| Hallam Nuclear Power Facility | |
|---|---|
Aerial view of Hallam Nuclear Power Facility (right) and Sheldon Power Station (left) | |
![]() | |
| Country |
|
| Coordinates | 40°33′30″N96°47′05″W / 40.55833°N 96.78469°W /40.55833; -96.78469 |
| Status | Decommissioned |
| Construction began |
|
| Commission date |
|
| Decommission date |
|
| Nuclear power station | |
| Reactor supplier | |
| Power generation | |
| Nameplate capacity |
|
TheHallam Nuclear Power Facility (HNPF) inNebraska was a 75 MWesodium-cooledgraphite-moderatednuclear power plant built byAtomics International and operated byConsumers Public Power District of Nebraska.[1] It was built in tandem with and co-located with a conventionalcoal-fired power station, theSheldon Power Station.[2] The facility featured a sharedturbo generator that could accept steam from either heat source, and a sharedcontrol room.
Full power was achieved in July 1963. The facility shut down on September 27, 1964 to resolve reactor problems. In May 1966, Consumers Public Power District rejected their option to purchase the facility from theAtomic Energy Commission (AEC). In response, the AEC announced its plan to decommission the facility in June, 1966. The facility operated for 6,271 hours and generated 192,458,000 kW-hrs of electric power.[3]
It was located nearHallam, about 25 miles southwest ofLincoln.

The sodium-cooled graphite-moderated reactor (SGR) design (of which HNFP was a demonstration) targeted economical commercial nuclear electricity. Theliquid metal coolant enabled operation at temperatures sufficiently high to produce steam conditions identical to those used infossil-fueled power plants, enhancingpower conversion efficiency and making use of commoditysteam turbines. It also enables low-pressure operation. Thegraphitemoderator enabled operation with low-enriched nuclear fuel as well the potential use of thethorium fuel cycle. These benefits were expected to overcome the added complication of a using chemically reactive coolant.[4]
The reactor was initially fueled with 3.6% enriched uranium-10 molybdenum alloy withstainless steel cladding. The graphite moderator was clad in stainless steel hexagons with each corner scalloped to make room for the process tubes, which contained the fuel clusters and control rods. Three sodium heat-transfer loops (each with a radioactive primary loop and a non-radioactive secondary) moved heat to three steam generators. Steam fed into a common header to a single turbine generator. The primary hot leg temperature was 945 °F, and the secondary hot leg temperature was 895 °F.
Uranium carbide was selected for the second core at 4.9% enrichment.



Hallam was proposed in March 1955 in response to the first round of invitations by the Atomic Energy Commission's Power Demonstration Reactor Program.[6] It used technology being developed in the smallerSodium Reactor Experiment (SRE), also built by Atomics International. Lessons from SRE applied to HNPF include:
Because HNPF was more than ten times larger than SRE, a components development and test program were performed to provide final design data. All major components were tested, including fuel, control rods, instrumentation, pumps, and valves. The fuel handling machine was assembled and tested. Scale model of a steam generator was tested in a sodium loop along with related equipment and instrumentation.[3]
A formal three-session training program for operators was conducted in 1960. 30 personnel attended the first session for six months. Each person received approximately 900 hours of training.
Construction began on April 1, 1959. Employment during construction peaked at 270 in March 1961, and 107,600 person-days total were required to complete the construction. Various construction assembly interferences were anticipated, and detailed scale models were procured. Labor problems resulted in the loss of 1750 person-days. The entire facility was completed on November 30, 1961, 4 months past the originally planned date of completion.[3]


Initial criticality was achieved in January 1962, followed by wet criticality six months later. Difficulties that arose during operation and required plant shutdown and correction included leaking control rod thimbles, seizure of secondary sodium pumps, leaking steam generator instrumentation and pipe flanges, difficulty of adjusting fuel channel flow orifices, and failure of primary and secondary sodium throttle valves.
The most severe issue was the ruptures of moderator elements. Seven elements ruptured in February 1964. The ruptures and subsequent absorption of sodium into the graphite reduced the thermal neutron flux in the core and caused a reduction in local power. The moderator elements swelled as well, reducing coolant and process space. Examination disclosed that failure was caused by low ductility stress-rupture leading to a one-inch-long crack about three inches below the top of each element.
Chauncey Starr, the president of Atomics International, testified that they had identified and claimed to have fixed the issue with the moderator can. He proposed a repair operation involving attaching snorkels to each moderator can into the cover gas space, which would cost $1.8M and require 6–9 months.[7] Nonetheless, the AEC underMilton Shaw decided to terminate their contract with the utility. Consumers chose not to purchase the plant, and it was instead decommissioned.
The plant's single 75 MWe reactor operated from 1963 to September 27, 1964.[3] Decommissioning was completed in 1969. Belowground components of the reactor wereentombed on-site and will have to be monitored until 2090.[8]
Currently, the site holds a fossil-fuel plant,Sheldon Power Station. The site is monitored from 17 monitoring wells, and no radioactivity above background levels in any samples has been detected.[9]