS2 will free up space on existing railway lines by removing a number of express services, thus allowing additional local train services to accommodate increased passenger numbers.[18]Network Rail considered that constructing a new high-speed railway will be more cost-effective and less disruptive than upgrading the existing conventional rail network.[19] The DfT has forecast that improved connectivity will have a positive economic impact, and that favourable journey times and ample capacity will generate a modal shift from air and road to rail.[5]
On 21 August 2019 the DfT ordered anindependent review of the project. The review was chaired byDouglas Oakervee, a Britishcivil engineer, who had been HS2's non-executive chairman for nearly two years.[20][21] The review was published by the DfT on 11 February 2020, alongside a statement from theprime minister confirming that HS2 would go ahead in full, with reservations.[22][23] Oakervee's conclusions were that the original rationale for HS2—to provide capacity and reliability on the rail network—was still valid, and that no "shovel-ready" interventions existed that could be deployed within the timeframe of the project. As a consequence, Oakervee recommended that the project go ahead as planned, subject to a series of further recommendations. After concluding that the project should proceed, the review recommended a further review of HS2 that would be undertaken by theInfrastructure and Projects Authority (IPA) and would concentrate on reducing costs and over-specification.[24]
On 15 April 2020 formal approval was given to construction companies to start work on the project.[25]
On 18 November 2021 the government's delayed Integrated Rail Plan was published.[26] It significantly affected parts of the HS2 programme, including curtailing much of the eastern leg.
Under the original proposal for the eastern leg, the high-speed line would have been built with a link to theEast Coast Main Line south of York for trains to continue to Newcastle. A branch would take trains into Leeds. There would also have been a branch to theMidland Main Line north of Derby for trains to continue to Sheffield. The original scheme also included a through station atToton, between Nottingham and Derby. The HS2 eastern section was largely eliminated, leaving a branch fromColeshill near Birmingham to East Midlands Parkway station, just south of Nottingham and Derby, where the HS2 track would end, with trains continuing north onto the Midland Main Line to serve the existing stations at Nottingham, Derby, Chesterfield, and Sheffield. HS2 trains with high speed track and conventional track operation would serve the centres of Nottingham and Derby, unlike in the previous proposal.
Upgrades to the East Coast Main Line were proposed to offer time improvements on the London to Leeds and Newcastle routes. Services from Birmingham to Leeds and Newcastle were planned to use the remaining section of the HS2 eastern leg. The London to Sheffield service would remain on the Midland Main Line, equalling the proposed original HS2 journey times. The integrated Rail Plan proposed a study to determine the best method for HS2 trains to reach Leeds.
In June 2022 theGolborne spur was removed from the Crewe-to-Manchester Parliamentary Bill.[27][28] Without this link, trains to Scotland would join theWest Coast Main Line further south at Crewe, instead of nearWigan. The Department for Transport stated that the government was considering the recommendations of the Union Connectivity Review, which gave alternatives such as a more northerly HS2 connection to the West Coast Main Line than Golborne and upgrades to the West Coast Main Line from Crewe toPreston.[27][29]
In July 2023 the Infrastructure and Projects Authority gave a red rating to the first two phases of the HS2 project, which it defined to mean: "Successful delivery of the project appears to be unachievable. There are major issues with project definition, schedule, budget, quality and/or benefits delivery, which at this stage do not appear to be manageable or resolvable. The project may need re-scoping and/or its overall viability reassessed." HS2 Ltd's chief executiveMark Thurston announced his resignation on 13 July.[30]
In October 2023 the prime minister,Rishi Sunak, announced at theConservative Party Conference that Phase 2 would be abandoned. The cancellation left a new high-speed track from London to Handsacre, northeast of Birmingham, with a branch to central Birmingham.[31] The construction of Euston station would depend on private sector funding: if funding was secured for the station access tunnel, construction would be the responsibility of HS2 Ltd.[32][33] Euston station was initially proposed to have 11 platforms to accommodate HS2 trains. There is a reduction to six platforms, as a proposal from October 2023 will cap the throughput to 9–11 trains per hour, rather than the 18 of which the HS2 track would otherwise be capable.[34][35]
Sunak said the £36 billion saved by not building the northern leg of HS2 would instead be spent on roads, buses and railways in every region of the country, under the title "Network North." The locations of these projects would range from southern Scotland toPlymouth. Money would be distributed in the North, Midlands and South of England according to where the reduction of costs (not benefits) would lie.[36] Around 30 per cent of the cost savings would be spent on railway projects.[37] After it was found that the list of projects included schemes that had already been built or were swiftly deleted, Sunak said the list was intended to provide illustrative examples.[38]
The House of CommonsPublic Accounts Committee, in a January 2024 report, in relation to the revised planned route,[39] stated "HS2 now offers very poor value for money to the taxpayer, and the Department [for Transport] and HS2 Ltd do not yet know what it expects the final benefits of the programme to be".[40] In January 2024 theleader of the opposition,Keir Starmer, said it would not be possible for any future Labour government to reinstate Phase 2, since contracts would have been cancelled.[41] This was confirmed in April 2024 byLouise Haigh, the shadow transport minister.[42]
In December 2024, the DfT stated there will be no WCML extensions from HS2 until the current project is completed.[43] The same month, Mark Wild was appointed as chief executive of High Speed Two Limited, and he undertook a thorough assessment of the programme. On 31 March 2025, he wrote to the Transport SecretaryHeidi Alexander, highlighting that "the organisation has failed in its mission to control costs and deliver to schedule" and summarising the overall situation as unsustainable.[44][45] He stated there was no reliable earned value to date measure, and estimated the programme was currently about one third complete compared to the planned three-quarters complete.[46]
He noted external events contributing to this – the COVID-19 pandemic, Brexit and the Russian invasion of Ukraine – but attributed the failure to three primary issues, briefly summarised as:[46][45]
This was followed by the Stewart Review, primarily into HS2 corporate governance and management, published on 18 June 2025. Amongst its conclusions, it stated "The top-down vision of building a railway that would be the best and fastest has been a major factor in undermining attempts to introduce a culture of cost control" and that the project had been "subject to evolving political aims, which pushed forward on the schedule before there was sufficient design maturity and caused progressive removals of scope".[47][48]
The same day the Transport Secretary made a statement to parliament accepting all the Stewart recommendations and calling the current situation "an appalling mess". She concluded that meeting the 2033 project end date was impossible, and that "Billions of pounds of taxpayers’ money has been wasted by constant scope changes, ineffective contracts and bad management". In future the project's priority would be to build at the lowest reasonable cost, even if this took longer.[49][50] She confirmed thattunneling to the Euston terminus would go ahead, but she did not choose the design for the station, though noted that the two "failed designs" had cost over £250 million.[47][50]
Work between Birmingham and Handsacre in Staffordshire was further deferred for four years in October 2025 as part of the project's reset; the work had already been paused in early 2023 in an attempt to control costs. Consequently, HS2 services would not extend onto the conventional rail network on opening. HS2 states it remains committed to the 18 mi (29 km) connection.[51]

HS2 parallels the West Coast Main Line (WCML), merging with the WCML at Handsacre. The line will be betweenEuston railway station in London and a junction with the WCML outside the village of Handsacre north of Lichfield inStaffordshire. There will be a branch to a new station atBirmingham Curzon Street.[52] There will also be new stations atOld Oak Common, in northwest London, andBirmingham Interchange, nearSolihull.[53] The section between Old Oak Common and the West Midlands is scheduled to open around 2030, with the link to Euston following between 2031 and 2035.[54] The high speed track, including the branch to Birmingham, is 225 kilometres (140 mi) long.[55][56][5] It is flanked by the WCML and theChiltern Line.
Upon opening, HS2 and West Coast Main Line compatible trains will operate from London, reaching Birmingham in 49 minutes and Birmingham Interchange in 38 minutes. Trains will journey to other destinations on a mix of HS2 and conventional track. Journeys to Liverpool will take 1 hour 50 minutes, to Glasgow 4 hours, and to Manchester 1 hour 40 minutes.[needs update] Trains will progress on HS2 track to Handsacre, then use the West Coast Main Line.[57][58]
The route to the north begins at Euston station in London, entering a twin-bore tunnel near the Mornington Street Bridge at the station's throat. After continuing through to the Old Oak Common station, trains proceed through a second, 8-mile (13 km) tunnel, emerging at its northwestern portal.[59] The line crosses theColne Valley Regional Park on theColne Valley Viaduct and then enters a 9.8-mile (15.8 km) tunnel under theChiltern Hills, to emerge nearSouth Heath, northwest ofAmersham. The route will roughly parallel theA413 road and theLondon to Aylesbury Line, to the west ofWendover. This is a greencut-and-cover tunnel under farmland, with soil spread over the final construction in order to reduce visual impact and noise, and allow use of the land above the tunnels for agriculture.[60] After passing west ofAylesbury, the route will pass through the corridor of the formerGreat Central Main Line, joining the alignment north ofQuainton Road to travel through rural Buckinghamshire and Oxfordshire up toMixbury, south ofBrackley, from where it will cross theA43 and open countryside through South Northamptonshire and Warwickshire, passing immediately south ofSoutham. After progressing through a tunnel bored underLong Itchington Wood, the route will pass through rural areas betweenKenilworth andCoventry, crossing theA46 to enter the West Midlands.
Birmingham Interchange Station will be on the outskirts of Solihull, close to the strategic road network, including theM42,M6,M6 toll andA45. These roads will be crossed on viaducts. The station is adjacent to Birmingham Airport and the National Exhibition Centre. North of the station west of Coleshill there will be a complex triangular branch junction, with six tracks at one section, which will link the HS2 Birmingham city centre spur with the main spine. The spine continues north from the branch to the northerly limit of the high speed track which is a connection onto the WCML at Handsacre. The Birmingham city centre spur will be routed along theWater Orton rail corridor, theBirmingham to Derby line throughCastle Bromwich and through a tunnel pastBromford.[citation needed]
A key feature of the HS2 proposals is that the new high-speed track will be connected to the existing West Coast Main Line track at Handsacre, north of Birmingham, taking trains north on the existing track. This is the only connection between the new and existing track. This connection allows HS2 services to serve the cities of Liverpool, Manchester and Glasgow on a mix of new high-speed track and the existing West Coast Main Line. Purpose-built trains will be capable of operating on new and existing tracks.[61][62][63]

HS2 is to share a southern terminus with the West Coast Main Line at London Euston, which is to be remodelled to integrate six new HS2 platforms and concourse with the current conventional rail station.[64] There will be an improved connection to the adjacentEuston Square tube station, which serves theCircle,Hammersmith & City andMetropolitan lines.[65]
In October 2018 demolition began on the formercarriage sheds at Euston station. This was to allow the start of construction at the throat of the station at Mornington Street Bridge.[66][67] In January 2019 thetaxi rank at Euston was moved to a temporary site at the front of the station so that demolition of the One Euston Square and Grant Thornton House tower blocks could commence. The demolition period was scheduled to last ten months.[68] In June 2020, workers finished the demolition of the western ramp and canopy of the station. This part of the station had housed theparcels depot, which fell into disuse after parcel traffic shifted to being serviced by road.[69][70]
In March 2023 the government postponed works on Euston station, saying that this was necessary to "manage inflationary pressures and work on an affordable design for the station". Delivery of services between Birmingham and Old Oak Common would instead be prioritised, with the Elizabeth line providing passenger transfer between Old Oak Common and central London until at least 2035, the earliest time at which Euston would be available under the new plans.[71]

Old Oak Common station, betweenPaddington andActon Main Line station, is under construction and scheduled to be completed before Euston. It will be the temporary London terminus of HS2 until Euston is completed. There will be connections with theElizabeth line,Heathrow Express toHeathrow Airport, and theGreat Western Main Line toReading,South West England andSouth Wales.[72] Old Oak Common railway station will also be connected, viaout of station interchanges, withLondon Overground stations atOld Oak Common Lane on theNorth London line andHythe Road on theWest London line.[73][74] Construction ofOld Oak Common station began in June 2021.[75]

Birmingham Interchange will be a through station situated in suburban Solihull, within a triangle of land enclosed by the M42,A45 andA452 highways. Apeople mover with a capacity of over 2,100 passengers per hour in each direction will connect the station to theNational Exhibition Centre,Birmingham Airport and the existingBirmingham International railway station.[76][77] TheAirRail Link people-mover already operates between Birmingham International station and the airport. In addition, there is a proposal to extend theWest Midlands Metro to serve the station.[78]
In 2010 Birmingham Airport's chief executive, Paul Kehoe, stated that HS2 is a key element in increasing the number of flights using the airport, with added patronage by inhabitants of London and theSouth East, as HS2 will reduce travel times from London to Birmingham Airport to under 40 minutes.[79]
Birmingham Curzon Street will be the terminal station at the end of a branch that connects to the HS2 spine via a junction at Coleshill.[80] Astation of the same name existed on the Curzon Street site between 1838 and 1966; the survivingGrade I listed station building will be retained and renovated.[81]
The site is immediately adjacent toMoor Street station, and approximately 400 metres (0.25 mi) northeast ofNew Street station, which is separated from Curzon and Moor streets by theBull Ring. Passenger interchange with Moor Street would be at street level, across Moor Street Queensway; interchange with New Street would be via a pedestrian walkway between Moor Street and New Street (opened in 2013).[82][83][84] In September 2018, one of Birmingham's oldest pubs, theFox and Grapes, was demolished to make way for the new developments.[85] TheWest Midlands Metro will be extended to serve the station.[86]
Development planning for the Fazeley Street quarter of Birmingham has changed as a result of HS2. Prior to the announcement of the HS2 station,Birmingham City University had planned to build a new campus inEastside.[87][88] The proposed Eastside development will now include a new museum quarter, with the original station building becoming a new museum of photography, fronting onto a new Curzon Square, which will also be home toIkon 2, a museum of contemporary art.[89]
Clearing the site for construction commenced in December 2018.[90][91]Grimshaw Architects received planning permission for three applications in April 2020. The new station is expected to have a zero-carbon rating and over 2,800 square metres (30,000 sq ft) of solar panels.[81]
The plan makes provision for HS2 service passenger interchanges to the Elizabeth line and Great Western Main Line atOld Oak Common station.[92] At Euston station, passenger interchanges will be possible on foot to the West Coast Main Line andLondon Underground ("Tube") services via the adjacentEuston tube station and Euston square tube station.[citation needed] TheWest Midlands Metro, a tram service, is to serve Birmingham Curzon Street station, providing access to onward services fromBirmingham Snow Hill, Birmingham New Street andWolverhampton.[citation needed]

The main stages of construction officially began on 4 September 2020,[93] following previous delays. Thecivil engineering aspect of the construction of Phase 1 is worth roughly £6.6 billion, with preparation including over 8,000 boreholes for ground investigation.[94] As of March 2025, no track had been laid, and approximately one third of the civil engineering construction work had been completed (of a planned 70-80 percent).[95] £40.5 billion had been spent on the project overall up to April 2025.[96]
As of October 2025, civil works are expected to be completed within four years, to be followed by installation of the rail systems.[97]
| Name | Coordinates | OS Coordinates |
|---|---|---|
| Colne Valley Viaduct | 51°35′09″N0°29′24″W / 51.5859°N 0.4900°W /51.5859; -0.4900 (Colne Valley Viaduct) | TQ04608858 |
| Wendover Dean Viaduct | 51°44′14″N0°43′22″W / 51.7371°N 0.7228°W /51.7371; -0.7228 (Wendover Dean Viaduct) | SP88180509 |
| Small Dean Viaduct | 51°45′00″N0°44′12″W / 51.7500°N 0.7368°W /51.7500; -0.7368 (Small Dean Viaduct) | SP87190651 |
| Thame Valley Viaduct | 51°49′25″N0°51′48″W / 51.8237°N 0.8633°W /51.8237; -0.8633 (Thame Valley Viaduct) | SP78331456 |
| Turweston Green Bridge | 52°02′47″N1°07′49″W / 52.0465°N 1.1304°W /52.0465; -1.1304 (Turweston Green Bridge) | SP59633908 |
| Balsall Common Viaduct | 52°23′49″N1°38′28″W / 52.3970°N 1.6412°W /52.3970; -1.6412 (Balsall Common Viaduct) | SP24417777 |
| Marston Box Rail Bridge | 52°32′51″N1°43′05″W / 52.5475°N 1.7181°W /52.5475; -1.7181 (Marston Box Rail Bridge) | SP19119448 |
| Aston Church Road Overbridge | 52°29′54″N1°51′26″W / 52.4983°N 1.8571°W /52.4983; -1.8571 (Aston Church Road Overbridge) | SP09708898 |
There are five twin-bore tunnel sections on the route from London to Birmingham. TheEuston tunnel will take passengers from Euston railway station to Old Oak Common station. TheNortholt tunnel covers the area between Old Oak Common and theColne Valley Viaduct in West Ruislip. TheChiltern tunnel is the longest tunnel on the route and travels 10 miles (16 km) underneath theChiltern Hills. The Long Itchington Wood tunnel is the shortest on the route and will take passengers underneath an ancient woodland. TheBromford tunnel will take trains intoBirmingham city centre.
| Tunnel | Name | Launch Date | Arrival Date | Digging Time | Distance Travelled | Ref. |
|---|---|---|---|---|---|---|
| Euston Tunnel | Karen | TBD | TBD | TBD | TBD | |
| Madeline | TBD | TBD | TBD | TBD | ||
| Northolt Tunnel West | Sushila | 6 Oct 2022 | 19 Dec 2024 | 2 years, 75 days | 8 km (4.97 mi) | |
| Caroline | 27 Oct 2022 | 3 Apr 2025 | 2 years, 159 days | 8 km (4.97 mi) | [98] | |
| Northolt Tunnel East | Emily | 25 Feb 2024 | 6 Jun 2025 | 1 year, 102 days | 5.5 km (3.42 mi) | [99] |
| Anne | 9 Apr 2024 | 26 Jun 2025 | 1 year, 79 days | 5.5 km (3.42 mi) | [100] | |
| Chiltern Tunnel | Florence | 13 May 2021 | 27 Feb 2024 | 2 years, 291 days | 16 km (9.94 mi) | [101] |
| Cecilia | 5 Jul 2021 | 21 Mar 2024 | 2 years, 261 days | 16 km (9.94 mi) | [102] | |
| Long Itchington Wood Tunnel | Dorothy | 2 Dec 2021 | 26 Jul 2022 | 237 days | 1.6 km (0.99 mi) | |
| 25 Nov 2022 | 30 Mar 2023 | 126 days | 1.6 km (0.99 mi) | [103] | ||
| Bromford Tunnel | Mary Ann | 14 Aug 2023 | 9 May 2025 | 1 year, 269 days | 5.8 km (3.60 mi) | [104] |
| Elizabeth | 6 Mar 2024 | 13 Oct 2025 | 1 year, 222 days | 5.8 km (3.60 mi) | [105][106] |
In April 2023, HS2 announced that work on the 4.5-mile-long (7.2 km) Euston tunnels linking Old Oak Common to Euston was being deferred and that tunnel-boring had been rescheduled to start in summer 2025.[107][108] In October 2023 the Government announced that any Euston terminus would not be government-funded.[109] However, in May 2024 the government was reportedly prepared to pay the upfront tunnelling cost of around £1 billion to avoid further costly delays to the project. It would then recoup costs from the wider development of the Euston station site.[110] In October 2024, the governement confirmed it would fund the tunnels.[111]
The 8.4-mile-long (13.5 km) Northolt tunnels were constructed with fourtunnel boring machines (TBM); two tunnelling West to East and two tunnelling East to West, which met in the middle. TBMSushila andCaroline, the first two of the four TBMs to be used, were launched from the West Ruislip portal in October 2022. The third launched in February 2024 and the fourth followed in April 2024, with all the tunnels finished by June 2025.[112][113][114]
The 10-mile-long (16 km) Chiltern tunnels were scheduled to take three years to dig, using two 2,000-tonne (2,000-long-ton; 2,200-short-ton) TBMs.[115] In July 2020, work was completed on a 17-metre (56 ft)-high headwall at the southern portal of the twin-bore tunnel.[116][117] The tunnels are lined with concrete that is cast in sections at a purpose-built facility at the southern portal; the first sections were cast in March 2021.[118] Tunnelling began in May 2021, with TBMFlorence, moving at a speed of up to 15 m (49 ft) per day.[117] The second TBM,Cecilia, was launched in July 2021.[119] Florence, the first of two TBMs, completed tunnelling and broke through in late February 2024,[120] and in March 2024, the second TBM, Cecilia, completed tunnelling.[121]
In December 2021 TBMDorothy was launched, tunnelling for 1-mile (1.6 km) under Long Itchington Wood. It completed the first bore in July 2022, and was returned to its initial position to complete the second, parallel bore.[122][123]Dorothy started the second bore in November 2022, and finished it in March 2023.[124][125]
The 3.6-mile-long (5.8 km) Bromford tunnels fromWater Orton inNorth Warwickshire to Birmingham are being bored by TBMsMary Ann andElizabeth.Mary Ann started tunnelling in August 2023 and completed in May 2025, whileElizabeth started in March 2024 and will finish in autumn 2025.[126]
Earlier government proposals were that by 2033 HS2 would provide up to 18 trains an hour to and from London.[127] The 2020 business case contained a suggested service pattern, although this was never finalised. Some services were to operate as two connected units that would be subsequently detached to serve multiple northern destinations.[128]
This section needs to beupdated. The reason given is: HS2 phases 2A and 2B have been cancelled. Please help update this article to reflect recent events or newly available information.(October 2023) |

After an initial period with reduced services north from Old Oak Common, a full nine-train-per-hour service from London Euston was proposed to operate after the opening of Phase 1.
| Route | tph | Calling at | Train length |
|---|---|---|---|
| London Euston –Birmingham Curzon Street | 3 | Old Oak Common,Birmingham Interchange | 400 m |
Speaking in the House of Lords in December 2024, Rail Minister Lord Hendy stated that HS2 services had not been determined or finalised and that Euston Station will have six HS2 platforms.[129] This is also in view of potentially upgrading Pendolino trains to 155 mph (249 km/h) for use on HS2 and WCML track to improve end-to-end times as suggested by rail consultants. Pendolino trains have a life limit of 2046 with upgrades.
The ongoing servicing and maintenance of HS2 was initially included within theWest Coast Partnershipfranchise, which was awarded toAvanti West Coast—a joint venture betweenFirstGroup andTrenitalia—when the franchise commenced in December 2019. Avanti West Coast would have been responsible for maintaining all aspects of the service, including ticketing, trains, and the maintenance of the infrastructure.[130][131] Following the2024 general election, the Labour party committed itself to ending thefranchise model and renationalising operators. Avanti West Coast's contract is not planned to be extended beyond the end of its core term on 18 October 2026.[132]
The government has stated that it would "assume a fares structure in line with that of the existing railway", and HS2 should attract sufficient passengers to not have to charge premium fares.[133] Paul Chapman, in charge of HS2's public relations strategy, suggested that there could be last-minute tickets sold at discount rates. He said, "when you have got a train departing on a regular basis, maybe every five or ten minutes, in that last half-hour before the train leaves and you have got empty seats...you can start selling tickets for £5 and £10 at a standby rate."[134]
This section needs to beupdated. The reason given is: reflecting the October 2023 cancellation of the whole of Phase 2. Please help update this article to reflect recent events or newly available information.(March 2025) |
| Type | Current capacity | Capacity post‑HS2 |
|---|---|---|
| Slow commuter | 3,900 | 6,500 |
| Fast commuter | 1,600 | 6,800 |
| Intercity | 5,800 | 1,800 |
| High-speed | 0 | 19,800 |
| Total | 11,300 | 34,900 |
HS2 was planned in the 2010s to carry up to 26,000 people per hour.[12][136] The line would be used intensively, with up to 17 trains per hour travelling to and from Euston. As all trains would be capable of the same speed, capacity is increased as faster trains will not need to reduce speed for slower freight and commuter trains.
By diverting the fastest services to HS2, capacity is released on the West Coast Main Line, allowing for more slow freight trains, local, regional, and commuter services.[137] Andrew McNaughton, Chief Technical Director, said, "Basically, as a dedicated passenger railway, we can carry more people per hour than two motorways. It's phenomenal capacity. It pretty much triples the number of seats long-distance to the North of England".[138]
The DfT report on High Speed Rail published in March 2010 sets out the specifications for a high-speed line. It will be built to a Continental Europeanstructure gauge (as was HS1) and will conform toEuropean Union technical standards for interoperability for high-speed rail.[139] HS2 is being built with aUIC GC loading gauge (also assumed for passenger capacity estimations)[140] with a maximum design speed of 400 km/h (250 mph).[141] Initially, trains would reach a maximum speed of 360 km/h (225 mph).[142]
Signalling will be based on theEuropean Rail Traffic Management System (ERTMS) with in-cab signalling, in order to resolve the visibility issues associated with lineside signals at speeds over 200 km/h (125 mph).ETCS Level 2 will be used on the line, withautomatic train operation (ATO) operating at GoA2 (Grade of Automation 2), where trains will be semi-automatic (on the HS2 line alone, with drivers operating the doors, driving the train if needed and handling emergencies).GSM-R will be used for operational communications.[143]
Electrification at25 kV 50 Hz AC will be provided by overhead lines, designed toSNCF Reseau's V360 standard, on licence to contractors.[144]
The line will use pre-castslab track on most open sections, with the Slab Track Austria system supplied byPORR, except in tunnels and stations where cast in situ track will be used.[143][145]
At first, platform height was to be 760 millimetres (2 ft 6 in), which is one of the European standard heights;[146] however, new HS2 stations will use a platform height of 1,115 millimetres (3 ft 7.9 in) to improve accessibility and allow for step-free, level access.[147] Trains continuing on to the conventional rail network will encounter platforms at the standard UK height of 915 millimetres (3 ft 0 in) with some variation.[148]

A procurement process was undertaken between 2017 and 2021 for the manufacture and maintenance of 54 high speed trains. Of five tenderers, a £1.97 billion contract was awarded to a joint venture betweenAlstom andHitachi Rail in December 2021. The contract covers design, construction and an initial 12-year maintenance period.[149] The trains will be based on an evolution of theZefiro V300 platform.[150]
Vehicle bodies will be welded and fitted out at the Hitachi facility inNewton Aycliffe,bogies will be manufactured at the Alstom facility in Crewe, and the final assembly of body, bogies, and other systems will take place at Alstom in Derby.[151] The design of the trains is still undergoing finalisation, with full production starting around 2027.[152]
Trains would have a maximum speed of at least 360 km/h (225 mph) and a length of 200 metres (660 ft); two units could be joined for a 400-metre (1,300 ft) train.[142]
In August 2025, HS2 Ltd confirmed it was working on options for a new operating model after the cancellation of phase 2, involving different lengths of rolling stock and no longer requiringplatform screen doors at its intermediate stations. However, the existing contract for 54 trains with Hitachi Rail and Alstom would not be amended.[153]
Alstom – together with Bombardier, the winner of the contract – proposed in October 2016 that HS2 "tilting trains" could operate on HS2 and on conventional tracks, to reduce end-to-end journey time, as speeds would rise when operating on conventional tracks.[154][155]
The 2010 DfT government command-paper explored requirements for the train design among its recommendations for design standards for the HS2 network. The paper addressed the particular problem of designing trains to continental European standards, which use taller and wider rolling stock, compared to the loading gauges that exist in the rail network in Great Britain, meaning both trains which would remain on the HS2 line, built to larger, continental European profile ('captive' trains), and smaller trains which could leave the line onto the existing network ('conventional-compatible' trains) were proposed.[156]
The DfT report also considered the possibility of "gauge clearance" work on non-high-speed lines as an alternative to conventional trains. This work would involve extensive reconstruction of stations, tunnels, and bridges, and the widening of clearances to allow continental European–profile trains to operate beyond the high-speed network. The report concluded that, although initial outlay on commissioning new rolling stock would be high, it would cost less than the widespread disruption of rebuilding large tracts of Britain's rail infrastructure.[142]
A rolling-stock depot will bebuilt in Washwood Heath, Birmingham.[157]
The infrastructure maintenance depot will be constructed roughly halfway along the route, north of Aylesbury, betweenSteeple Claydon andCalvert in Buckinghamshire. This site is adjacent to the intersection of HS2 and theEast West Rail route.[158]
This section needs to beupdated. The reason given is: relating to the Nov 2021 Integrated Rail Plan. Please help update this article to reflect recent events or newly available information.(November 2021) |
The DfT initially estimated the cost of the first 190-kilometre (120 mi) section, from London to Birmingham, at between £15.8 and £17.4 billion,[159] and the entire Y-shaped 540-kilometre (335 mi) network at between £30.9 and £36 billion,[160][159] not including the Manchester Airport station which would be locally funded.[161] In June 2013, the projected cost (in 2011 prices) rose by £10 billion, to £42.6 billion, with an extra £7.5 billion budgeted for rolling stock, for a total of £50.1 billion.[162] Less than a week later, it was revealed that the DfT had been using an outdated model to estimate the productivity increases associated with the railway.[163] In 2014, the most commonly cited cost applied to the project was £56.6 billion, which corresponds to the June 2013 funding package, as adjusted for inflation by theHouse of Lords' Economic Affairs Committee in 2015.[164] Over sixty years, the line was estimated to provide £92.2 billion of net benefits and £43.6 billion in new revenue. As a result, thebenefit–cost ratio of the project was then estimated to be 2.30; that is, it is projected to provide £2.30 of benefits for every £1 spent.[165]
Cost increases have led to reductions in the planned track; for instance, the link between HS1 and HS2 was later dropped on cost grounds.[166] In April 2016Sir Jeremy Heywood, a senior civil servant, was reviewing the HS2 project to trim costs and gauge whether the project could be kept within budget.[167][168] The cost of HS2 is around 25 per cent higher than the international average, which was blamed on the higher population density and cost of land, in a report byPwC. The costs are also higher because the line will be built directly into city centres instead of joining existing networks on the outskirts.[169] By 2019, Oakervee estimated that the projected cost, in 2019 prices, had increased from £80.7 billion to £87.7 billion—the budget in 2019 prices was at the time of the Oakervee Review only £62.4 billion—and the benefit–cost ratio had dropped to between 1.3 and 1.5.[22] Based on Oakervee's estimations, HS2 ranks as the most expensive high-speed railway (HSR) project and has the highest cost per kilometre in a database of 94 HSR projects.[170]Lord Berkeley, the deputy chair of the Oakervee Review, disagreed with Oakervee's findings and suggested that the cost of the project could now be as high as £170 billion.[171] As of 2020[update], the budget envelope set out by the DfT is £98 billion.[172] HS2 Ltd tapped into a £4.3 billion contingency fund to meet £1.7 billion of extra costs resulting from delays caused by theCOVID-19 pandemic.[173] The benefit cost ratio for the whole project was last officially estimated at 1.1 for the whole project in July 2022.[174][175]
Sources of funding other than central government have been mooted for additional links. The City of Liverpool, omitted from direct HS2 access, in March 2016 offered £2 billion to fund a link from the city to the HS2 backbone 20 miles (32 km) away.[176] HS2 received funding from theEuropean Union'sConnecting Europe Facility.[177]
£40.5 billion (nominal prices) had been spent on the whole project up to April 2025, as confirmed in a government report in July 2025.[178] The government allocated a further £25.3 billion to be spent on the project between 2026 and 2030.[179]
HS2's classification as an "England and Wales" project had been criticised by MPs,[180]Plaid Cymru[181] and pastWelsh Government ministers, arguing that HS2's classification over Wales has little justification. They argue this is because there is no dedicated high-speed or conventional infrastructure of HS2 planned in Wales and minimal HS2 services to the north of Wales. A DfT study detailed that HS2 was forecasted to have a "negativeeconomic impact on Wales", as well as onBristol in England.[citation needed]
Rail infrastructure is notdevolved to Wales, therefore devolved authorities are entitled to less of theBarnett Formula, when funding is increased to thedevolved administrations in proportion to an increase in funding for England or, in this case, England and Wales. The Welsh Government has stated that it wants its "fair share" from HS2's billions in funding, which the Welsh Government stated would be roughly £5 billion in 2020.[182] By February 2020 the Welsh government received £755 million in HS2-linked funding, with the UK Government stating it was "investing record amounts in Wales' railway infrastructure" and that the Welsh government has actually received a "significant uplift" in Barnett-based funding due to the UK Government's increased funding of HS2.[183]Simon Hart,Secretary of State for Wales, stated that Network Rail would invest £1.5 billion in Wales' railways between 2019 and 2024.[184]
Following the cancelling of Phase 2, Wales' estimated claim was reduced to £3.9 billion.Mark Drakeford while as First Minister considered legal action in the courts over the issue, however following his replacement, the Welsh Government dropped their calls for legal action. While in June 2024, the Welsh Government reduced the claimed figure to £350 million, stating difficulties with estimating the consequential. Labour'sShadow Secretary of State for Wales,Jo Stevens, claimed HS2 is "no longer in existence", when questioned on Wales' funding issue.[185]
In 2020, trains between north Wales and London take roughly 3 hours and 45 minutes, with HS2 set to decrease the travel time between Crewe and London by thirty minutes. However, with no confirmed services directly between Euston and north Wales, passengers could be required to change at Crewe, and use theNorth Wales Main Line between Crewe andHolyhead, where any improvements have failed to receive funding.[184]
The DfT study estimated that theSouth Wales economy could lose up to £200 million per year, due to theregion's "inferior transport infrastructure". The same study highlighted that north Wales could benefit from faster journey times and a potential boost for the region's economy, with the DfT forecasting a benefit of £50 million from HS2, although with a potential £150 million negative economic impact to Wales overall. First Minister of Wales Mark Drakeford described in a letter to Prime MinisterBoris Johnson thatWales' railway system has been "systematically neglected" and that HS2's funding further contributes to it. HS2 has increased calls for Wales' rail infrastructure to be fullydevolved, as it is in Scotland.[186]
In July 2021 theWelsh Affairs Committee advised that HS2 should be reclassified as an "England only" project, allowing Wales to be entitled to its Barnett Formula, in line with Scotland andNorthern Ireland; but the committee also called for the establishment of a "Wales Rail Board" instead of devolving rail infrastructure to Wales, and for the upgrading of the North Wales Main Line.[187][186]
A 2008 paper, "Delivering a Sustainable Transport System", identified fourteen strategic national transport corridors in England, and described the London – West Midlands – North West England route as the "single most important and heavily used" and also as the one which presented "both the greatest challenges in terms of future capacity and the greatest opportunities to promote a shift of passenger and freight traffic from road to rail".[188][189] The paper noted that railway passenger numbers had been growing significantly in recent years—doubling from 1995 to 2015[190]—and that the Rugby – Euston section was expected to have insufficient capacity sometime around 2025.[191] This is despite theWest Coast Main Line upgrade on some sections of the track—which was completed in 2008—lengthened trains, and an assumption that plans to upgrade the route withcab signalling would be realised.[192]
According to the DfT, the primary purpose of HS2 is to provide additional capacity on the rail network from London to the Midlands and North.[193] It says the new line "would improve rail services from London to cities in the North of England and Scotland,[194] and that the chosen route to the west of London will improve passenger transport links toHeathrow Airport".[195][verify] Additionally, the new line will be connected to the Great Western Main Line andCrossrail at Old Oak Common railway station; this will provide links with East and West London and the Thames Valley.[196]
In launching the project, the DfT announced that HS2 between London and the West Midlands would follow a different alignment from the West Coast Main Line, rejecting the option of further upgrading or building new tracks alongside the West Coast Main Line as being too costly and disruptive, and because theVictorian-era West Coast Main Line alignment was unsuitable for very high speeds.[197] A study by Network Rail found that upgrading the existing network to deliver the same extra capacity released by constructing HS2 would require fifteen years of weekend closures. This does not include the additional express seats added by HS2, nor would it deliver any journey time reductions.[19]
HS2 is officially supported by theLabour Party,Conservative Party, theLiberal Democrats and, since September 2024, theGreen Party of England and Wales.[198] TheConservative–Liberal Democrat coalition government formed in May 2010 stated, in its initial programme for government, its commitment to creating a high-speed rail network.[199][200]
In a report brought out in 2019, the High Speed Rail Industry Leaders group (HSRIL) stated that in order to meet 2050 carbon emissions targets, HS2 must be built.[201] Network Rail support the project and state that upgrading the existing network instead of building HS2 would take longer and cause more disruption to passengers.[19]
Until September 2024 Green Party policy was that the party would scrap HS2 and spend the money saved on local transport links.[198]Reform UK and theUK Independence Party also oppose the scheme.[202][203] The2017 act allowed HS2 Ltd. the power to acquire land. In a document that ran to 50,000 pages it gave local councils the power to petition for design changes and to hold up work if they were unhappy.[204] Eighteen councils affected by the planned route set up the 51M group, named for the cost of HS2 for each individual constituency in millions of pounds.[205] Between 2017 and the beginning of 2024 HS2 had to obtain more than 8,000 planning and environmental consents and has gone to court more than 20 times.[204] Before he became prime minister, Boris Johnson was personally against HS2.[198] Other former and current Conservative MPs against HS2 includeCheryl Gillan andLiam Fox.[206][207]
Stop HS2 was set up in 2010 to co-ordinate local opposition and campaign on the national level against HS2.[208] In June 2020 it organised a "Rebel Trail" withExtinction Rebellion, which was a protest march of 125 miles (200 km) from Birmingham to London, stopping at camps inWarwickshire,Buckinghamshire and London.[209] Groups such as theWildlife Trusts and theNational Trust oppose the project, based on concerns about destruction of local biodiversity.[210]
In 2017 aprotest camp was established at Harvil Road in theColne Valley Regional Park byenvironmental activists intending to protect the wildlife habitats of bats and owls. The protesters asserted that freshwater aquifer would be affected by HS2 construction and this would impact London's water supply. The camp included members of the Green Party and Extinction Rebellion. In January 2020, HS2 bailiffs began to evict people from the site, after HS2 has exercised its right to compulsorily purchase the land fromHillingdon council, which had not been prepared to sell the land otherwise.[211] A prosecution of two activists accused of aggravated trespass had previously collapsed in 2019, when HS2 was unable to prove it owned the land the activists were allegedly trespassing upon.[212]
In early 2020, during the clearance of woodland along the route, the group HS2 Rebellion squatted on a site in the Colne Valley, aiming to block construction; the protesters argued that public money would be more suited to supporting theNational Health Service during the COVID-19 pandemic.[213] HS2 and Hillingdon council both moved to get separateinjunctions allowing them to remove thesquatters.[214] In March 2020 another camp was set up, atJones' Hill Wood in Buckinghamshire. In October 2020, activists, including "Swampy", were evicted from treehouses there.[215]
In January 2021 it was revealed that protesters haddug a tunnel underneathEuston Square Gardens. The protesters were criticised for endangering themselves and emergency services personnel, and for being "costly to the taxpayer".[216][217] In June 2021 HS2 stated that protests had so far cost the company £75 million.[218]
In early 2021 the Bluebell Woods Protection Camp was set up at Cash's Pit, adjacent to theA51 road, on the line of the proposed route as it passes north of the village ofSwynnerton inStaffordshire.
There have been incidents of violence directed towards HS2 workers.[219][220]
The impact of HS2 has received particular attention in theChiltern Hills, anArea of Outstanding Natural Beauty, where the line passes through theMisbourne Valley.[221][222] In January 2011, the government announced that two million trees would be planted along sections of the route to mitigate the visual impact.[223] The route was changed so as to tunnel underneath the southern end of the Chilterns, with the line emerging northwest ofAmersham.[224] The proposals include a re-alignment of more than 1 kilometre (0.62 mi) of theRiver Tame, and construction of a 0.63 km (0.39 mi) viaduct and a cutting[225] through ancient woodland at anature reserve atPark Hall near Birmingham.[226] The work on the tunnel extension has started, but there is a challenge from local planning authorities that the work does not have permission. The tunnel extension has been referred to the minister of state for a decision.
Amid concerns that HS2 was carrying out preparatory works duringnesting season, theSpringwatch presenter and conservationistChris Packham filed for ajudicial review of the decision to proceed and an emergency injunction to prevent construction, havingcrowdfunded £100,000 to cover legal fees. His bid failed before theHigh Court of Justice, which ruled that a judicial review "had no real prospect of success".[227] Packham was subsequently given leave to appeal to theCourt of Appeal, withLord Justice Lewison ruling that there was "considerable public interest".[228][229] On 31 July 2020 Packham lost his case in the Court of Appeal.[230]
Phase 1 is estimated to result in the demolition of more than 400 houses: 250 around Euston; 20–30 between Old Oak Common andWest Ruislip; around 50 inBirmingham; and the remainder in pockets along the route.[231] No Grade I or Grade II* listed buildings will be demolished, but six Grade II listed buildings will be, with alterations to four and removal and relocation of eight.[232] These included a 17th-century farm inUxbridge once visited byQueen Elizabeth I in 1602,[233] and the Eagle and Tun pub, which was the set for theUB40 music video for "Red Red Wine".[234][235] In Birmingham theCurzon Gate student residence and theFox and Grapes, a derelict pub, were demolished;[236]Birmingham City University requested £30 million in compensation after the plans were announced.[87] Once original plans had been released in 2010, the Exceptional Hardship Scheme (EHS) was set up to compensate homeowners whose houses were to be affected by the line at the government's discretion. Phase 1 of the scheme came to an end on 17 June 2010 and Phase 2 ended in 2013.[237]
TheWoodland Trust states that 108ancient woodlands will be damaged due to HS2, 33sites of Special Scientific Interest will be affected and 21 designated nature reserves will be destroyed.[210][238] In Englandancient woodland refers to areas that have been constantly forested since at least 1600. Such areas accommodate a complex and diverse ecology of plants and animals and are recognised as "irreplaceable habitat" by the government.[239][240] 52,000 such sites exist.[128] According to the trust, 56 hectares (0.6 km2) are threatened with total loss from the construction of phases 1 and 2.[241] Rare species such as thedingy skipper andwhite clawed crayfish could see a decreased population or even localised extinction upon the realisation of the project.[242] To mitigate the loss, HS2 Ltd says that seven million trees and shrubs will be planted during Phase 1, creating 900 hectares (9 km2) of new woods. A further 33 square kilometres (13 sq mi) of natural habitats are also planned.[243] HS2 Ltd disputes the Trust's figure, saying it includes ancient woodlands several kilometres from the route and that only 43 ancient woodlands are directly impacted, of which over 80% will remain intact.[244]

In 2007 the DfT commissioned a report, "Estimated Carbon Impact of a New North-South Line", fromBooz Allen Hamilton, to investigate the likely overallcarbon impact associated with the construction and operation of a new rail line to either Manchester or Scotland, including the extent of carbon dioxide emission reduction or increase from a shift to rail use, and a comparison with the case in which no new high-speed lines were built.[245] The report concluded that there was no net carbon benefit in the foreseeable future, taking only the route to Manchester. Additional emissions from building a new rail route would be larger in the first ten years, at least, when compared to a model where no new line was built.[246]
The 2006Eddington Report cautioned against the common argument of modal shift from aviation to high-speed rail as a carbon-emissions benefit, given that only 1.2% of UK carbon emissions are due to domestic commercial aviation, and that rail transport energy efficiency is reduced as speed increases.[247] The 2007 governmentwhite paper "Delivering a Sustainable Railway" stated that trains that travel at a speed of 350 km/h (220 mph) used 90% more energy than at 200 km/h (125 mph),[248] which would result in carbon emissions for a London to Edinburgh journey of approximately 14 kilograms (31 lb) per passenger for high-speed rail compared to 7 kilograms (15 lb) per passenger for conventional rail. Air travel emits 26 kilograms (57 lb) per passenger for the same journey. The paper questioned the value for money of high-speed rail as a method of reducing carbon emissions, but noted that with a switch to carbon-free or carbon-neutral electricity production the case becomes much more favourable.[248]
The "High-Speed Rail Command Paper", published in March 2010, stated that the project was likely to be roughly carbon neutral.[249] The House of CommonsTransport Select Committee report in November 2011 (paragraph 77) concluded that the government's assertion that HS2 would have substantial carbon reduction benefits did not stand up to scrutiny. At best, the select committee found, HS2 could make a small contribution to the government's carbon-reduction targets. However, this was dependent on making rapid progress in reducing carbon emissions from UK electricity generation.[13] Others argue these reports do not properly account for the carbon reduction benefits coming from the modal shift to rail for shorter-distance journeys, due to the capacity realised by HS2 on existing mainlines resulting in better local services.[250][251]
The Phase 1 environmental statement estimates that 5.8–6.2 million tonnes ofcarbon dioxide equivalent emissions will be involved in the construction of that section of the line, with operation of the line estimated to be carbon negative thereafter; operational emissions,modal shift, and other environmental mitigations—such as tree planting and decarbonisation of the electrical grid—are expected to provide a saving of 3 million tonnes of CO2-equivalent emissions over sixty years of operation. The carbon dioxide emissions per passenger-kilometre in 2030 are estimated to be 8 grams for high-speed rail, as opposed to 22 grams for conventional intercity rail,[note 1] 67 grams for private car transport, and 170 grams for domestic aviation.[252]
The government stated that one-third of the carbon footprint from constructing Phase 1 results from tunnelling, the amount of which has been increased following requests from local residents to mitigate the impact of the railway on habitats and its visual impact.[128]
HS2 Ltd stated that 21,300 dwellings could experience a noticeable increase in rail noise and that 200 non-residential receptors (community, education, healthcare, and recreational/social facilities) within 300 metres (330 yards) of the preferred route have the potential to experience significant noise impacts.[231] The government has stated that trees planted to create a visual barrier will reduce noise pollution.[223]
HS2 Ltd announced in March 2012 that it would conduct consultations with local people and organisations along the London-to-West-Midlands route, through community and planning forums, and an environment forum.[253] It confirmed that the consultations would be conducted in line with the terms of theAarhus Convention.[254] HS2 Ltd set up 25 community forums along the Phase 1 route in March 2012. The forums were intended to allow local authorities, residents associations, special interest groups, and environment bodies in each community forum area to engage with HS2 Ltd.[255]Jeremy Wright,Member of Parliament forKenilworth and Southam, stated that in his area the community forums were not a success since HS2 had not provided clear details about the project and took up to 18 months to respond to his constituents.[256]
Since the announcement of Phase 1, the government has had plans to create an overall 'Y shaped' line with termini in Manchester and Leeds. Since the intentions to further extend were announced, an additional compensation scheme was set up.[257] Consultations with those affected were set up over late 2012 and January 2013, to allow homeowners to express their concerns within their local community.[258]
The results of the consultations are not yet known, but Alison Munro, chief executive of HS2 Ltd, has stated that it is also looking at other options, including property bonds.[259] The statutory blight regime would apply to any route confirmed for a new high-speed line following the public consultations, which took place between 2011 and January 2013.[260][258]
The revision of the route through South Yorkshire, which replaced the original plans for a station atMeadowhall with a station off the HS2 tracks at Sheffield, was cited as a major reason for the collapse of theSheffield City Region devolution deal signed in 2015; Sheffield City Council's successful lobbying for a city-centre station—in opposition toBarnsley,Doncaster, andRotherham's preference for the Meadowhall option—caused Doncaster and Barnsley councils to seek an all-Yorkshire devolution deal instead.[261][262]

Between 2018 and early 2022 HS2 examined more than 100 archaeological sites along the railway route.[263]
Early discoveries during construction were twoVictorian-era glass jartime capsules found during the demolition of the derelictNational Temperance Hospital inCamden, dating from 1879 and 1884. The capsules contained newspapers, the hospital's rules, pro-temperance movement material, and official records.[264][265]
The "Hillingdon Hoard" of more than 300late Iron Agepotins was discovered in by archaeologists working on the railway project inHillingdon,West London.[266] Archaeologists working on the railway had previously discoveredhunter-gatherer flint tools from a much earlier (earlyMesolithic) site in the easternColne Valley within theLondon Borough of Hillingdon, evidence of what may be the earliest settlers of what is now Greater London.[267]
Before construction could begin on the new Euston station, archaeologists had to remove roughly 40,000 skeletons from the former burial ground ofSt James's Church, which was in use between 1790 and 1853 and lies on the site of the new station.[268] Many of the skeletons were identifiable by surviving leadcoffin plates, including the long-lost remains of the explorer CaptainMatthew Flinders,[269] who is to be re-buried in his home town ofDonington, Lincolnshire. The rest of the remains are to be reburied atBrookwood Cemetery,Surrey.[270] There were also excavations to remove roughly 6,500 skeletons from a burial ground on the site of the new Curzon Street Station in Birmingham. Other notable finds in the burials were grave goods such as coins, plates, toys and necklaces,[271] as well as evidence ofbody snatching. Excavations in Birmingham also uncovered the world's oldestrailway roundhouse.[272][235]
In July 2020, archaeological teams announced a number of discoveries nearWendover inBuckinghamshire. The skeleton of anIron Age man was discovered face-down in a ditch with his hands bound together under his pelvis, suggesting that he may be a victim of a murder or execution. Archaeologists also discovered the remains of aRoman buried in a lead coffin, and stated that he may have been someone of high status due to the expensive method of burial. One of the most significant finds was that of a large circular monument of wooden posts 65 metres (213 ft) in diameter with features aligned with thewinter solstice, similar to that ofStonehenge inWiltshire. A goldenstater from the 1st century BC was also discovered, with archaeologists stating that it was almost certainly minted in Britain.[273][274]
In Coleshill, Warwickshire, the remains of large manor and ornamental gardens, laid out byRobert Digby in the 16th century, were excavated.[275]
In September 2021, archaeologists from LP-Archaeology announced the discovery of the remains of old St Mary's Church inStoke Mandeville, Buckinghamshire, while working on the route of the HS2 railway. TheNormanparish church structure, which dates back to 1080, fell into ruin after 1866, when a new church was built elsewhere in the area.[276][277] Discovered in the ruins of the Norman church were medieval markings in the form of drilled holes on two stones; these are variously interpreted asritual protective marks, or as an earlysundial.[277] Researchers' discovery of flint walls forming a square structure, enclosed by a circular borderline, indicate that the Norman church as built on an earlierAnglo-Saxon church. As part of excavations, approximately 3,000 bodies were moved to a new burial site. Evidence of a settlement from theRoman period was also discovered nearby.[278][279][276]
In early 2021 a significant site called "Blackgrounds" (for its rich dark soil) was discovered on what was previously pastureland near the village ofChipping Warden inWest Northamptonshire, close to theRiver Cherwell.[263][280] While the existence of an archaeological site in the region had been previously known, the excavations showed an unexpectedly significant site.[280] A team of 80 with the MOLA Headland Infrastructure archaeological consortium, which is working with HS2 Ltd, excavated the site, which consisted of a small Iron Age village that became a Roman town.[263] The population grew, from about 30 roundhouses during the Iron Age, into a significant Roman settlement with a population in the hundreds.[280] Discoveries included a particularly largeRoman road; more than 300Roman coins; and jewellery, glass vessels, and decorative pottery (includingsamian pottery imported fromGaul), as well as signs of cosmetics. Roman-era workshops and kilns were discovered, along with at least four wells.[263][280] A pair ofshackles was also unearthed.[280] Taken together, the evidence was indicative of a prosperous trading site.[263][280]
HS2 Phase One represents the largest single programme of historic environment work undertaken in the UK[281] and has generated a vast amount of digital archaeological data. The digital data, includingBIM andGIS data,[282] specialist reporting and reports all hold potential for future analysis, public engagement and legacy and will be held in a digital archive hosted by theArchaeology Data Service.[283]
A scheme has been announced to use the chalk excavated from the Chiltern tunnel torewild a section of theColne Valley Western Slopes. The 127 ha (310-acre) scheme will take its inspiration from theKnepp wilding, and will stretch along the line from the viaduct atDenham Country Park to the Chiltern tunnel's southern portal.[284]

Phase 2 was intended to extend HS2 north toFradley (a village northwest of Lichfield) then divide into two branches. The western branch would have travelled north past Crewe before again splitting into two branches nearKnutsford, one terminating atManchester Piccadilly railway station and the other joining the West Coast Main Line (WCML) at Golborne, south of Wigan. A station may have been built to serveManchester Airport. The eastern branch would have been built through the East Midlands and connect to theMidland Main Line north ofDerby, then continue to Leeds; it would then have formed two branches, one terminating in central Leeds and the other connecting to theEast Coast Main Line near York.
Phase 2 was split into three sub-phases:
Phase 2b east was truncated in November 2021, with the branch expected to end atEast Midlands Parkway railway station, south ofNottingham.[289] In June 2022, the link to the WCML at Golborne, a part of phase 2b west, was cancelled.[290] In October 2023 phase 2a and the remainder of phase 2b were cancelled, leaving phase 1 the only extant element of the project.[291]

Early proposals for HS2 outlined the construction of a two-kilometre-long (1.2 mi) link between HS2 andHS1, which would have allowed high-speed trains to operate directly from the North and Midlands to destinations in continental Europe via theChannel Tunnel.[292][293][294] The link, which was to be built through Camden Town in North London, was abandoned in 2014 on grounds of cost and insufficient capacity for trains on HS2 track.[295][296] Following the cancellation of this link, it was proposed that passengers would transfer between these two lines viashuttle bus,automated people mover or an "enhanced walking route" between Euston and St Pancras stations.[296]
Various alternative schemes have been proposed for an HS2–HS1 link, including a tunnel under Camden,[297] as well as the rejectedHS4Air scheme.[298]
Prior to the cancellation of the northern phases, the original HS2 scheme specified connections from the new high-speed tracks onto existing conventional tracks at junctions on existing mainlines.[299] TheWest Coast Main Line was to have branches inCrewe, and a branch east ofLichfield Trent Valley, 3.5 kilometres (2.2 mi) northeast ofLichfield. TheMidland Main Line was to have a brand onto HS2 atEast Midlands Parkway station inNottinghamshire. TheNorthern Powerhouse Rail was to have a branch atMillington junction.[299]
Further proposals were suggested during the original launch of the project around 2009.
No direct HS2 track access was planned for theLiverpool City Region, with the nearest HS2 track passing 16 miles (26 km) from Liverpool city centre. In February 2016, the Liverpool City Council offered £2 billion towards funding a direct HS2 line into the city centre.[176]
Steve Rotheram, theMetro Mayor of the Liverpool City Region, announced the creation of a Station Commission to determine the size, type, and location of a new "transport hub" in Liverpool's city centre, a station that would have linked the HS2 mainline with the local transport infrastructure. The station would have served HS2 and NPR trains. The North's Strategic Transport Plan recognised the need for a new station to accommodate HS2 and NPR trains.[300][301][302]
In the HS2 plan, after phase 2a had opened, Liverpool trains would have used the HS2 track from London as far as Crewe, before changing to the existing conventional rail track on the West Coast Main Line to proceed toLiverpool Lime Street, with a stop atRuncorn.
The Integrated Rail Plan proposed to connect Liverpool to HS2 on a reused and upgradedFiddlers Ferry freight line, fromDitton junction inHalebank to a new station atWarrington Bank Quay Low-Level, which would have been shared withNorthern Powerhouse Rail trains, then onto high-speed track from Warrington to London.[303]Transport for the North's preferred option was a new high-speed line from Liverpool to the HS2 track into Manchester from Millington junction, with a stop at Warrington, which would also have doubled as a connection from Liverpool to HS2 via Millington. The revised plans under the Integrated Rail Plan had a high-speed line only east of Warrington, with HS2 andNorthern Powerhouse Rail trains reaching Liverpool Lime Street from Warrington on upgraded conventional rail track. Metro mayor Steve Rotheram, along with Greater Manchester's mayorAndy Burnham, were critical of the Integrated Rail Plan.[304]
In 2009 the then transport secretary,Lord Adonis, outlined a policy for high-speed rail in the UK as an alternative to domestic air travel, with particular emphasis on travel between the major cities of Scotland and England, "I see this as the union railway, uniting England and Scotland, north and south, richer and poorer parts of our country, sharing wealth and opportunity, pioneering a fundamentally better Britain".[305]
In June 2011, business and governmental organisations — including Network Rail,CBI Scotland andTransport Scotland (the transport agency of theScottish Government) — formed the Scottish Partnership Group for high-speed rail to campaign for the extension of the HS2 project north toEdinburgh andGlasgow. In December 2011, it published a study that outlined a case for extending high-speed rail to Scotland, proposing a route north from Manchester to Edinburgh and Glasgow as well as an extension toNewcastle upon Tyne.[306]
In November 2012 the Scottish Government announced plans to build a 74 km (46 mi) high-speed rail link between Edinburgh and Glasgow. The proposed link would have reduced journey times between the two cities to under 30 minutes and was planned to open by 2024, eventually connecting to the high-speed network being developed in England.[307] The plan was cancelled in 2016.[308] In May 2015 HS2 Ltd had concluded that there was "no business case" to extend HS2 north into Scotland, and that high-speed rail services should proceed north on upgraded conventional track.[309]
The DfT conducted a study on towns and cities that would lose economically from HS2, highlightingBristol andCardiff.[310][184][311][312] With decreased journey times between London and Northern England under HS2, Cardiff in particular would be set to lose much of its competitive edge that arose from its proximity to London's financial and legal service companies, due to improved rail connections between London and northern England.[313]
Proposals were put forward to build a high-speed line between Birmingham to Cardiff or Bristol, creating an X-shaped high-speed network, with Birmingham at its centre.[314] There were also proposals for a new high-speed rail project in South Wales, beyond just Cardiff, to connect with the HS2 network.[315]
original rationale for HS2 – still holds: there is a need for greater capacity (both more trains on tracks and more seats on trains and reliability on the GB rail network)
Prime minister Rishi Sunak announced two weeks ago that the Euston station project would be privately funded and removed from the responsibilities of HS2 Ltd.
the New HS2 station will consist of six platforms, which can support up to 10 HS2 trains per hour