Brightline West

From Wikipedia, the free encyclopedia
Future American high-speed rail route
This article is about the passenger rail service between Las Vegas and Southern California. For the similarly branded rail route in Florida, seeBrightline.

Brightline West
A map of planned high-speed rail routes in California and Nevada onI-15 corridor. The separateCalifornia High-Speed Rail is indicated in black, grey and light grey.
Overview
Service typeHigh-speed rail
StatusUnder construction[1]
LocaleCalifornia, Nevada
PredecessorDesert Wind
First serviceSeptember 2029 (anticipated)
Current operatorBrightline
Websitebrightlinewest.com
Route
TerminiRancho Cucamonga, California, US
Enterprise, Nevada, US
StopsVictor Valley,Hesperia California, US
Distance travelled218 miles (351 km)[2]
Average journey timeApprox. 2h 10m[2]
Technical
Track gauge4 ft 8+12 in (1,435 mm)standard gauge
ElectrificationOverhead line25 kV 60 Hz AC
Operating speed
  • Maximum (TBC):
  • 180 or 200 mph (290 or 320 km/h)
  • Average:
  • 101 mph (165 km/h)[2]
Track ownersDesertXpress Enterprises, LLC[3] (Fortress Investment Group)[4]
Route map
Las VegasHarry Reid International Airport
Maintenance facility
Victor Valley
Hesperia
Rancho Cucamonga
Metrolink (California)Ontario International Airport viaOmnitrans
This diagram:

Brightline West is a proposed privately runhigh-speed rail route, under early construction, to link theLas Vegas Valley andRancho Cucamonga inGreater Los Angeles through theCalifornia High Desert viaInterstate 15. The line will connect with existing rail at theRancho Cucamonga station ofMetrolink'sSan Bernardino Line, a commuter rail line in Southern California. The project is intended to provide an alternative to air and automobile travel betweenSouthern California andLas Vegas, a popular leisure destination. In December 2023, theUnited States Department of Transportation awarded Brightline West a $3 billion grant as part of theInfrastructure Investment and Jobs Act. Construction, initially expected to begin shortly after the grant was announced in 2023, began on April 22, 2024.[5][6][7][8] Revenue service is planned to start by September 2029.[9]

The line was developed starting in 2005 asDesertXpress and has passed through several developers and investors. In September 2018, the project known asXpressWest, was acquired byFortress Investment Group, which ownsBrightline in Florida, the only privately runinter-city rail route in the United States. An extension of Brightline West fromVictor Valley to theCalifornia High-Speed Rail station inPalmdale is also under consideration.

Context

[edit]
Map

Las Vegas is a gambling and tourist destination for the Greater Los Angeles area.[10] Interstate 15 is a direct route between the two regions.[11][12][13] An estimated 50 million people travel between Los Angeles and Las Vegas annually, with 85% using a car.[14] Travel by automobile takes over four hours[15] while scheduled buses cover the route in five to seven hours.[16] Interstate 15 is an importantfreight route, so reduced congestion on the route would benefit thesupply chain.[17]

The highway carries heavy traffic on Thursday, Friday, and Sunday which causes significant delays.[18] Motorists returning to Los Angeles on Sunday can create a 18-mile (29 km) backup.[19] Airlines have direct flights, but traffic and security at the airport add time to the short flight.[20][12] Las Vegas lost its last passenger train service in 1997 whenAmtrak canceled theDesert Wind.[21]

Brightline project

[edit]

In September 2018,Fortress Investment Group, which owns an inter-city rail route in Florida calledBrightline, announced that it would acquire the federally approved XpressWest rail corridor project, indicating that it would begin construction of the rail line in the second half of 2020 with expected completion in the second half of 2024. After some delays, groundbreaking began on April 22, 2024 with service initially expected to start sometime in 2028.[22] The project is expected to generate around 18,000 jobs at its peak. Los Angeles County finished an environmental assessment for the project in 2016. In October 2019, design plans were almost 30% complete.[23] In September 2020, the line was rebranded to Brightline West, and is being called "a Brightline affiliated company."[24][25]

Funding assistance

[edit]

A high speed line following the Palmdale–Apple Valley–Las Vegas route was included in the 2018 California State Rail Plan as part of the 2040 timeline of projects.[26] Subsequently, the state of California issued tax-exempt,private activity bonds to XpressWest to partially fund construction.[27] These bonds are meant to assist private ventures for the public interest.[28]

In September 2019, it was announced that California would assist the project in funding. In October 2019 California Infrastructure and Economic Development Bank approved $3.25 billion in bonds.[29][30] In April 2020, California government officials signed off on issuing $600 million in tax-exempt private activity bonds for XpressWest.[31][32] The state of Nevada allocated the company an additional $200 million in private activity bonds in July 2020.[33]

Cofounder and co-CEO of Fortress,Wes Edens, estimated the cost of construction at $8 billion in 2020.[34] In September 2020, up to $3.2 billion in the tax-exempt, private activity bonds were offered.[35] In November, it was decided to let the rights for the sale of the bonds lapse.[36][37][38] A bond sale was planned for 2021 but was moved to 2022 to allow continued progress on project planning and for the bonds to be more attractive to investors.[39][40][41]

Los Angeles Metro is considering re-programming around $2 billion in Measure M funding slated for the High Desert Corridor, a proposed freeway between Victorville and Palmdale, canceled in October 2019, to instead create a development plan for an extension of the XpressWest route between the two cities.[42][43][44]

In February 2023, the company applied for $3.75 billion in funding fromInfrastructure Investment and Jobs Act.[45] A bipartisan congressional group from Nevada and California wrote a letter in April 2023 in support of the funding.[46] In December 2023, theUnited States Department of Transportation awarded Brightline West $3 billion of the grant request and in September 2024 signed it.[10][47][48] In January 2024, Brightline West received $2.5 billion ofprivate activity bonds from theUS Department of Transportation in addition to $1 billion given in 2020.[49][50] The remainder of the cost (estimated at $12 billion as of April 2024[51]) is expected to be privately financed.[52]

Due to rising costs of labor force and materials, the company requested a $6 billion loan from the U.S. Department of Transportation. The costs are now estimated to be $21.5 billion.[53]

Rancho Cucamonga extension

[edit]

The company initiated planning on a rail line over theCajon Pass toRancho Cucamonga in June 2020.[54] TheInfrastructure Investment and Jobs Act passed in November 2021 has billions of dollars for rail projects which provides expanded opportunities for companies such as Brightline.[55] In January 2022, the Federal Transportation Department's Federal Rail Administration began reviewing the 49-mile segment (79 km) that would allow speeds of up to 180 miles per hour (290 km/h).

The environmental report for the Rancho Cucamonga route was released in October 2022.[56] The environmental report includes the location of the proposed intermediate station inHesperia. The report notes some mitigation measures will be necessary: temporary impacts on noise and wetlands, temporary and permanent impacts on some threatened or endangered species, visual impacts on views in the San Gabriel and San Bernardino Mountains, and traffic impacts around stations in Hesperia and Rancho Cucamonga. The report concludes that the project "will not result in a significant impact on the environment" or have "disproportionately high and adverse impacts" on low-income or minority populations.[57] The environmental permit was approved in July 2023.[58]

The San Bernardino County Transportation Authority was awarded a $25-million grant in July 2023 from theRebuilding American Infrastructure with Sustainability and Equity (RAISE) program to fund design and construction costs of the stations in Hesperia and Apple Valley.[59][60]

Construction

[edit]

Preparatory work involving ground surveys in the right of way of Interstate 15 and recruitment of up to 11,000 workers began in January 2024.[61][62] Agroundbreaking ceremony was held on April 22, 2024, at the plannedLas Vegas station site, marking the official start of construction.[1] Heavy construction was scheduled to begin in early 2025,[47] with the Nevada DOT saying work could start in April 2025.[63] However, as of October 2025, the major construction for the rail line is expected to begin in April 2026.[64]

The company originally aimed to have the line operational for the2028 Summer Olympics in Los Angeles. However, as of April 2025,[update] officials now anticipate the line will begin service September 2029, too late for the Olympics.[9]

Since the groundbreaking, field investigations and early-site activities has advanced throughout both Nevada and California. By mid-2025, Brightline West crews were performing geotechnical borings, utility potholing, and survey operations along the Interstate 15 corridor, including bridge-potholing work near the I-15/SR-210 interchange in Rancho Cucamonga.[65] In California's High Desert, crews expanded operations through Victor Valley and Hesperia, conducting soil sampling and drainage surveys.[66]

In North Las Vegas, PCM Railone announced construction of a US $20 million conrete-tie production facility dedicated to the Brightline West project, with tie shipments expected to begin in late 2025.[67] According to updated planning documents, main civil works, including embankment grading, drainage, and bridge pier construction, are scheduled to accelerate through 2025-2026, with fully heavy-construction activity beginning by early 2026.[68]

Route

[edit]
Interstate 15 approaching Cave Mountain, California (above) and in theIvanpah Valley,Nevada (below). The line is planned to run in the highwaymedian strip for most of its length.

The tracks are planned to be laid in the median ofInterstate 15, aside from a short section connecting toRancho Cucamonga and a section on the east side of the highway approaching the Las Vegas station.[69][70] Sections will pass through federal land controlled by theBureau of Land Management and theNational Park Service.[71][72] While plans at first called for a fullydouble-track railway along the route, Brightline intends initially to build the project as a mostlysingle-track route withpassing sidings, partly because additional sections were moved to the highway median where space is more limited.[73]

In the original plan, the route did not extend into Los Angeles due to the high cost of building rail in urban areas.[74] The 50-mile (80 km) extension from Victor Valley to the city ofPalmdale, where it would connect to theCalifornia High-Speed Rail system currently in development, in order to provide service to Los Angeles, was not included in the initial phase.[75] In June 2012, the new plan included the link between Victor Valley and Palmdale as part of construction for the first phase of the project. Passengers would transfer toMetrolink to access the Los Angeles area.[76]

In June 2020, the company initiated planning on a rail line south of Apple Valley over theCajon Pass toRancho Cucamonga to provide more direct Los Angeles service, while not ruling out the Palmdale expansion.[54] The details of other sections have not been announced. Later phases may include extensions toPhoenix, Arizona;Salt Lake City, Utah; orDenver, Colorado.[77][78]

In 2009, XpressWest estimated that it would carry around five million round trip passengers in the first full year of operation,[79] with the company charging fares of around $50 for a one-way trip between Victorville and Las Vegas.[80] In 2012, the round-trip fare was planned to be around $89 (equivalent to $122 in 2024),[81] with trains expected to run every 20 minutes on peak, and up to every 12 minutes as demand requires.[82] As of 2020[update], the stated frequency is 45 minutes between departures.[83]

In 2023, Brightline West relocated more sections of the route into the median of I-15. The Victor Valley station was reconfigured to have passenger platforms in the highway median. The vehicle maintenance facility was moved from the Victor Valley site to a 246-acre parcel (100 ha) west of I-15 inSloan, Nevada, and will connect to theUnion Pacific mainline at this location.[84]

Stations

[edit]

TheLas Vegas station will be south of theLas Vegas Strip onLas Vegas Boulevard inEnterprise.[85] The 110-acre site (45 ha) is across from thePremium Outlets South mall.[44] The two-story station will feature retail and restaurant space.[86] The Las Vegas station on Las Vegas Boulevard was announced in 2020. The land was acquired in July 2021.[44] In April 2023, renderings of the Las Vegas station were released.[87]

Victor Valley station will be in the northeast portion of the town ofApple Valley, adjacent toI-15 at Dale Evans Parkway.[88][40]Passenger platforms will be in the median of I-15 and accessed via walkway under the northbound lanes of the highway.[59][89][90]

A station inHesperia will be built in the median of I-15 at the Joshua St exit.[91] Trains will make limited stops here in the morning and evening.[92]

The line will continue into theGreater Los Angeles area, terminating atRancho Cucamonga Metrolink station.[93] Service to a planned transit center incorporating the station will operate under the jurisdiction of theSan Bernardino County Transportation Authority (SBCTA).[94] SBCTA and the city of Rancho Cucamonga approved the sale of a 5-acre parcel (2.0 ha) to Brightline for the high speed rail station in 2022.[95] A proposed 2.8 miles (4.5 km)underground people-mover would provide a link to theOntario International Airport.Omnitrans currently offers direct bus service to the airport from this station.[96][97]

High Desert Corridor

[edit]
The High Desert Corridor along with current and planned future rail connections in Southern California.
Main article:High Desert Corridor

The High Desert Corridor is a proposed high-speed rail connection between Brightline West andCalifornia High-Speed Rail. It will connectVictor Valley station andPalmdale station. At Palmdale, passengers can connect to the existing Metrolink service or continue intoLos Angeles using California High-Speed Rail's tracks.[13]

Right-of-way agreements

[edit]

In June 2020, the company entered into an agreement to lease the state-owned Interstate 15 right-of-way between Las Vegas and Victor Valley fromCaltrans.[98][93][99] The 50-year lease is in the amount of $842,000 per year starting in 2020, adjusted according to the consumer price index every three years.[100] A similar agreement for the Apple Valley toRancho Cucamonga segment was signed in March 2023.[101]

Brightline entered into amemorandum of understanding (MOU) with theSan Bernardino County Transportation Authority in 2020 for the spur between Apple Valley to Rancho Cucamonga, as it provided connectivity within theInland Empire.[93][54]Metrolink also approved a MOU to study the links to the Rancho Cucamonga and Palmdale Metrolink stations.[13] A MOU was signed in October 2021 with theCalifornia State Transportation Agency (CalSTA), Caltrans, and California High-Speed Rail Authority, for the use of 48 miles (77 km) within Interstate 15 to Rancho Cucamonga.[102][103]

Environmental impact

[edit]

The Brightline West project underwent detailed federal and state environmental reviews led by the Federal Railroad Administration (FRA) and Caltrans. The final Environmental Impact Statement (EIS) was approved in July 2023, determining that the rail line would not cause significant adverse impacts with appropriate mitigation measures.[104]

Wildlife crossings

[edit]

A 6-foot-high concrete barrier (1.8 m) will keep vehicles away from the rail line along the center divider of Interstate 15. This will prevent animals from making what is already a dangerous crossing of the freeway.Desert bighorn sheep once thrived in these mountain ranges, though they now face many challenges. Wildlife researchers determined thatwildlife crossings atSoda,Cady andClark mountains could help sustain the sheep and other wildlife.[105]

Under an agreement with Caltrans and theCalifornia Department of Fish and Wildlife, wildlife crossings will cross over the freeway and the rail line at the three proposed locations.[45] Hundreds of existingculverts and crossings under the Interstate will be maintained or improved. Fencing to protect thedesert tortoise and to exclude wildlife will be restored or installed as part of the project.[106]

Brightline West has also pledged to offset its construction-related emission through pilot programs using battery-electric machinery andsolar-powered construction offices.[107]

Rolling stock

[edit]
Prototype car ofSiemens Velaro Novo high speed train, similar to platform proposed for Brightline West

Vehicles will require a highpower-to-weight ratio to climb steep grades on the planned route – up to 4.5% between Victorville and Las Vegas,[108] and up to 6% through Cajon Pass.[109]

Brightline was in active discussion until mid-2024 withAlstom andSiemens Mobility to procure rolling stock for the service and for potential future routes.[110][111] In May 2024, Siemens announced that Brightline had selected them as the preferred train vendor for Brightline West service.[112] The initial order consists of 10 seven-car American Pioneer 220 trainsets, with a capacity of 434–450 passengers.[112]

The service plans to use theAmerican Pioneer 220, an American variant of theSiemens Velaro Novo high-speed electric multiple unit.[113][114] Brightline would be the first customer of the Siemens Velaro Novo platform, which has been tested in Germany using theICE-S train,[115][40][34] and has a designed top speed of 225 mph (360 km/h).[116][117]

The service will use up to 25 train pairs,[118] traveling up to 200 miles per hour (320 km/h),[2] at 45 minute intervals.[118]

The Siemens rolling stock will be assembled at a new factory inHorseheads, New York.[119]

In 2025, Siemens Mobility began detailed work on the American Pioneer 220 trainsets, incorporating energy-efficient systems and interior layouts customized for the Las Vegas-Southern California corridor.[120] Each train will feature two service classes, onboardWi-Fi, touchless ticketing, and dedicated accessibility areas. Siemens confirmed that the units will meet full Buy America standards, with the majority of components produced domestically, including traction systems and bogies manufactured in Sacramento, California.[121]

The Horseheads facility, which opened in late 2024, will serve as Siemens Mobility's North American high-speed rail assembly hub, producing Brightline West's carshells, final train integration, and testing before delivery to Nevada for commissioning.[122] Siemens has indicated that the first completed trainset is expected to roll out by late 2027, allowing for testing and certifaction ahead of the planned 2029 service launch.[123]

Impacts

[edit]

Oak View Group plans a 20,000-seatarena on a 25-acre (10 ha) site adjacent to theLas Vegas station.[124] This project is part of a larger 66-acre (27 ha) development envisioned as a sports and entertainment district.[125] According toTim Leiweke, CEO of Oak View Group, this is a prime location for future growth in Las Vegas' gaming and entertainment corridor.[126]

PCM Railone AG [de] announced in June 2024 that they would build a production facility forconcrete ties and open a North American headquarters inNorth Las Vegas.[127]

Early project development

[edit]

DesertXpress

[edit]

The original plan under the nameDesertXpress was to provide an alternative to automobile travel and airline travel between theLos Angeles area and the Las Vegas area alongInterstate 15. The city ofVictorville was selected as the location for the westernmostterminal, as extending the train line farther into theLos Angeles Basin through theCajon Pass was considered to be prohibitively expensive.[128] The station would include free parking and through-checking of baggage straight to theLas Vegas Strip resorts.[72] A future extension would have included a new link to theCalifornia High-Speed Rail station inPalmdale.[129]

DesertXpress Enterprises, LLC was founded in 2005 to develop, construct, own and operate the high-speed rail project. 70% of the company was held by Anthony A. Marnell II ofMarnell Corrao Associates through hisDX, LLC company.Gary Tharaldson and François Badeau held 20 and 10%, respectively.[130] In 2006, the preparation of a firstFederal Railroad Administration-Environmental Impact Statement (EIS) was started.[131]

The total cost of the link between Apple Valley and Las Vegas was expected to be around US$5 billion.[132] In March 2010, project planners said they could obtain the full funding amount through exclusively private investors,[72][133] but had also applied for a $4.9 billion loan through the federal Railroad Rehabilitation & Improvement Financing program.[133] As of October 2011, the start of the project was contingent on receiving a $6 billion loan from the federal government, the approval or denial of which was expected in mid-2012.[134]

A preferred design was identified with the release of the Final Environmental Impact Statement in April 2011, which began a public comment period that ended in May 2011. The federal government approved the design in July 2011.[79] The planned route was approved by theSurface Transportation Board in October 2011.[135] The trains were to be self-propelled, allelectric multiple unit (EMU) trains with maximum speed of 150 mph (240 km/h).[82]

The train would travel at speeds of up to 150 mph (240 km/h) averaging 130 mph (210 km/h) and making the 186 mi (299 km) trip from Victorville to Las Vegas in about 1 hour 24 minutes.[136][137][138] In March 2010, executives with the project said they expected construction to begin in 2010.[72] In October 2011, construction was planned to begin in the last quarter of 2012, with completion in the last quarter of 2016, subject to funding.[134][139]

Transformation to XpressWest

[edit]

In June 2012, the developer announced a new plan to build a network of high-speed rail for the region by expanding to Arizona, Utah and Colorado. The initial phase was to include high-speed tracks, Las Vegas to Apple Valley and Apple Valley to Palmdale.

The 185-mile (298 km) link between Las Vegas and Victorville was designed to be double-tracked which is dedicated for the high-speed trains. The costs of this section was estimated at $6.9 billion. The developer would put up $1.4 billion in private investment and the rest of funding would borrowed under the Railroad Rehabilitation and Improvement Financing program provided by theFederal Railroad Administration.

Future plans include a link between Las Vegas and Phoenix, Arizona, and another from Las Vegas to Salt Lake City, Utah,[140] and Denver, Colorado.[141] The project was rebranded toXpressWest to reflect the expanded mission.[81]

DesertXpress Enterprises signed a document withLos Angeles County Metropolitan Transportation Authority officials in June 2012 to explore the plan to build a 50-mile (80 km) high-speed rail link between Victor Valley and Palmdale. The link would initially connect to theMetrolink system in Palmdale. This would allow passengers to complete a train ride between Los Angeles and Las Vegas with one transfer, by using Metrolink in the Los Angeles area and a transfer to the high-speed train at Palmdale station. The station would eventually connect withCalifornia High-Speed Rail, and is designed to have the same specifications and technology, allowing it to continue on California High-Speed Rail further intoBurbank andLos Angeles. The early estimate of the costs for this link was $1.5 billion. and the earliest environmental work was to be completed by the end of 2013. The date of the service for this link has not been determined.[76]

Joint venture

[edit]

In February 2013, the federal loan remained unapproved and construction was not expected to start until mid-2014 at the earliest.[142][143][144]

RepresentativePaul Ryan (R-WI), the chairman of theHouse Budget Committee and senatorJeff Sessions (R-AL), the ranking minority member of theSenate Committee on the Budget were the main opponents to the federal loan application of XpressWest. They argued that the project represented high risk to the taxpayer. They wrote to then-Transportation SecretaryRay LaHood in March 2013 and recommended the administration to reject the loan application.[145] The letter indicated that the total cost was estimated to be $6.9 billion. The $1.4 billion would come from the private sources and the remaining $5.5 billion would come from the federal loan. The letter cited a taxpayer risk analysis report as a basis of their recommendation.[146]

In July 2013, there were reports that loan was indefinitely suspended,[147] which were later confirmed by the federal government, which said that it had been suspended in part due to the failure of the application in regard to the "Buy America" policy, which required applicants to use American-made products.[148] Despite the indefinite suspension of the federal loan application, which was viewed as a denial of the application, the developer indicated that the XpressWest project would proceed without providing the details on financial plan.[149]

In 2014, Nevada SenatorHarry Reid mentioned that the federal loan request may resurface, but little had been seen so far of the project's continued viability.[150] In 2015, theNevada High-Speed Rail Authority was proposed to look into the feasibility of high-speed rail into southern Nevada from California, possibly XpressWest.[151] The bill was introduced in April 2015, and was passed by the legislature in May 2015, by a vote of 40–1.[152] It was approved by the Governor in May 2015.[153]

In September 2015, XpressWest and the newly formed China Railway International USA, a consortium of Chinese rail industry companies, announced a joint venture to design, build, and operate the service between Las Vegas and Palmdale, with construction planned to begin in September 2016.[154] A CAHSRA spokesperson said that there have been ongoing discussions concerning allowing the trains to use California High-Speed Rail lines to go further into the Los Angeles area, although no commitments had been made.[155]

In June 2016, XpressWest announced that the joint venture had been called off. The biggest reason cited for the termination of the joint venture was a federal regulation requiring the manufacture of the high speed trains inside the United States. XpressWest said that they are "undeterred by this development and remains dedicated to completing its high-speed passenger rail project."[156]

See also

[edit]

References

[edit]
  1. ^abAkers, Mick (April 19, 2024)."Brightline West to break ground on Las Vegas high-speed rail project".Las Vegas Review-Journal. RetrievedApril 19, 2024.
  2. ^abcd"Brightline West | Brightline".
  3. ^"Rail News – Brightline on track to begin Las Vegas high-speed rail project".Progressive Railroading. April 14, 2021. RetrievedJuly 10, 2021.
  4. ^Varghese, Romy (August 26, 2020)."Fortress Wins California Approval for Vegas Rail Reimbursement".Bloomberg.
  5. ^Seeman, Matthew (July 15, 2023)."Brightline West high-speed train clears environmental regulatory hurdle".News3lv. RetrievedJuly 15, 2023.
  6. ^Akers, Mick (January 14, 2021)."Spring start eyed for construction of Vegas-to-So Cal rail line".Las Vegas Review-Journal. RetrievedJanuary 14, 2021.
  7. ^Akers, Mick (November 16, 2022)."High-speed rail project construction could begin in '23".Las Vegas Review-Journal. RetrievedNovember 16, 2022.
  8. ^McLawhorn, Jennifer (April 22, 2024)."Brightline West Breaks Ground in Nevada".Railway Track and Structures. RetrievedApril 29, 2024.
  9. ^abBraun, Martin Z. (October 1, 2025)."California-to-Vegas High-Speed Rail Costs Jump $5.5 Billion".Bloomberg.com. RetrievedOctober 6, 2025.
  10. ^abUranga, Rachel (December 5, 2023)."SoCal to Vegas in two hours? High-speed rail comes closer to reality with $3-billion award".Los Angeles Times. RetrievedDecember 26, 2023.
  11. ^Gillan, Jeff (October 22, 2021)."High-speed rail takes step to link Las Vegas with Los Angeles".KSNV. RetrievedOctober 24, 2021.
  12. ^abJernigan, Meg (December 21, 2017)."How to Travel From Las Vegas to Los Angeles".Travel Tips – USA Today. Archived fromthe original on September 5, 2017. RetrievedOctober 5, 2020.
  13. ^abcOhnsman, Alan (August 22, 2020)."High-Speed Rail Heats Up In California As Brightline Eyes Las Vegas Route Extensions".Forbes. RetrievedSeptember 26, 2020.
  14. ^Ohnsman, Alan (April 25, 2023)."'The Greenest Bullet Train In The World': Wes Edens Wants To Kickstart U.S. High-Speed Rail With A Vegas-L.A. Line".Forbes. RetrievedApril 26, 2023.
  15. ^Newton, Damien (November 2, 2022)."Brightline Releases Environmental Documents for High-Speed Rail from Victorville to Las Vegas".Streetsblog California. RetrievedNovember 3, 2022.
  16. ^"Los Angeles to Las Vegas Travel Options". About.com. Archived fromthe original on January 12, 2011. RetrievedOctober 24, 2010.
  17. ^Lassen, David (April 24, 2024)."Governments in alignment as Brightline West work begins".Trains. RetrievedApril 25, 2024.
  18. ^"Interstate 15 Northbound – Barstow to Nevada". AARoads. RetrievedOctober 24, 2010.
  19. ^Dowd, Katie (November 27, 2022)."18-mile gridlock on Calif.-Nevada border amid slammed travel day".SFGATE. RetrievedNovember 27, 2022.
  20. ^Ohnsman, Alan (January 24, 2022)."High-Speed Las Vegas Train Back On Track As U.S. Reviews L.A. Extension".Forbes. RetrievedMay 3, 2022.
  21. ^"US infrastructure plan spurs talk of Vegas-LA rail service".AP News. April 18, 2021. RetrievedApril 19, 2021.
  22. ^Ritter, Ken (April 22, 2024)."Rail spikes hammered, bullet train being built from Sin City to the City of Angels".AP News. RetrievedApril 23, 2024.
  23. ^"Virgin Trains USA to Move Ahead on Vegas to Calif. Line".Construction Equipment Guide. October 23, 2019.
  24. ^"West Coast | Brightline".www.gobrightline.com. Archived fromthe original on May 6, 2021. RetrievedSeptember 16, 2020.
  25. ^"LA To Vegas Fact Sheet"(PDF). Brightline. Archived fromthe original(PDF) on January 27, 2021. RetrievedSeptember 16, 2020.
  26. ^"2018 California State Rail Plan (Draft)"(PDF). CalTrans. Archived fromthe original(PDF) on January 29, 2018. RetrievedSeptember 23, 2019.
  27. ^"State Treasurer Fiona Ma announces CDLAC Board approval of $300M in bonds for Apple Valley-Las Vegas high-speed rail".Orange County Breeze. September 21, 2019. Archived fromthe original on September 23, 2019. RetrievedSeptember 23, 2019.
  28. ^Varghese, Romy (December 21, 2021)."Fortress-Backed Rail Company Brightline Gets an Ally in California's Treasurer".Yahoo News | Finance. RetrievedDecember 22, 2021.
  29. ^"California to assist financing of private California-Vegas train". Associated Press. September 19, 2019.
  30. ^"Virgin Trains USA hoping to start construction of train line from Victorville to Las Vegas in 2020".Victor Valley News Group. October 24, 2019.
  31. ^O'Connor, Devin (April 15, 2020)."Virgin Hotels Las Vegas Remains Focused on Fall 2020 Opening, Virgin Trains Receives $600M".Casino.org. RetrievedJuly 1, 2020.
  32. ^Hass, Greg (July 21, 2020)."Financing for DesertXpress line from Las Vegas to Apple Valley takes step forward".KLAS.Archived from the original on July 21, 2020. RetrievedAugust 9, 2020.
  33. ^Ohnsman, Alan (July 24, 2020)."Los Angeles-To-Las Vegas High-Speed Train Wins $200 Million Nevada Bond Allocation".Forbes. RetrievedJuly 29, 2020.
  34. ^abOhnsman, Alan (September 25, 2020)."Rail Startup Brightline Kicks Off $3.2 Billion Bond Sale For LA-To-Vegas High-Speed Train".Forbes. RetrievedSeptember 26, 2020.
  35. ^Akers, Mick (October 5, 2020)."Vegas-to-LA high-speed train could serve as Raiders fan pipeline".Las Vegas Review-Journal. RetrievedOctober 6, 2020.
  36. ^Horwath, Bryan (November 2, 2020)."Las Vegas-California high-speed rail project hits snag".Las Vegas Sun. RetrievedNovember 6, 2020.
  37. ^Akers, Mike (October 26, 2020)."Brightline reveals more details about Vegas-to-LA high-speed rail line".Las Vegas Review-Journal. RetrievedDecember 10, 2020.
  38. ^Akers, Mick (December 9, 2020)."Nevada reallocates $200M in bonds from high-speed rail to affordable housing".Las Vegas Review-Journal. RetrievedDecember 10, 2020.
  39. ^Akers, Mick (June 22, 2021)."Las Vegas-LA high-speed rail plan delayed until 2022".Las Vegas Review-Journal. RetrievedJune 22, 2021.
  40. ^abcDe La Cruz, Rene Ray (January 19, 2021)."With revised plan, Brightline eyes 2021 groundbreaking of Apple Valley rail project".Victor Valley Daily Press. RetrievedJanuary 21, 2021.
  41. ^Komenda, Ed (April 9, 2021)."Brightline CEO: Vegas-to-LA high-speed rail line still on track to break ground in 2021".Reno Gazette Journal. RetrievedApril 11, 2021.
  42. ^"Editorial: It was a terrible idea to build a new freeway in Los Angeles County. Now it's on hold for good".Los Angeles Times. October 6, 2019. RetrievedJuly 17, 2020.
  43. ^Linton, Joe (August 19, 2020)."Metro Looks to Shift High Desert Freeway Funds to High-Speed Rail".Streetsblog Los Angeles.Archived from the original on August 20, 2020. RetrievedAugust 27, 2020.
  44. ^abcAkers, Mick (July 6, 2021)."Brightline buys land for high-speed rail terminal".Las Vegas Review-Journal. RetrievedJuly 9, 2021.
  45. ^abAkers, Mick (February 15, 2023)."Brightline West agrees to build wildlife crossings along I-15".Las Vegas Review-Journal. RetrievedFebruary 17, 2023.
  46. ^Ritter, Ken (April 24, 2023)."Las Vegas-to-California bullet train gets bipartisan backing".ABC News. Associated Press. RetrievedApril 25, 2023.
  47. ^abAkers, Mick (September 26, 2024)."Brightline West's $3B high-speed rail grant signed; heavy construction to begin in 2025".Las Vegas Review-Journal. RetrievedSeptember 26, 2024.
  48. ^Luczak, Marybeth (September 27, 2024)."FRA Advances Brightline West Project With Signed Agreement".Railway Age. RetrievedSeptember 30, 2024.
  49. ^Seeman, Matthew (January 23, 2024)."$2.5 billion in bonds approved for Brightline West high-speed train to Las Vegas".News 3.
  50. ^Luczak, Marybeth (January 23, 2024)."Brightline West Lands $2.5B in Private Activity Bonds".Railway Age. RetrievedSeptember 30, 2024.
  51. ^Ritter, Ken (April 22, 2024)."Rail spikes hammered, bullet train being built from Sin City to the City of Angels".Associated Press News. RetrievedJune 9, 2024.
  52. ^Birenbaum, Gabby (December 5, 2023)."Vegas to L.A. high-speed rail line secures $3 billion in federal funding".The Nevada Independent.Archived from the original on December 5, 2023. RetrievedDecember 5, 2023.
  53. ^Cruz, Rene Ray De La."Cost spikes for Brightline West's high-speed rail project from Vegas to Southern California".Victorville Daily Press. RetrievedOctober 22, 2025.
  54. ^abcBurroughs, David (July 2, 2020)."Virgin Trains plans extension of LA – Las Vegas high-speed line".International Railway Journal. RetrievedJuly 16, 2020.
  55. ^Varghese, Romy (April 18, 2022)."Will a Fast Train to Vegas Lure Road Trippers From Their Cars?".Bloomberg. RetrievedMay 3, 2022.
  56. ^"Comment period begins for environmental report on Brightline West Cajon Pass project".permits.performance.gov. Federal Infrastructure Projects Permitting Dashboard. Archived fromthe original on March 31, 2023. RetrievedApril 21, 2023.
  57. ^"Comment period begins for environmental report on Brightline West Cajon Pass project".Trains. Kalmbach Media. November 10, 2022. RetrievedApril 16, 2023.
  58. ^Akers, Mick (July 14, 2023)."High-speed rail receives key approval for link into LA".Las Vegas Review Journal. RetrievedJuly 15, 2023.
  59. ^abSharp, Steven (July 5, 2023)."$25M awarded for Brightline West stations in Hesperia and Apple Valley".Urbanize LA. RetrievedJuly 8, 2023.
  60. ^"STB approves Brightline West high speed rail modifications and extension across Cajon Pass".Trains. Kalmbach Media. November 20, 2023.
  61. ^McLawhorn, Jennifer (January 18, 2024)."Brightline West Will Begin Hiring Workers and Launch Field Investigation Work".RT&S. Simmons-Boardman Publishing Inc.
  62. ^De La Cruz, Rene Ray (January 29, 2024)."Brightline West conducts fieldwork in California ahead of high-speed rail groundbreaking".Victorville Daily Press. RetrievedJanuary 29, 2024.
  63. ^Schultz, Jaclyn (February 25, 2025)."Brightline project 'on budget, on time,' according to new U.S. Transportation Secretary Sean Duffy".Fox 5 Vegas. RetrievedMarch 1, 2025.
  64. ^Cruz, Rene Ray De La."Brightline West eyes 2026 for California construction of high-speed rail project".Victorville Daily Press. RetrievedOctober 22, 2025.
  65. ^"Brightline West Update: Field Investigation Work in Southern California Advances on I-15 Corridor". Brightline West. August 18, 2025. RetrievedNovember 4, 2025.
  66. ^"Brightline West field work moves forward along I-15 in High Desert".Victor Valley Daily Press. July 7, 2025. RetrievedNovember 4, 2025.
  67. ^"PCM Railone AG invests $20 million in Nevada plant to supply Brightline West".Railway Track & Structures. October 10, 2024. RetrievedNovember 4, 2025.
  68. ^"Brightline West high-speed rail on track to connect Southern California and Las Vegas by 2028".Asian Journal. May 22, 2025. RetrievedNovember 4, 2025.
  69. ^"Caltrans and XpressWest Complete Lease Agreement". Caltrans. June 30, 2020. RetrievedJuly 18, 2020.
  70. ^"Project Description"(PDF). Federal Railroad Administration. September 2023. RetrievedMarch 29, 2024.
  71. ^Akers, Mick (June 30, 2020)."High-speed rail project gets OK to use I-15 right of way in California".Las Vegas Review-Journal. RetrievedJuly 1, 2020.
  72. ^abcdRichard N. Velotta (March 25, 2010)."Work on high-speed rail set to begin this year".Las Vegas Sun. RetrievedOctober 24, 2010.
  73. ^"Digest: Proposed Las Vegas high speed project seeks STB approval of route changes".Trains. September 17, 2020. RetrievedSeptember 18, 2020.
  74. ^Schneider, Benjamin (December 13, 2023)."Brightline's new Las Vegas train line could be the start of a U.S. high-speed rail revolution".Fast Company.
  75. ^"Expansion and connectivity".Desert Xpress. RetrievedJuly 9, 2011.
  76. ^abRichard N. Velotta (June 7, 2012)."DesertXpress inks deal to add train link from Victorville to Palmdale, making travel to L.A. possible".Vegas Inc. Archived fromthe original on October 26, 2014. RetrievedJune 13, 2012.
  77. ^Rosenberg, Mike (July 29, 2012)."Bay Area to Sin City? Las Vegas bullet train backers gamble on record loan".San Jose Mercury News. RetrievedNovember 20, 2012.
  78. ^"China, U.S. Reach Agreement on High-Speed Rail Before Xi Visit".Bloomberg. September 16, 2015.
  79. ^ab"DesertXpress – Las Vegas to Victorville Environmental Impact Statement". Archived fromthe original on May 30, 2009.
  80. ^Lisa Mascaro (July 2, 2009)."Path clears for federal support of fast train to California".Las Vegas Sun. RetrievedOctober 24, 2010.
  81. ^abRichard N. Velotta (June 11, 2012)."DesertXpress Vegas-California rail project renamed". Associated Press. RetrievedJune 13, 2012.
  82. ^ab"The Trains".XpressWest. Archived fromthe original on July 6, 2012. RetrievedJune 13, 2012.
  83. ^"Construction on Las Vegas-California train could start this year".Las Vegas Sun. April 15, 2020. RetrievedJuly 17, 2020.
  84. ^"Brightline West's Modified Alignment Approval Brings High-Speed Rail Project Closer to Reality".Victor Valley News Group. November 21, 2023.
  85. ^Emerson, Elaine (July 6, 2021)."Brightline buys land on Las Vegas Boulevard for planned train terminal".FOX5 Las Vegas. RetrievedJuly 6, 2021.
  86. ^Martin, Bradley (February 11, 2020)."Dine Outdoors at the Virgin Trains Las Vegas Terminal in 2023".Eater Vegas. RetrievedMarch 4, 2020.
  87. ^Akers, Mick (April 22, 2023) [April 21, 2023]."First look: Brightline's Vegas high-speed train station revealed".Las Vegas Review-Journal. RetrievedApril 22, 2023.
  88. ^"Brightline West: High Speed Train from Apple Valley to Las Vegas".Town of Apple Valley.Archived from the original on May 23, 2021. RetrievedJune 4, 2021.
  89. ^"Clark County OKs plans for high-speed train station".Las Vegas Review-Journal. March 4, 2020. RetrievedMarch 5, 2020.
  90. ^"Virgin Trains USA buys land in California".KTNV. March 13, 2020. RetrievedJuly 1, 2020.
  91. ^Akers, Mick (August 2022)."Sisolak believes LV-LA high-speed train will come to fruition".Las Vegas Review-Journal. RetrievedFebruary 18, 2023.
  92. ^"Hesperia Passenger Station Proposed for Cajon Pass High-Speed Rail System connecting Hesperia to Rancho Cucamonga".Victor Valley News Group. November 5, 2022.
  93. ^abcSharp, Steven (July 7, 2020)."High-Speed Train to Las Vegas Takes Another Step Forward".Urbanize LA. Archived fromthe original on July 7, 2020. RetrievedJuly 7, 2020.
  94. ^Cruz, Rene Ray De La (October 27, 2021)."Brightline adds Rancho Cucamonga to high-speed rail project bound for Las Vegas".Victor Valley Daily Press. RetrievedOctober 28, 2021.
  95. ^Darling, Jordan B. (October 27, 2022)."Rancho Cucamonga, SBCTA approve sale of 5 acres for high-speed rail station".The Sun. RetrievedOctober 28, 2022.
  96. ^Lin, Summer (July 27, 2022)."Elon Musk abandoned plans for a four-mile tunnel at Ontario airport. Locals are picking it up".Los Angeles Times. RetrievedJanuary 12, 2023.
  97. ^Brightline."Rancho Cucamonga, SBCTA move progress sale of Cucamonga Station to Brightline West" (Press release). Mass Transit Magazine. RetrievedJanuary 11, 2023.
  98. ^Lilly, Caitlin (June 30, 2020)."XpressWest receives permission to use I-15 right-of-way in California".KVVU-TV. RetrievedJuly 2, 2020.
  99. ^"High-speed train company receives permission to use I-15 right-of-way in California".KTNV. June 30, 2020. RetrievedJuly 1, 2020.
  100. ^Parsons, Jim (July 8, 2020)."Vegas-LA High-Speed Rail Line Can Use Interstate 15 Right-of-Way".Engineering News-Record. RetrievedJuly 17, 2020.
  101. ^De La Cruz, Rene Ray (March 14, 2023)."Brightline, Caltrans to sign pact for Apple Valley to Rancho Cucamonga rail line".Victorville Daily Press. RetrievedMarch 15, 2023.
  102. ^Luczak, Marybeth (October 22, 2021)."Brightline West Project Advancing in California".Railway Age. RetrievedOctober 24, 2021.
  103. ^"Brightline West on Track to Rancho Cucamonga" (Press release). Brightline. October 21, 2021. Archived fromthe original on November 23, 2022. RetrievedJanuary 5, 2023.
  104. ^"Federal Railroad Administration Issues Final Environmental Impact Statement for Brightline West". Federal Railroad Administration. July 17, 2023. RetrievedNovember 4, 2025.
  105. ^Sahagún, Louis (September 16, 2021)."High-speed train to Las Vegas is hailed as an eco jackpot. But will it harm desert sheep?".Los Angeles Times. RetrievedMarch 9, 2023.
  106. ^Martinez, Christian (February 16, 2023)."As trains tear from L.A. to Vegas at 180 mph, bighorn sheep will have safe passage".Los Angeles Times. RetrievedMarch 9, 2023.
  107. ^"Brightline West Sustainability Update 2025". Brightline West. March 2025. RetrievedNovember 4, 2025.
  108. ^DesertXpress "XpressWest" – Las Vegas to Victorville environmental review (Report). Federal Railroad Administration.
  109. ^"I-15 Comprehensive Corridor Study"(PDF). San Bernardino County Transportation Authority. December 20, 2005. p. 4.steep grades approaching 6% sustained for approximately 5 miles through the Cajon Pass...
  110. ^Mann, Ted (September 6, 2023)."European Rail Giants Fight for Slice of U.S. High-Speed Train Line".WSJ.
  111. ^"Brightline West Presentation (High Speed Rail 2023 Conference)"(video).youtube.com. US High Speed Rail Association. May 23, 2023.
  112. ^ab"Brightline West Selects Siemens To Manufacture High Speed Rail Train Sets" (Press release). Siemens Mobility. May 1, 2024.Archived from the original on May 1, 2024. RetrievedMay 1, 2024.
  113. ^"FRA-2020-0096 Decision Letter 2023".www.regulations.gov.Federal Railroad Administration. March 14, 2023. RetrievedMarch 23, 2023.
  114. ^"The American Pioneer 220: High Speed Rail for the U.S."Siemens Mobility Global.
  115. ^"ICE S auf Messfahrt mit dem EWET – Nürnberger Eisenbahnfreunde e.V." (in German). October 30, 2021. RetrievedMarch 9, 2023.
  116. ^"Siemens reveals Velaro Novo 360 km/h train concept".Railway Gazette International. June 13, 2018. Archived fromthe original on November 9, 2020. RetrievedMay 4, 2024.
  117. ^"Velaro Novo".Siemens Mobility Global.
  118. ^abSimmons, Mark (January 22, 2024)."Brightline West starts preparatory works".International Railway Journal.Archived from the original on January 22, 2024. RetrievedJanuary 22, 2024.
  119. ^"First US high-speed rail production facility to set up shop in Horseheads, New York".Trains. September 9, 2024.Archived from the original on September 11, 2024. RetrievedSeptember 9, 2024.
  120. ^"Siemens unveils design updates for Brightline West's high-speed trains".Trains Magazine. June 10, 2025. RetrievedNovember 4, 2025.
  121. ^"Brightline West trainsets to meet Buy America standards".Railway Age. August 20, 2025. RetrievedNovember 4, 2025.
  122. ^"Siemens Horseheads plant begins work on Brightline West high-speed trainsets". Railway Gazette International. May 2025. RetrievedNovember 4, 2025.
  123. ^"Brightline West Train Production Timeline Update". Brightline West. October 2025. RetrievedNovember 4, 2025.
  124. ^Golden, Jessica; Brewer, Contessa (March 30, 2022)."Stadium developer plans $3 billion sports arena and casino project in Las Vegas".CNBC. RetrievedMay 3, 2022.
  125. ^Stutz, Howard (June 15, 2023)."Vegas basketball arena developer says $10B project is growing, won't require public money".The Nevada Independent. RetrievedJanuary 16, 2024.
  126. ^"Oak View Group Acquires 25 Acres in Las Vegas With Vision to Build Retail & Entertainment District Including 20,000 Seat Arena, Casino and Hotel" (Press release).Oak View Group. March 30, 2022. RetrievedJanuary 16, 2024 – viaPR Newswire.
  127. ^Hemmersmeier, Sean (June 25, 2024)."German railway manufacturer to open $20M facility in North Las Vegas".Las Vegas Review-Journal. RetrievedJune 27, 2024.
  128. ^"KVBC Las Vegas Story".KVBC Television. Las Vegas, Nevada. July 25, 2006. Archived fromthe original on September 27, 2007. RetrievedOctober 1, 2020.
  129. ^Velotta, Richard N. (October 22, 2010)."Pressure on DesertXpress in first run at high-speed rail".Las Vegas Sun. RetrievedOctober 24, 2010.
  130. ^"Conduit Exempt Facility Bondfinancing: DesertXpress Enterprises, LLC"(PDF). California Infrastructure and Economic Development Bank. 2018. Archived fromthe original(PDF) on April 20, 2020. RetrievedApril 20, 2020.
  131. ^"Federal Railroad Administration, Environmental Impact Statement: DesertXpress High Speed Train Between Apple Valley, CA and Las Vegas, NV"(PDF).Federal Register.71 (135): 40176−40177. July 14, 2006. RetrievedApril 20, 2020.
  132. ^Maldonado, Cinthia (August 28, 2019)."High-speed train back on track, construction set for 2020".KTNV. RetrievedSeptember 6, 2019.
  133. ^abRichard N. Velotta (March 25, 2011)."DesertXpress high-speed rail project rolls forward".Las Vegas Sun. RetrievedMay 9, 2011.
  134. ^abCy Ryan (October 10, 2011)."DesertXpress hopes for federal loan, aims for 2012 start on work".Las Vegas Sun. Archived fromthe original on November 9, 2011. RetrievedOctober 28, 2011.
  135. ^"STB approves DesertXpress route". Progressive Railroading. October 27, 2011.Archived from the original on May 9, 2012. RetrievedOctober 28, 2011.
  136. ^Gloria Hillard (April 30, 2012)."Towns Debate Impact of Calif.-Las Vegas Bullet Train". NPR. RetrievedJune 13, 2012.
  137. ^"Proven, Reliable, Safe Technology".DesertXpress. 2008. Archived fromthe original on June 12, 2008. RetrievedAugust 8, 2008.
  138. ^Benjamin Spillman (June 28, 2009)."DesertXpress on right track?".Las Vegas Review-Journal.
  139. ^"Progress".DesertXpress. RetrievedOctober 16, 2011.
  140. ^Tavss, Jeff (December 8, 2023)."Plans for high-speed rail between Salt Lake City and Las Vegas not moving forward".FOX 13 News Utah (KSTU). RetrievedDecember 9, 2023.
  141. ^"The Network".XpressWest. Archived fromthe original on April 28, 2019. RetrievedJune 13, 2012.
  142. ^"High Speed Rail To Las Vegas Breaks Ground 2017".Canyon News. March 30, 2017. RetrievedFebruary 20, 2018.
  143. ^Laura Carroll (February 12, 2013)."High-speed train project at least months away from start".Las Vegas Review-Journal. RetrievedMarch 8, 2013.
  144. ^Velotta, Richard N. (April 22, 2017)."Arrival of Las Vegas Raiders breathes new life into high-speed rail project".Las Vegas Review-Journal. RetrievedApril 23, 2017.
  145. ^Demirjian, Karoun (March 18, 2013)."High-speed rail project beset by political mine fields".Las Vegas Sun. RetrievedJuly 23, 2013.
  146. ^"Letter from Ryan and Sessions to LaHood". United States Senate Committee on the Budget Republicans. RetrievedJuly 23, 2013.
  147. ^Warren, Mackenzie (July 12, 2013)."Feds suspend $5.5B loan application for XpressWest".KSNV MyNews3.com. Archived fromthe original on October 19, 2013. RetrievedJuly 23, 2013.
  148. ^Tetreault, Steve (July 16, 2013)."Feds: XPressWest failed to meet 'Buy America' rules for high-speed train".Las Vegas Review Journal. RetrievedJuly 23, 2013.
  149. ^"XpressWest vows to proceed, despite federal loan denial".Railway Track & Structures. July 22, 2013. RetrievedJuly 23, 2013.
  150. ^"Las Vegas rail service plans have seen starts, stops".Las Vegas Review-Journal. September 2, 2014. RetrievedJanuary 13, 2014.
  151. ^Young, Allen (May 26, 2015)."Nevada joins the high-speed rail bandwagon with plans for Vegas, SoCal link". RetrievedMay 28, 2015.
  152. ^"Vote on SB457".Nevada Legislature. Nevada Legislative Counsel Bureau. May 20, 2015. RetrievedMay 28, 2015.
  153. ^Nevada Legislature SB457, Nevada State Legislature, retrievedJuly 15, 2015 (Became Chapter 260 – seeBills signed by Governor)
  154. ^"US-Chinese joint venture to develop Las Vegas high speed line".Railway Gazette International. September 18, 2015. Archived fromthe original on September 26, 2015. RetrievedSeptember 29, 2015.
  155. ^Makien, Julie (September 18, 2015)."A high-speed rail from L.A. to Las Vegas? China says it's partnering with U.S. to build".Los Angeles Times.
  156. ^Makinen, Julie (June 8, 2016)."China will not build L.A.-to-Vegas rail line – U.S. company calls the deal off".Los Angeles Times. RetrievedJune 9, 2016.

Further reading

[edit]

External links

[edit]
Template:Attached KML/Brightline West
KML is not from Wikidata
Stations
Planned stations
Rolling stock
Connecting services
Related
  • NOTE: Entire system is under construction
  • Category
Stations
Rolling stock
Related
Connecting services
Brightline West
  • Italics indicate future services
  • Category
Technologies
Proposed
High-speed trains
by service speed
or planned service speed
400 km/h
(249 mph)
or more
350–399 km/h
(217–248 mph)
300–349 km/h
(186–217 mph)
250–299 km/h
(155–186 mph)
200–249 km/h
(124–155 mph)
High-speed railway line
By countries and territories

planned networks in italics
Africa
Americas
Asia
Europe
Oceania
Services
Active
Under construction
Planned
Higher-speed rail
90 to 125 mph (145 to 201 km/h)