Apollo program

This is a good article. Click here for more information.
From Wikipedia, the free encyclopedia
(Redirected fromApollo project)
1961–1972 American crewed lunar exploration program

Apollo program
The letter "A" printed with a depiction of a trans-lunar trajectory streaking across; the Moon and Earth are depicted on opposite sides of the "A", with Apollo's face outlined on the Moon
Program overview
CountryUnited States
OrganizationNASA
PurposeCrewedlunar landing
StatusCompleted
Program history
Cost
  • $25.4 billion (1973)
  • $257 billion (2020)[1]
Duration1961–1972
First flight
  • SA-1
  • October 27, 1961 (1961-10-27)
First crewed flight
  • Apollo 7
  • October 11, 1968 (1968-10-11)
Last flight
Successes32
Failures2 (Apollo 1 and13)
Partial failures1 (Apollo 6)
Launch site(s)
Vehicle information
Crewed vehicle(s)
Launch vehicle(s)
Part ofa series on the
United States space program

TheApollo program, also known asProject Apollo, was the United Stateshuman spaceflight program led byNASA, which successfullylanded the first humans on theMoon in 1969.[2] Apollo followedProject Mercury that put the first Americans in space. It was conceived in 1960 as a three-person spacecraft during PresidentDwight D. Eisenhower's administration. Apollo was later dedicated to PresidentJohn F. Kennedy's national goal for the 1960s of "landing a man on the Moon and returning him safely to the Earth" in an address toCongress on May 25, 1961. It was the third US human spaceflight program to fly, preceded byProject Gemini conceived in 1961 to extend spaceflight capability in support of Apollo.

Kennedy's goal was accomplished on theApollo 11 mission when astronautsNeil Armstrong andBuzz Aldrin landed theirApollo Lunar Module (LM) on July 20, 1969, and walked on the lunar surface, whileMichael Collins remained inlunar orbit in thecommand and service module (CSM), and all three landed safely on Earth in the Pacific Ocean on July 24. Five subsequent Apollo missions also landedastronauts on the Moon, the last,Apollo 17, in December 1972. In these six spaceflights,twelve people walked on the Moon.

Astronaut Buzz Aldrin, standing on the Moon
Buzz Aldrin (pictured) walked on theMoon withNeil Armstrong, onApollo 11, July 20–21, 1969.
NASA Apollo 17Lunar Roving Vehicle
Earthrise, the iconic 1968 image fromApollo 8 taken by astronautWilliam Anders

Apollo ran from 1961 to 1972, with the first crewed flight in 1968. It encountered a major setback in 1967 when anApollo 1 cabin fire killed the entire crew during a prelaunch test. After the first successful landing, sufficient flight hardware remained for nine follow-on landings with a plan for extended lunargeological andastrophysical exploration. Budget cuts forced the cancellation of three of these. Five of the remaining six missions achieved successful landings, but theApollo 13 landing had to be aborted after an oxygen tank exploded en route to the Moon, crippling the CSM. The crew barely managed a safe return to Earth by using the lunar module as a "lifeboat" on the return journey. Apollo used theSaturn family of rockets as launch vehicles, which were also used for anApollo Applications Program, which consisted ofSkylab, aspace station that supported three crewed missions in 1973–1974, and theApollo–Soyuz Test Project, a jointUnited States-Soviet Unionlow Earth orbit mission in 1975.

Apollo set several majorhuman spaceflight milestones. It stands alone in sending crewed missions beyondlow Earth orbit.Apollo 8 was the first crewed spacecraft to orbit another celestial body, and Apollo 11 was the first crewed spacecraft to land humans on one.

Overall, the Apollo program returned 842 pounds (382 kg) of lunar rocks and soil to Earth, greatly contributing to the understanding of the Moon's composition and geological history. The program laid the foundation for NASA's subsequent human spaceflight capability and funded construction of itsJohnson Space Center andKennedy Space Center. Apollo also spurred advances in many areas of technology incidental to rocketry and human spaceflight, includingavionics, telecommunications, and computers.

Name

[edit]

The program was named afterApollo, the Greek god of light, music, and the Sun, by NASA managerAbe Silverstein, who later said, "I was naming the spacecraft like I'd name my baby."[3] Silverstein chose the name at home one evening, early in 1960, because he felt "Apollo riding his chariot across the Sun was appropriate to the grand scale of the proposed program".[4]

The context of this was that the program focused at its beginning mainly on developing an advanced crewed spacecraft, theApollo command and service module, succeeding theMercury program. Alunar landing became the focus of the program only in 1961.[5] ThereafterProject Gemini instead followed the Mercury program to test and study advanced crewed spaceflight technology.

Background

[edit]

Origin and spacecraft feasibility studies

[edit]
Main article:Apollo spacecraft feasibility study

The Apollo program was conceived during the Eisenhower administration in early 1960, as a follow-up to Project Mercury. While the Mercurycapsule could support only one astronaut on a limited Earth orbital mission, Apollo would carry three. Possible missions included ferrying crews to aspace station,circumlunar flights, and eventual crewedlunar landings.

In July 1960, NASA Deputy AdministratorHugh L. Dryden announced the Apollo program to industry representatives at a series ofSpace Task Group conferences. Preliminary specifications were laid out for a spacecraft with amission module cabin separate from thecommand module (piloting and reentry cabin), and apropulsion and equipment module. On August 30, a feasibility study competition was announced, and on October 25, three study contracts were awarded toGeneral Dynamics/Convair,General Electric, and theGlenn L. Martin Company. Meanwhile, NASA performed its own in-house spacecraft design studies led byMaxime Faget, to serve as a gauge to judge and monitor the three industry designs.[6]

Political pressure builds

[edit]
Main articles:Space Race andSputnik crisis

In November 1960,John F. Kennedy was elected president after acampaign that promised American superiority over theSoviet Union in the fields ofspace exploration andmissile defense. Up to the election of 1960, Kennedy had been speaking out against the "missile gap" that he and many other senators said had developed between the Soviet Union and the United States due to the inaction of President Eisenhower.[7] Beyond military power, Kennedy used aerospace technology as a symbol of national prestige, pledging to make the US not "first but, first and, first if, but first period".[8] Despite Kennedy's rhetoric, he did not immediately come to a decision on the status of the Apollo program once he became president. He knew little about the technical details of the space program, and was put off by the massive financial commitment required by a crewed Moon landing.[9] When Kennedy's newly appointed NASA AdministratorJames E. Webb requested a 30 percent budget increase for his agency, Kennedy supported an acceleration of NASA's large booster program but deferred a decision on the broader issue.[10]

On April 12, 1961, SovietcosmonautYuri Gagarin became the first person to fly in space, reinforcing American fears about being left behind in a technological competition with the Soviet Union. At a meeting of the US HouseCommittee on Science and Astronautics one day after Gagarin's flight, many congressmen pledged their support for a crash program aimed at ensuring that America would catch up.[11] Kennedy was circumspect in his response to the news, refusing to make a commitment on America's response to the Soviets.[12]

President John F. Kennedy addresses a joint session of Congress, with Vice President Lyndon B. Johnson and House Speaker Sam Rayburn seated behind him
PresidentKennedy delivers his proposal to put a man on the Moon before a joint session ofCongress, May 25, 1961.

On April 20, Kennedy sent a memo toVice PresidentLyndon B. Johnson, asking Johnson to look into the status of America's space program, and into programs that could offer NASA the opportunity to catch up.[13][14] Johnson responded approximately one week later, concluding that "we are neither making maximum effort nor achieving results necessary if this country is to reach a position of leadership."[15][16] His memo concluded that a crewed Moon landing was far enough in the future that it was likely the United States would achieve it first.[15]

On May 25, 1961, twenty days after the first US crewed spaceflightFreedom 7, Kennedy proposed the crewed Moon landing in aSpecial Message to the Congress on Urgent National Needs:

Now it is time to take longer strides—time for a great new American enterprise—time for this nation to take a clearly leading role in space achievement, which in many ways may hold the key to our future on Earth.

... I believe that this nation should commit itself to achieving the goal, before this decade is out, of landing a man on the Moon and returning him safely to the Earth. No single space project in this period will be more impressive to mankind, or more important in the long-range exploration of space; and none will be so difficult or expensive to accomplish.[17][a]

NASA expansion

[edit]

At the time of Kennedy's proposal, only one American had flown in space—less than a month earlier—and NASA had not yet sent an astronaut into orbit. Even some NASA employees doubted whether Kennedy's ambitious goal could be met.[18] By 1963, Kennedy even came close to agreeing to a joint US-USSR Moon mission, to eliminate duplication of effort.[19]

With the clear goal of a crewed landing replacing the more nebulous goals of space stations and circumlunar flights, NASA decided that, in order to make progress quickly, it would discard the feasibility study designs of Convair, GE, and Martin, and proceed with Faget's command and service module design. The mission module was determined to be useful only as an extra room, and therefore unnecessary.[20] They used Faget's design as the specification for another competition for spacecraft procurement bids in October 1961. On November 28, 1961, it was announced thatNorth American Aviation had won the contract, although its bid was not rated as good as the Martin proposal. Webb, Dryden andRobert Seamans chose it in preference due to North American's longer association with NASA andits predecessor.[21]

Landing humans on the Moon by the end of 1969 required the most sudden burst of technological creativity, and the largest commitment of resources ($25 billion; $182 billion in 2023 US dollars)[22] ever made by any nation in peacetime. At its peak, the Apollo program employed 400,000 people and required the support of over 20,000 industrial firms and universities.[23]

On July 1, 1960, NASA established theMarshall Space Flight Center (MSFC) inHuntsville, Alabama. MSFC designed the heavy lift-classSaturn launch vehicles, which would be required for Apollo.[24]

Manned Spacecraft Center

[edit]
Main article:Johnson Space Center

It became clear that managing the Apollo program would exceed the capabilities ofRobert R. Gilruth'sSpace Task Group, which had been directing the nation's crewed space program from NASA'sLangley Research Center. So Gilruth was given authority to grow his organization into a new NASA center, theManned Spacecraft Center (MSC). A site was chosen inHouston, Texas, on land donated byRice University, and Administrator Webb announced the conversion on September 19, 1961.[25] It was also clear NASA would soon outgrow its practice of controlling missions from itsCape Canaveral Air Force Station launch facilities in Florida, so a newMission Control Center would be included in the MSC.[26]

President Kennedy speaks atRice University, September 12, 1962 (17 min, 47 s).

In September 1962, by which time two Project Mercury astronauts had orbited the Earth, Gilruth had moved his organization to rented space in Houston, and construction of the MSC facility was under way, Kennedy visited Rice to reiterate his challenge ina famous speech:

But why, some say, the Moon? Why choose this as our goal? And they may well ask, whyclimb the highest mountain? Why, 35 years ago,fly the Atlantic? ...We choose to go to the Moon. We choose to go to the Moon in this decade and do the other things, not because they are easy, but because they are hard; because that goal will serve to organize and measure the best of our energies and skills; because that challenge is one that we are willing to accept, one we are unwilling to postpone, and one we intend to win ...[27][b]

The MSC was completed in September 1963. It was renamed by theUnited States Congress in honor ofLyndon B. Johnson soon after his death in 1973.[28]

Launch Operations Center

[edit]
Main article:Kennedy Space Center

It also became clear that Apollo would outgrow the Canaveral launch facilities inFlorida. The two newest launch complexes were already being built for theSaturn I andIB rockets at the northernmost end:LC-34 andLC-37. But an even bigger facility would be needed for the mammoth rocket required for the crewed lunar mission, so land acquisition was started in July 1961 for a Launch Operations Center (LOC) immediately north of Canaveral atMerritt Island. The design, development and construction of the center was conducted byKurt H. Debus, a member ofWernher von Braun's originalV-2 rocket engineering team. Debus was named the LOC's first Director.[29] Construction began in November 1962. FollowingKennedy's death, President Johnson issued an executive order on November 29, 1963, to rename the LOC and Cape Canaveral in honor of Kennedy.[30]

George Mueller,Wernher von Braun, andEberhard Rees watch theAS-101 launch from the firing room.

The LOC includedLaunch Complex 39, aLaunch Control Center, and a 130-million-cubic-foot (3,700,000 m3)Vertical Assembly Building (VAB).[31] in which the space vehicle (launch vehicle and spacecraft) would be assembled on amobile launcher platform and then moved by acrawler-transporter to one of several launch pads. Although at least three pads were planned, only two, designated A and B, were completed in October 1965. The LOC also included anOperations and Checkout Building (OCB) to whichGemini and Apollo spacecraft were initially received prior to being mated to their launch vehicles. The Apollo spacecraft could be tested in twovacuum chambers capable of simulating atmospheric pressure at altitudes up to 250,000 feet (76 km), which is nearly a vacuum.[32][33]

Organization

[edit]

AdministratorWebb realized that in order to keep Apollo costs under control, he had to develop greater project management skills in his organization, so he recruitedGeorge E. Mueller for a high management job. Mueller accepted, on the condition that he have a say in NASA reorganization necessary to effectively administer Apollo. Webb then worked with Associate Administrator (later Deputy Administrator) Seamans to reorganize the Office of Manned Space Flight (OMSF).[34] On July 23, 1963, Webb announced Mueller's appointment as Deputy Associate Administrator for Manned Space Flight, to replace then Associate AdministratorD. Brainerd Holmes on his retirement effective September 1. Under Webb's reorganization, the directors of the Manned Spacecraft Center (Gilruth),Marshall Space Flight Center (von Braun), and the Launch Operations Center (Debus) reported to Mueller.[35]

Based on his industry experience on Air Force missile projects, Mueller realized some skilled managers could be found among high-ranking officers in theU.S. Air Force, so he got Webb's permission to recruit GeneralSamuel C. Phillips, who gained a reputation for his effective management of theMinuteman program, as OMSF program controller. Phillips's superior officerBernard A. Schriever agreed to loan Phillips to NASA, along with a staff of officers under him, on the condition that Phillips be made Apollo Program Director. Mueller agreed, and Phillips managed Apollo from January 1964, until it achieved the first human landing in July 1969, after which he returned to Air Force duty.[36]

Charles Fishman, inOne Giant Leap, estimated the number of people and organizations involved into the Apollo program as "410,000 men and women at some 20,000 different companies contributed to the effort".[37]

Choosing a mission mode

[edit]
See also:Moon landing
John Houbolt explaining theLOR concept
Early Apollo configuration forDirect Ascent andEarth Orbit Rendezvous, 1961

Once Kennedy had defined a goal, the Apollo mission planners were faced with the challenge of designing a spacecraft that could meet it while minimizing risk to human life, limiting cost, and not exceeding limits in possible technology and astronaut skill. Four possible mission modes were considered:

  • Direct Ascent: The spacecraft would be launched as a unit and travel directly to the lunar surface, without first going into lunar orbit. A 50,000-pound (23,000 kg) Earth return ship would land all three astronauts atop a 113,000-pound (51,000 kg) descent propulsion stage,[38] which would be left on the Moon. This design would have required development of the extremely powerfulSaturn C-8 orNova launch vehicle to carry a 163,000-pound (74,000 kg) payload to the Moon.[39]
  • Earth Orbit Rendezvous (EOR): Multiple rocket launches (up to 15 in some plans) would carry parts of the Direct Ascent spacecraft and propulsion units fortranslunar injection (TLI). These would be assembled into a single spacecraft in Earth orbit.
  • Lunar Surface Rendezvous: Two spacecraft would be launched in succession. The first, an automated vehicle carrying propellant for the return to Earth, would land on the Moon, to be followed some time later by the crewed vehicle. Propellant would have to be transferred from the automated vehicle to the crewed vehicle.[40]
  • Lunar Orbit Rendezvous (LOR): This turned out to be the winning configuration, which achieved the goal withApollo 11 on July 20, 1969: a singleSaturn V launched a 96,886-pound (43,947 kg) spacecraft that was composed of a 63,608-pound (28,852 kg)Apollo command and service module which remained in orbit around the Moon and a 33,278-pound (15,095 kg) two-stageApollo Lunar Module spacecraft which was flown by two astronauts to the surface, flown back to dock with the command module and was then discarded.[41] Landing the smaller spacecraft on the Moon, and returning an even smaller part (10,042 pounds or 4,555 kilograms) to lunar orbit, minimized the total mass to be launched from Earth, but this was the last method initially considered because of the perceived risk of rendezvous and docking.

In early 1961, direct ascent was generally the mission mode in favor at NASA. Many engineers feared that rendezvous and docking, maneuvers that had not been attempted inEarth orbit, would be nearly impossible inlunar orbit. LOR advocates includingJohn Houbolt at Langley Research Center emphasized the important weight reductions that were offered by the LOR approach. Throughout 1960 and 1961, Houbolt campaigned for the recognition of LOR as a viable and practical option. Bypassing the NASA hierarchy, he sent a series of memos and reports on the issue to Associate Administrator Robert Seamans; while acknowledging that he spoke "somewhat as a voice in the wilderness", Houbolt pleaded that LOR should not be discounted in studies of the question.[42]

Seamans's establishment of an ad hoc committee headed by his special technical assistant Nicholas E. Golovin in July 1961, to recommend alaunch vehicle to be used in the Apollo program, represented a turning point in NASA's mission mode decision.[43] This committee recognized that the chosen mode was an important part of the launch vehicle choice, and recommended in favor of a hybrid EOR-LOR mode. Its consideration of LOR—as well as Houbolt's ceaseless work—played an important role in publicizing the workability of the approach. In late 1961 and early 1962, members of the Manned Spacecraft Center began to come around to support LOR, including the newly hired deputy director of the Office of Manned Space Flight,Joseph Shea, who became a champion of LOR.[44] The engineers at Marshall Space Flight Center (MSFC), who were heavily invested in direct ascent, took longer to become convinced of its merits, but their conversion was announced by Wernher von Braun at a briefing on June 7, 1962.[45]

But even after NASA reached internal agreement, it was far from smooth sailing. Kennedy'sscience advisorJerome Wiesner, who had expressed his opposition to human spaceflight to Kennedy before the President took office,[46] and had opposed the decision to land people on the Moon, hired Golovin, who had left NASA, to chair his own "Space Vehicle Panel", ostensibly to monitor, but actually to second-guess NASA's decisions on theSaturn V launch vehicle and LOR by forcing Shea, Seamans, and even Webb to defend themselves, delaying its formal announcement to the press on July 11, 1962, and forcing Webb to still hedge the decision as "tentative".[47]

Wiesner kept up the pressure, even making the disagreement public during a two-day September visit by the President toMarshall Space Flight Center. Wiesner blurted out "No, that's no good" in front of the press, during a presentation by von Braun. Webb jumped in and defended von Braun, until Kennedy ended the squabble by stating that the matter was "still subject to final review". Webb held firm and issued arequest for proposal to candidate Lunar Excursion Module (LEM) contractors. Wiesner finally relented, unwilling to settle the dispute once and for all in Kennedy's office, because of the President's involvement with the OctoberCuban Missile Crisis, and fear of Kennedy's support for Webb. NASA announced the selection ofGrumman as the LEM contractor in November 1962.[48]

Space historian James Hansen concludes that:

Without NASA's adoption of this stubbornly held minority opinion in 1962, the United States may still have reached the Moon, but almost certainly it would not have been accomplished by the end of the 1960s, President Kennedy's target date.[49]

The LOR method had the advantage of allowing the lander spacecraft to be used as a "lifeboat" in the event of a failure of the command ship. Some documents prove this theory was discussed before and after the method was chosen. In 1964 an MSC study concluded, "TheLM [as lifeboat] ... was finally dropped, because no single reasonableCSM failure could be identified that would prohibit use of theSPS."[50] Ironically, just such a failure happened onApollo 13 when an oxygen tank explosion left the CSM without electrical power. The lunar module provided propulsion, electrical power and life support to get the crew home safely.[51]

Spacecraft

[edit]
Main article:Apollo (spacecraft)
An Apolloboilerplate command module is on exhibit in theMeteor Crater Visitor Center inWinslow, Arizona.

Faget's preliminary Apollo design employed a cone-shaped command module, supported by one of several service modules providing propulsion and electrical power, sized appropriately for the space station, cislunar, and lunar landing missions. Once Kennedy's Moon landing goal became official, detailed design began of a command and service module (CSM) in which the crew would spend the entire direct-ascent mission and lift off from the lunar surface for the return trip, after being soft-landed by a larger landing propulsion module. The final choice of lunar orbit rendezvous changed the CSM's role to the translunar ferry used to transport the crew, along with a new spacecraft, the Lunar Excursion Module (LEM, later shortened to LM (Lunar Module) but still pronounced/ˈlɛm/) which would take two individuals to the lunar surface and return them to the CSM.[52]

Command and service module

[edit]
Main article:Apollo command and service module
The cone-shaped command module, attached to the cylindrical service module, orbits the Moon with a panel removed, exposing the scientific instrument module
Apollo 15CSMEndeavour in lunar orbit

Thecommand module (CM) was the conical crew cabin, designed to carry three astronauts from launch to lunar orbit and back to an Earth ocean landing. It was the only component of the Apollo spacecraft to survive without major configuration changes as the program evolved from the early Apollo study designs. Its exterior was covered with anablative heat shield, and had its ownreaction control system (RCS) engines tocontrol its attitude and steer itsatmospheric entry path. Parachutes were carried to slow its descent to splashdown. The module was 11.42 feet (3.48 m) tall, 12.83 feet (3.91 m) in diameter, and weighed approximately 12,250 pounds (5,560 kg).[53]

Original cockpit of the command module of Apollo 11 with three seats, photographed from above. It is located in theNational Air and Space Museum; the very high resolution image was produced in 2007 by theSmithsonian Institution.

A cylindricalservice module (SM) supported the command module, with a service propulsion engine and an RCS with propellants, and afuel cell power generation system withliquid hydrogen andliquid oxygen reactants. A high-gainS-band antenna was used for long-distance communications on the lunar flights. On the extended lunar missions, an orbital scientific instrument package was carried. The service module was discarded just before reentry. The module was 24.6 feet (7.5 m) long and 12.83 feet (3.91 m) in diameter. The initial lunar flight version weighed approximately 51,300 pounds (23,300 kg) fully fueled, while a later version designed to carry a lunar orbit scientific instrument package weighed just over 54,000 pounds (24,000 kg).[53]

North American Aviation won the contract to build the CSM, and also the second stage of the Saturn V launch vehicle for NASA. Because the CSM design was started early before the selection of lunar orbit rendezvous, the service propulsion engine was sized to lift the CSM off the Moon, and thus was oversized to about twice the thrust required for translunar flight.[54] Also, there was no provision for docking with the lunar module. A 1964 program definition study concluded that the initial design should be continued as Block I which would be used for early testing, while Block II, the actual lunar spacecraft, would incorporate the docking equipment and take advantage of the lessons learned in Block I development.[52]

Apollo Lunar Module

[edit]
Main article:Apollo Lunar Module
Apollo 11Lunar ModuleEagle (andBuzz Aldrin) on the Moon, photographed byNeil Armstrong

TheApollo Lunar Module (LM) was designed to descend from lunar orbit to land two astronauts on the Moon and take them back to orbit to rendezvous with the command module. Not designed to fly through the Earth's atmosphere or return to Earth, its fuselage was designed totally without aerodynamic considerations and was of an extremely lightweight construction. It consisted of separate descent and ascent stages, each with its own engine. The descent stage contained storage for the descent propellant, surface stay consumables, and surface exploration equipment. The ascent stage contained the crew cabin, ascent propellant, and a reaction control system. The initial LM model weighed approximately 33,300 pounds (15,100 kg), and allowed surface stays up to around 34 hours. Anextended lunar module (ELM) weighed over 36,200 pounds (16,400 kg), and allowed surface stays of more than three days.[53] The contract for design and construction of the lunar module was awarded toGrumman Aircraft Engineering Corporation, and the project was overseen byThomas J. Kelly.[55]

Launch vehicles

[edit]
Four Apollo rocket assemblies, drawn to scale:Little Joe II,Saturn I,Saturn IB, andSaturn V

Before the Apollo program began, Wernher von Braun and his team of rocket engineers had started work on plans for very large launch vehicles, theSaturn series, and the even largerNova series. In the midst of these plans, von Braun was transferred from the Army to NASA and was made Director of the Marshall Space Flight Center. The initial direct ascent plan to send the three-person Apollo command and service module directly to the lunar surface, on top of a large descent rocket stage, would require a Nova-class launcher, with a lunar payload capability of over 180,000 pounds (82,000 kg).[56] The June 11, 1962, decision to use lunar orbit rendezvous enabled the Saturn V to replace the Nova, and the MSFC proceeded to develop theSaturn rocket family for Apollo.[57]

Since Apollo, like Mercury, used more than one launch vehicle for space missions, NASA used spacecraft-launch vehicle combination series numbers: AS-10x for Saturn I, AS-20x for Saturn IB, and AS-50x for Saturn V (compareMercury-Redstone 3,Mercury-Atlas 6) to designate and plan all missions, rather than numbering them sequentially as in Project Gemini. This was changed by the time human flights began.[58]

Little Joe II

[edit]
Main article:Little Joe II

Since Apollo, like Mercury, would require alaunch escape system (LES) in case of a launch failure, a relatively small rocket was required for qualification flight testing of this system. A rocket bigger than theLittle Joe used by Mercury would be required, so theLittle Joe II was built byGeneral Dynamics/Convair. After an August 1963qualification test flight,[59] four LES test flights (A-001 through004) were made at theWhite Sands Missile Range between May 1964 and January 1966.[60]

Saturn I

[edit]
Main article:Saturn I
A Saturn IB rocket launchesApollo 7, 1968

Saturn I, the first US heavy lift launch vehicle, was initially planned to launch partially equipped CSMs in low Earth orbit tests. TheS-I first stage burnedRP-1 with liquid oxygen (LOX) oxidizer in eight clusteredRocketdyne H-1 engines, to produce 1,500,000 pounds-force (6,670 kN) of thrust. TheS-IV second stage used six liquid hydrogen-fueledPratt & WhitneyRL-10 engines with 90,000 pounds-force (400 kN) of thrust. TheS-V third stage flew inactively on Saturn I four times.[61]

The first four Saturn I test flights were launched from LC-34, with only the first stage live, carrying dummy upper stages filled with water. The first flight with a live S-IV was launched from LC-37. This was followed by five launches ofboilerplate CSMs (designatedAS-101 throughAS-105) into orbit in 1964 and 1965. The last three of these further supported the Apollo program by also carryingPegasus satellites, which verified the safety of the translunar environment by measuring the frequency and severity ofmicrometeorite impacts.[62]

In September 1962, NASA planned to launch four crewed CSM flights on the Saturn I from late 1965 through 1966, concurrent with Project Gemini. The 22,500-pound (10,200 kg) payload capacity[63] would have severely limited the systems which could be included, so the decision was made in October 1963 to use the upratedSaturn IB for all crewed Earth orbital flights.[64]

Saturn IB

[edit]
Main article:Saturn IB

The Saturn IB was an upgraded version of the Saturn I. TheS-IB first stage increased the thrust to 1,600,000 pounds-force (7,120 kN) by uprating the H-1 engine. The second stage replaced the S-IV with theS-IVB-200, powered by a singleJ-2 engine burning liquid hydrogen fuel with LOX, to produce 200,000pounds-force (890 kN) of thrust.[65] A restartable version of the S-IVB was used as the third stage of the Saturn V. The Saturn IB could send over 40,000 pounds (18,100 kg) into low Earth orbit, sufficient for a partially fueled CSM or the LM.[66] Saturn IB launch vehicles and flights were designated with an AS-200 series number, "AS" indicating "Apollo Saturn" and the "2" indicating the second member of the Saturn rocket family.[67]

Saturn V

[edit]
Main article:Saturn V
ASaturn V rocket launches Apollo 11, 1969

Saturn V launch vehicles and flights were designated with an AS-500 series number, "AS" indicating "Apollo Saturn" and the "5" indicating Saturn V.[67] The three-stage Saturn V was designed to send a fully fueled CSM and LM to the Moon. It was 33 feet (10.1 m) in diameter and stood 363 feet (110.6 m) tall with its 96,800-pound (43,900 kg) lunar payload. Its capability grew to 103,600 pounds (47,000 kg) for the later advanced lunar landings. TheS-IC first stage burned RP-1/LOX for a rated thrust of 7,500,000 pounds-force (33,400 kN), which was upgraded to 7,610,000 pounds-force (33,900 kN). The second and third stages burned liquid hydrogen; the third stage was a modified version of the S-IVB, with thrust increased to 230,000 pounds-force (1,020 kN) and capability to restart the engine for translunar injection after reaching aparking orbit.[68]

Astronauts

[edit]
Main article:List of Apollo astronauts
Apollo 1 crew:Ed White, command pilotGus Grissom, andRoger Chaffee

NASA's director of flight crew operations during the Apollo program wasDonald K. "Deke" Slayton, one of the originalMercury Seven astronauts who was medically grounded in September 1962 due to aheart murmur. Slayton was responsible for making all Gemini and Apollo crew assignments.[69]

Thirty-two astronauts were assigned to fly missions in the Apollo program. Twenty-four of these left Earth's orbit and flew around the Moon between December 1968 and December 1972 (three of them twice). Half of the 24 walked on the Moon's surface, though none of them returned to it after landing once. One of the moonwalkers was a trained geologist. Of the 32,Gus Grissom,Ed White, andRoger Chaffee were killed during a ground test in preparation for theApollo 1 mission.[58]

Apollo 11 crew, from left: CommanderNeil Armstrong, Command Module PilotMichael Collins, and Lunar Module PilotBuzz Aldrin

The Apollo astronauts were chosen from the Project Mercury and Gemini veterans, plus from two later astronaut groups. All missions were commanded by Gemini or Mercury veterans. Crews on all development flights (except the Earth orbit CSM development flights) through the first two landings on Apollo 11 andApollo 12, included at least two (sometimes three) Gemini veterans.Harrison Schmitt, a geologist, was the firstNASA scientist astronaut to fly in space, and landed on the Moon on the last mission, Apollo 17. Schmitt participated in thelunar geology training of all of the Apollo landing crews.[70]

NASA awarded all 32 of these astronauts its highest honor, theDistinguished Service Medal, given for "distinguished service, ability, or courage", and personal "contribution representing substantial progress to the NASA mission". The medals were awarded posthumously to Grissom, White, and Chaffee in 1969, then to the crews of all missions fromApollo 8 onward. The crew that flew the first Earth orbital test missionApollo 7,Walter M. Schirra,Donn Eisele, andWalter Cunningham, were awarded the lesserNASA Exceptional Service Medal, because of discipline problems with theflight director's orders during their flight. In October 2008, the NASA Administrator decided to award them the Distinguished Service Medals. For Schirra and Eisele, this was posthumously.[71]

Lunar mission profile

[edit]

The first lunar landing mission was planned to proceed:[72]

  • Launch The three Saturn V stages burn for about 11 minutes to achieve a 100-nautical-mile (190 km) circular parking orbit. The third stage burns a small portion of its fuel to achieve orbit.
    Launch The three Saturn V stages burn for about 11 minutes to achieve a 100-nautical-mile (190 km) circularparking orbit. The third stage burns a small portion of its fuel to achieve orbit.
  • Translunar injection After one to two orbits to verify readiness of spacecraft systems, the S-IVB third stage reignites for about six minutes to send the spacecraft to the Moon.
    Translunar injection After one to two orbits to verify readiness of spacecraft systems, theS-IVB third stage reignites for about six minutes to send the spacecraft to the Moon.
  • Transposition and docking The Spacecraft Lunar Module Adapter (SLA) panels separate to free the CSM and expose the LM. The command module pilot (CMP) moves the CSM out a safe distance, and turns 180°.
    Transposition and docking TheSpacecraft Lunar Module Adapter (SLA) panels separate to free the CSM and expose the LM. The command module pilot (CMP) moves the CSM out a safe distance, and turns 180°.
  • Extraction The CMP docks the CSM with the LM, and pulls the complete spacecraft away from the S-IVB. The lunar voyage takes between two and three days. Midcourse corrections are made as necessary using the SM engine.
    Extraction The CMP docks the CSM with the LM, and pulls the complete spacecraft away from the S-IVB. The lunar voyage takes between two and three days. Midcourse corrections are made as necessary using theSM engine.
  • Lunar orbit insertion The spacecraft passes about 60 nautical miles (110 km) behind the Moon, and the SM engine is fired to slow the spacecraft and put it into a 60-by-170-nautical-mile (110 by 310 km) orbit, which is soon circularized at 60 nautical miles by a second burn.
    Lunar orbit insertion The spacecraft passes about 60 nautical miles (110 km) behind the Moon, and the SM engine is fired to slow the spacecraft and put it into a 60-by-170-nautical-mile (110 by 310 km) orbit, which is soon circularized at 60 nautical miles by a second burn.
  • After a rest period, the commander (CDR) and lunar module pilot (LMP) move to the LM, power up its systems, and deploy the landing gear. The CSM and LM separate; the CMP visually inspects the LM, then the LM crew move a safe distance away and fire the descent engine for Descent orbit insertion, which takes it to a perilune of about 50,000 feet (15 km).
    After a rest period, the commander (CDR) and lunar module pilot (LMP) move to the LM, power up its systems, and deploy the landing gear. The CSM and LM separate; the CMP visually inspects the LM, then the LM crew move a safe distance away and fire the descent engine forDescent orbit insertion, which takes it to aperilune of about 50,000 feet (15 km).
  • Powered descent At perilune, the descent engine fires again to start the descent. The CDR takes control after pitchover for a vertical landing.
    Powered descent At perilune, the descent engine fires again to start the descent. The CDR takes control after pitchover for a vertical landing.
  • The CDR and LMP perform one or more EVAs exploring the lunar surface and collecting samples, alternating with rest periods.
    The CDR and LMP perform one or moreEVAs exploring the lunar surface and collecting samples, alternating with rest periods.
  • The ascent stage lifts off, using the descent stage as a launching pad.
    Theascent stage lifts off, using the descent stage as a launching pad.
  • The LM rendezvouses and docks with the CSM.
    The LM rendezvouses and docks with the CSM.
  • The CDR and LMP transfer back to the CM with their material samples, then the LM ascent stage is jettisoned, to eventually fall out of orbit and crash on the surface.
    The CDR and LMP transfer back to the CM with their material samples, then the LM ascent stage is jettisoned, to eventually fall out of orbit and crash on the surface.
  • Trans-Earth injection The SM engine fires to send the CSM back to Earth.
    Trans-Earth injection The SM engine fires to send the CSM back to Earth.
  • The SM is jettisoned just before reentry, and the CM turns 180° to face its blunt end forward for reentry.
    The SM is jettisoned just before reentry, and the CM turns 180° to face its blunt end forward for reentry.
  • Atmospheric drag slows the CM. Aerodynamic heating surrounds it with an envelope of ionized air which causes a communications blackout for several minutes.
    Atmospheric drag slows the CM. Aerodynamic heating surrounds it with an envelope of ionized air which causes a communications blackout for several minutes.
  • Parachutes are deployed, slowing the CM for a splashdown in the Pacific Ocean. The astronauts are recovered and brought to an aircraft carrier.
    Parachutes are deployed, slowing the CM for a splashdown in thePacific Ocean. The astronauts are recovered and brought to anaircraft carrier.
Apollo Mission Flight Plan, 1967

Profile variations

[edit]
Neil Armstrong pilots the ApolloLunar ModuleEagle and lands himself and navigatorBuzz Aldrin on the Moon, July 20, 1969.
  • The first three lunar missions (Apollo 8,Apollo 10, and Apollo 11) used afree return trajectory, keeping a flight path coplanar with the lunar orbit, which would allow a return to Earth in case the SM engine failed to make lunar orbit insertion. Landing site lighting conditions on later missions dictated a lunar orbital plane change, which required a course change maneuver soon after TLI, and eliminated the free-return option.[73]
  • After Apollo 12 placed the second of severalseismometers on the Moon,[74] the jettisoned LM ascent stages on Apollo 12 and later missions were deliberately crashed on the Moon at known locations to induce vibrations in the Moon's structure. The only exceptions to this were the Apollo 13 LM which burned up in the Earth's atmosphere, andApollo 16, where a loss ofattitude control after jettison prevented making a targeted impact.[75]
  • As another active seismic experiment, the S-IVBs on Apollo 13 and subsequent missions were deliberately crashed on the Moon instead of being sent to solar orbit.[76]
  • Starting with Apollo 13, descent orbit insertion was to be performed using the service module engine instead of the LM engine, in order to allow a greater fuel reserve for landing. This was actually done for the first time on Apollo 14, since the Apollo 13 mission was aborted before landing.[77]

Development history

[edit]

Uncrewed flight tests

[edit]
Composite image of uncrewed development Apollo mission launches in chronological sequence.
Apollo uncrewed development mission launches. Click on a launch image to read the main article about each mission.
For a more comprehensive list, seeList of Apollo missions.

Two Block I CSMs were launched from LC-34 on suborbital flights in 1966 with the Saturn IB. The first,AS-201 launched on February 26, reached an altitude of 265.7 nautical miles (492.1 km) and splashed down 4,577 nautical miles (8,477 km) downrange in theAtlantic Ocean.[78] The second,AS-202 on August 25, reached 617.1 nautical miles (1,142.9 km) altitude and was recovered 13,900 nautical miles (25,700 km) downrange in the Pacific Ocean. These flights validated the service module engine and the command module heat shield.[79]

A third Saturn IB test,AS-203 launched from pad 37, went into orbit to support design of the S-IVB upper stage restart capability needed for the Saturn V. It carried a nose cone instead of the Apollo spacecraft, and its payload was the unburned liquid hydrogen fuel, the behavior of which engineers measured with temperature and pressure sensors, and a TV camera. This flight occurred on July 5, before AS-202, which was delayed because of problems getting the Apollo spacecraft ready for flight.[80]

Preparation for crewed flight

[edit]

Two crewed orbital Block I CSM missions were planned: AS-204 and AS-205. The Block I crew positions were titled Command Pilot, Senior Pilot, and Pilot. The Senior Pilot would assume navigation duties, while the Pilot would function as a systems engineer.[81] The astronauts would weara modified version of the Gemini spacesuit.[82]

After an uncrewed LM test flight AS-206, a crew would fly the first Block II CSM and LM in a dual mission known as AS-207/208, or AS-278 (each spacecraft would be launched on a separate Saturn IB).[83] The Block II crew positions were titled Commander, Command Module Pilot, and Lunar Module Pilot. The astronauts would begin wearing a newApollo A6L spacesuit, designed to accommodate lunarextravehicular activity (EVA). The traditional visor helmet was replaced with a clear "fishbowl" type for greater visibility, and the lunar surface EVA suit would include a water-cooled undergarment.[84]

Deke Slayton, the groundedMercury astronaut who became director of flight crew operations for the Gemini and Apollo programs, selected the first Apollo crew in January 1966, with Grissom as Command Pilot, White as Senior Pilot, and rookieDonn F. Eisele as Pilot. But Eisele dislocated his shoulder twice aboard theKC135 weightlessness training aircraft, and had to undergo surgery on January 27. Slayton replaced him with Chaffee.[85] NASA announced the final crew selection for AS-204 on March 21, 1966, with the backup crew consisting of Gemini veteransJames McDivitt andDavid Scott, with rookieRussell L. "Rusty" Schweickart. Mercury/Gemini veteranWally Schirra, Eisele, and rookieWalter Cunningham were announced on September 29 as the prime crew for AS-205.[85]

In December 1966, the AS-205 mission was canceled, since the validation of the CSM would be accomplished on the 14-day first flight, and AS-205 would have been devoted to space experiments and contribute no new engineering knowledge about the spacecraft. Its Saturn IB was allocated to the dual mission, now redesignated AS-205/208 or AS-258, planned for August 1967. McDivitt, Scott and Schweickart were promoted to the prime AS-258 crew, and Schirra, Eisele and Cunningham were reassigned as the Apollo 1 backup crew.[86]

Program delays

[edit]

The spacecraft for the AS-202 and AS-204 missions were delivered by North American Aviation to the Kennedy Space Center with long lists of equipment problems which had to be corrected before flight; these delays caused the launch of AS-202 to slip behind AS-203, and eliminated hopes the first crewed mission might be ready to launch as soon as November 1966, concurrently with the last Gemini mission. Eventually, the planned AS-204 flight date was pushed to February 21, 1967.[87]

North American Aviation was prime contractor not only for the Apollo CSM, but for the Saturn VS-II second stage as well, and delays in this stage pushed the first uncrewed Saturn V flight AS-501 from late 1966 to November 1967. (The initial assembly of AS-501 had to use a dummy spacer spool in place of the stage.)[88]

The problems with North American were severe enough in late 1965 to cause Manned Space Flight Administrator George Mueller to appoint program director Samuel Phillips to head a "tiger team" to investigate North American's problems and identify corrections. Phillips documented his findings in a December 19 letter to NAA presidentLee Atwood, with a strongly worded letter by Mueller, and also gave a presentation of the results to Mueller and Deputy Administrator Robert Seamans.[89] Meanwhile,Grumman was also encountering problems with the Lunar Module, eliminating hopes it would be ready for crewed flight in 1967, not long after the first crewed CSM flights.[90]

Apollo 1 fire

[edit]
Charred Apollo 1 cabin interior
Main article:Apollo 1

Grissom, White, and Chaffee decided to name their flight Apollo 1 as a motivational focus on the first crewed flight. They trained and conducted tests of their spacecraft at North American, and in the altitude chamber at the Kennedy Space Center. A "plugs-out" test was planned for January, which would simulate a launch countdown on LC-34 with the spacecraft transferring from pad-supplied to internal power. If successful, this would be followed by a more rigorous countdown simulation test closer to the February 21 launch, with both spacecraft and launch vehicle fueled.[91]

The plugs-out test began on the morning of January 27, 1967, and immediately was plagued with problems. First, the crew noticed a strange odor in their spacesuits which delayed the sealing of the hatch. Then, communications problems frustrated the astronauts and forced a hold in the simulated countdown. During this hold, an electrical fire began in the cabin and spread quickly in the high pressure, 100% oxygen atmosphere. Pressure rose high enough from the fire that the cabin inner wall burst, allowing the fire to erupt onto the pad area and frustrating attempts to rescue the crew. The astronauts were asphyxiated before the hatch could be opened.[92]

Block II spacesuit in January 1968, before (left) and after changes recommended after the Apollo 1 fire

NASA immediately convened an accident review board, overseen by both houses of Congress. While the determination of responsibility for the accident was complex, the review board concluded that "deficiencies existed in command module design, workmanship and quality control".[92] At the insistence of NASA Administrator Webb, North American removedHarrison Storms as command module program manager.[93] Webb also reassigned Apollo Spacecraft Program Office (ASPO) ManagerJoseph Francis Shea, replacing him withGeorge Low.[94]

To remedy the causes of the fire, changes were made in the Block II spacecraft and operational procedures, the most important of which were use of a nitrogen/oxygen mixture instead of pure oxygen before and during launch, and removal of flammable cabin and space suit materials.[95] The Block II design already called for replacement of the Block Iplug-type hatch cover with a quick-release, outward opening door.[95] NASA discontinued the crewed Block I program, using the Block I spacecraft only for uncrewed Saturn V flights. Crew members would also exclusively wear modified, fire-resistant A7L Block II space suits, and would be designated by the Block II titles, regardless of whether a LM was present on the flight or not.[84]

Uncrewed Saturn V and LM tests

[edit]

On April 24, 1967, Mueller published an official Apollo mission numbering scheme, using sequential numbers for all flights, crewed or uncrewed. The sequence would start withApollo 4 to cover the first three uncrewed flights while retiring the Apollo 1 designation to honor the crew, per their widows' wishes.[58][96]

In September 1967, Mueller approved asequence of mission types which had to be successfully accomplished in order to achieve the crewed lunar landing. Each step had to be successfully accomplished before the next ones could be performed, and it was unknown how many tries of each mission would be necessary; therefore letters were used instead of numbers. TheA missions were uncrewed Saturn V validation;B was uncrewed LM validation using the Saturn IB;C was crewed CSM Earth orbit validation using the Saturn IB;D was the first crewed CSM/LM flight (this replaced AS-258, using a single Saturn V launch);E would be a higher Earth orbit CSM/LM flight;F would be the first lunar mission, testing the LM in lunar orbit but without landing (a "dress rehearsal"); andG would be the first crewed landing. The list of types covered follow-on lunar exploration to includeH lunar landings,I for lunar orbital survey missions, andJ for extended-stay lunar landings.[97]

The delay in the CSM caused by the fire enabled NASA to catch up on human-rating the LM and Saturn V. Apollo 4 (AS-501) was the first uncrewed flight of the Saturn V, carrying a Block I CSM on November 9, 1967. The capability of the command module's heat shield to survive a trans-lunar reentry was demonstrated by using the service module engine to ram it into the atmosphere at higher than the usual Earth-orbital reentry speed.

Apollo 5 (AS-204) was the first uncrewed test flight of the LM in Earth orbit, launched from pad 37 on January 22, 1968, by the Saturn IB that would have been used for Apollo 1. The LM engines were successfully test-fired and restarted, despite a computer programming error which cut short the first descent stage firing. The ascent engine was fired in abort mode, known as a "fire-in-the-hole" test, where it was lit simultaneously with jettison of the descent stage. Although Grumman wanted a second uncrewed test, George Low decided the next LM flight would be crewed.[98]

This was followed on April 4, 1968, byApollo 6 (AS-502) which carried a CSM and a LM Test Article as ballast. The intent of this mission was to achieve trans-lunar injection, followed closely by a simulated direct-return abort, using the service module engine to achieve another high-speed reentry. The Saturn V experiencedpogo oscillation, a problem caused by non-steady engine combustion, which damaged fuel lines in the second and third stages. Two S-II engines shut down prematurely, but the remaining engines were able to compensate. The damage to the third stage engine was more severe, preventing it from restarting for trans-lunar injection. Mission controllers were able to use the service module engine to essentially repeat the flight profile of Apollo 4. Based on the good performance of Apollo 6 and identification of satisfactory fixes to the Apollo 6 problems, NASA declared the Saturn V ready to fly crew, canceling a third uncrewed test.[99]

Crewed development missions

[edit]
Composite image of six crewed Apollo development mission patches, from Apollo 1 to Apollo 11.
Apollo crewed development mission patches. Click on a patch to read the main article about that mission.

Apollo 7, launched from LC-34 on October 11, 1968, was the C mission, crewed bySchirra,Eisele, andCunningham. It was an 11-day Earth-orbital flight which tested the CSM systems.[100]

Apollo 8 was planned to be the D mission in December 1968, crewed by McDivitt, Scott and Schweickart, launched on a Saturn V instead of two Saturn IBs.[101] In the summer it had become clear that the LM would not be ready in time. Rather than waste the Saturn V on another simple Earth-orbiting mission, ASPO Manager George Low suggested the bold step of sending Apollo 8 to orbit the Moon instead, deferring the D mission to the next mission in March 1969, and eliminating the E mission. This would keep the program on track. The Soviet Union had sent two tortoises, mealworms, wine flies, and other lifeforms around the Moon on September 15, 1968, aboardZond 5, and it was believed they might soon repeat the feat with human cosmonauts.[102][103] The decision was not announced publicly until successful completion of Apollo 7. Gemini veteransFrank Borman andJim Lovell, and rookieWilliam Anders captured the world's attention by making ten lunar orbits in 20 hours, transmitting television pictures of the lunar surface onChristmas Eve, and returning safely to Earth.[104]

Neil Armstrong descends the LM's ladder in preparation for the first steps on the lunar surface, as televised live on July 20, 1969.

The following March, LM flight, rendezvous and docking were successfully demonstrated in Earth orbit onApollo 9, and Schweickart tested the full lunarEVA suit with itsportable life support system (PLSS) outside the LM.[105] The F mission was successfully carried out onApollo 10 in May 1969 by Gemini veteransThomas P. Stafford,John Young andEugene Cernan. Stafford and Cernan took the LM to within 50,000 feet (15 km) of the lunar surface.[106]

The G mission was achieved onApollo 11 in July 1969 by an all-Gemini veteran crew consisting ofNeil Armstrong,Michael Collins andBuzz Aldrin. Armstrong and Aldrin performed the first landing at theSea of Tranquility at 20:17:40UTC on July 20, 1969. They spent a total of 21 hours, 36 minutes on the surface, and spent 2 hours, 31 minutes outside the spacecraft,[107] walking on the surface, taking photographs, collecting material samples, and deploying automated scientific instruments, while continuously sending black-and-white television back to Earth. The astronauts returned safely on July 24.[108]

That's one small step for [a] man, one giant leap for mankind.

— Neil Armstrong, just after stepping onto the Moon's surface[109]

Production lunar landings

[edit]

In November 1969,Charles "Pete" Conrad became the third person to step onto the Moon, which he did while speaking more informally than had Armstrong:

Whoopee! Man, that may have been a small one forNeil, but that's a long one for me.

— Pete Conrad[110]
Composite image of six production crewed Apollo lunar landing mission patches, from Apollo 12 to Apollo 17.
Apollo production crewed lunar landing mission patches. Click on a patch to read the main article about that mission.

Conrad and rookieAlan L. Bean made a precision landing of Apollo 12 within walking distance of theSurveyor 3 uncrewed lunar probe, which had landed in April 1967 on theOcean of Storms. The command module pilot was Gemini veteranRichard F. Gordon Jr. Conrad and Bean carried the first lunar surface color television camera, but it was damaged when accidentally pointed into the Sun. They made two EVAs totaling 7 hours and 45 minutes.[107] On one, they walked to the Surveyor, photographed it, and removed some parts which they returned to Earth.[111]

The contracted batch of 15 Saturn Vs was enough for lunar landing missions through Apollo 20. Shortly after Apollo 11, NASA publicized a preliminary list of eight more planned landing sites after Apollo 12, with plans to increase the mass of the CSM and LM for the last five missions, along with the payload capacity of the Saturn V. These final missions would combine the I and J types in the 1967 list, allowing the CMP to operate a package of lunar orbital sensors and cameras while his companions were on the surface, and allowing them to stay on the Moon for over three days. These missions would also carry theLunar Roving Vehicle (LRV) increasing the exploration area and allowing televised liftoff of the LM. Also, the Block II spacesuit wasrevised for the extended missions to allow greater flexibility and visibility for driving the LRV.[112]

Apollo landings on the Moon, 1969–1972

The success of the first two landings allowed the remaining missions to be crewed with a single veteran as commander, with two rookies. Apollo 13 launched Lovell,Jack Swigert, andFred Haise in April 1970, headed for theFra Mauro formation. But two days out, a liquid oxygen tank exploded, disabling the service module and forcing the crew to use the LM as a "lifeboat" to return to Earth. Another NASA review board was convened to determine the cause, which turned out to be a combination of damage of the tank in the factory, and a subcontractor not making a tank component according to updated design specifications.[51] Apollo was grounded again, for the remainder of 1970 while the oxygen tank was redesigned and an extra one was added.[113]

Mission cutbacks

[edit]

About the time of the first landing in 1969, it was decided to use an existing Saturn V to launch the Skylab orbital laboratory pre-built on the ground, replacing the original plan to construct it in orbit from several Saturn IB launches; this eliminated Apollo 20. NASA's yearly budget also began to shrink in light of the successful landing, and NASA also had to make funds available for thedevelopment of the upcomingSpace Shuttle. By 1971, the decision was made to also cancel missions 18 and 19.[114] The two unused Saturn Vs became museum exhibits at theJohn F. Kennedy Space Center on Merritt Island, Florida,George C. Marshall Space Center inHuntsville, Alabama,Michoud Assembly Facility inNew Orleans, Louisiana, andLyndon B. Johnson Space Center in Houston, Texas.[115]

The cutbacks forced mission planners to reassess the original planned landing sites in order to achieve the most effective geological sample and data collection from the remaining four missions.Apollo 15 had been planned to be the last of the H series missions, but since there would be only two subsequent missions left, it was changed to the first of three J missions.[116]

Apollo 13's Fra Mauro mission was reassigned toApollo 14, commanded in February 1971 by Mercury veteranAlan Shepard, withStuart Roosa andEdgar Mitchell.[117] This time the mission was successful. Shepard and Mitchell spent 33 hours and 31 minutes on the surface,[118] and completed two EVAs totalling 9 hours 24 minutes, which was a record for the longest EVA by a lunar crew at the time.[117]

In August 1971, just after conclusion of the Apollo 15 mission, PresidentRichard Nixon proposed canceling the two remaining lunar landing missions, Apollo 16 and 17.Office of Management and Budget Deputy DirectorCaspar Weinberger was opposed to this, and persuaded Nixon to keep the remaining missions.[119]

Extended missions

[edit]
Lunar Roving Vehicle used on Apollos 15–17

Apollo 15 was launched on July 26, 1971, withDavid Scott,Alfred Worden andJames Irwin. Scott and Irwin landed on July 30 nearHadley Rille, and spent just under two days, 19 hours on the surface. In over 18 hours of EVA, they collected about 77 kilograms (170 lb) of lunar material.[120]

Apollo 16 landed in theDescartes Highlands on April 20, 1972. The crew was commanded by John Young, withKen Mattingly andCharles Duke. Young and Duke spent just under three days on the surface, with a total of over 20 hours EVA.[121]

Apollo 17 was the last of the Apollo program, landing in theTaurus–Littrow region in December 1972. Eugene Cernan commandedRonald E. Evans and NASA's first scientist-astronaut, geologistHarrison H. Schmitt.[122] Schmitt was originally scheduled for Apollo 18,[123] but the lunar geological community lobbied for his inclusion on the final lunar landing.[124] Cernan and Schmitt stayed on the surface for just over three days and spent just over 23 hours of total EVA.[122]

Canceled missions

[edit]
Main article:Canceled Apollo missions

Several missions were planned for but were canceled before details were finalized.

Mission summary

[edit]
For a more comprehensive list, seeList of Apollo missions.
DesignationDateLVCSMLMCrewSummary
AS-201Feb 26, 1966AS-201CSM-009First flight of Saturn IB and Block I CSM; suborbital to Atlantic Ocean; qualified heat shield to orbital reentry speed.
AS-203Jul 5, 1966AS-203No spacecraft; observations of liquid hydrogen fuel behavior in orbit to support design of S-IVB restart capability.
AS-202Aug 25, 1966AS-202CSM-011Suborbital flight of CSM to Pacific Ocean.
Apollo 1Feb 21, 1967SA-204CSM-012Gus Grissom
Ed White
Roger B. Chaffee
Not flown. All crew members died in a fire during a launch pad test on January 27, 1967.
Apollo 4Nov 9, 1967SA-501CSM-017LTA-10RFirst test flight of Saturn V, placed a CSM in a high Earth orbit; demonstrated S-IVB restart; qualified CM heat shield to lunar reentry speed.
Apollo 5Jan 22–23, 1968SA-204LM-1Earth orbital flight test of LM, launched on Saturn IB; demonstrated ascent and descent propulsion; human-rated the LM. No crew.
Apollo 6Apr 4, 1968SA-502CM-020
SM-014
LTA-2RUncrewed, second flight of Saturn V, attempted demonstration of trans-lunar injection, and direct-return abort using SM engine; three engine failures, including failure of S-IVB restart. Flight controllers used SM engine to repeat Apollo 4's flight profile. Human-rated the Saturn V.
Apollo 7Oct 11–22, 1968SA-205CSM-101Wally Schirra
Walt Cunningham
Donn Eisele
First crewed Earth orbital demonstration of Block II CSM, launched on Saturn IB. First live television broadcast from a crewed mission.
Apollo 8Dec 21–27, 1968SA-503CSM-103LTA-BFrank Borman
James Lovell
William Anders
First crewed flight of Saturn V; First crewed flight to Moon; CSM made 10 lunar orbits in 20 hours.
Apollo 9Mar 3–13, 1969SA-504CSM-104
Gumdrop
LM-3
Spider
James McDivitt
David Scott
Russell Schweickart
Second crewed flight of Saturn V; First crewed flight of CSM and LM in Earth orbit; demonstrated portable life support system to be used on the lunar surface.
Apollo 10May 18–26, 1969SA-505CSM-106
Charlie Brown
LM-4
Snoopy
Thomas Stafford
John Young
Eugene Cernan
Dress rehearsal for first lunar landing; flew LM down to 50,000 ft (15 km; 9.5 mi) from lunar surface.
Apollo 11Jul 16–24, 1969SA-506CSM-107
Columbia
LM-5EagleNeil Armstrong
Michael Collins
Buzz Aldrin
First landing, inTranquility Base,Sea of Tranquility. Surface EVA time: 2h 31m. Samples returned: 47.51 lb (21.55 kg).
Apollo 12Nov 14–24, 1969SA-507CSM-108
Yankee Clipper
LM-6
Intrepid
Pete Conrad
Richard Gordon
Alan Bean
Second landing, inOcean of Storms nearSurveyor 3. Surface EVA time: 7h 45m. Samples returned: 75.62 lb (34.30 kg).
Apollo 13Apr 11–17, 1970SA-508CSM-109
Odyssey
LM-7
Aquarius
James Lovell
Jack Swigert
Fred Haise
Third landing attempt aborted in transit to the Moon, due to SM failure. Crew used LM as "lifeboat" to return to Earth. Mission called a "successful failure".[125]
Apollo 14Jan 31 – Feb 9, 1971SA-509CSM-110
Kitty Hawk
LM-8
Antares
Alan Shepard
Stuart Roosa
Edgar Mitchell
Third landing, inFra Mauro formation. Surface EVA time: 9h 21m. Samples returned: 94.35 lb (42.80 kg).
Apollo 15Jul 26 – Aug 7, 1971SA-510CSM-112
Endeavour
LM-10
Falcon
David Scott
Alfred Worden
James Irwin
Fourth landing, inHadley-Apennine. First extended mission, usedRover on Moon. Surface EVA time: 18h 33m. Samples returned: 169.10 lb (76.70 kg).
Apollo 16Apr 16–27, 1972SA-511CSM-113
Casper
LM-11
Orion
John Young
Ken Mattingly
Charles Duke
Fifth landing, inPlain of Descartes. Second extended mission, used Rover on Moon. Surface EVA time: 20h 14m. Samples returned: 207.89 lb (94.30 kg).
Apollo 17Dec 7–19, 1972SA-512CSM-114
America
LM-12
Challenger
Eugene Cernan
Ronald Evans
Harrison Schmitt
Only Saturn V night launch. Sixth landing, inTaurus–Littrow. Third extended mission, used Rover on Moon. First geologist on the Moon. Apollo's last crewed Moon landing. Surface EVA time: 22h 2m. Samples returned: 243.40 lb (110.40 kg).

Source:Apollo by the Numbers: A Statistical Reference (Orloff 2004).[126]

Samples returned

[edit]
Main article:Moon rock
The most famous of the Moon rocks recovered, theGenesis Rock, returned from Apollo 15.
Apollo 16's sample 61016, better known as Big Muley, is the largest sample collected during the Apollo program

The Apollo program returned over 382 kg (842 lb) of lunar rocks andsoil to theLunar Receiving Laboratory in Houston.[127][126][128] Today, 75% of the samples are stored at theLunar Sample Laboratory Facility built in 1979.[129]

The rocks collected from the Moon are extremely old compared to rocks found on Earth, as measured byradiometric dating techniques. They range in age from about 3.2 billion years for thebasaltic samples derived from thelunar maria, to about 4.6 billion years for samples derived from thehighlands crust.[130] As such, they represent samples from a very early period in the development of theSolar System, that are largely absent on Earth. One important rock found during the Apollo Program is dubbed theGenesis Rock, retrieved by astronauts David Scott and James Irwin during the Apollo 15 mission.[131] Thisanorthosite rock is composed almost exclusively of the calcium-rich feldspar mineralanorthite, and is believed to be representative of the highland crust.[132] A geochemical component calledKREEP was discovered by Apollo 12, which has no known terrestrial counterpart.[133] KREEP and the anorthositic samples have been used to infer that the outer portion of the Moon was once completely molten (seelunar magma ocean).[134]

Almost all the rocks show evidence of impact process effects. Many samples appear to be pitted withmicrometeoroid impact craters, which is never seen on Earth rocks, due to the thick atmosphere. Many show signs of being subjected to high-pressure shock waves that are generated during impact events. Some of the returned samples are ofimpact melt (materials melted near an impact crater.) All samples returned from the Moon are highlybrecciated as a result of being subjected to multiple impact events.[135]

From analyses of the composition of the returned lunar samples, it is now believed that the Moon wascreated through the impact of a large astronomical body with Earth.[136]

Costs

[edit]

Apollo cost $25.4 billion or approximately $257 billion (2023) using improved cost analysis.[137]

Of this amount, $20.2 billion ($145 billion adjusted) was spent on the design, development, and production of theSaturn family of launch vehicles, theApollo spacecraft,spacesuits,scientific experiments, and mission operations. The cost of constructing and operating Apollo-related ground facilities, such as the NASA human spaceflight centers and theglobal tracking and data acquisition network, added an additional $5.2 billion ($37.3 billion adjusted).

The amount grows to $28 billion ($280 billion adjusted) if the costs for related projects such as Project Gemini and the roboticRanger,Surveyor, andLunar Orbiter programs are included.[1]

NASA's official cost breakdown, as reported to Congress in the Spring of 1973, is as follows:

Project ApolloCost (original, billion $)
Apollo spacecraft8.5
Saturn launch vehicles9.1
Launch vehicle engine development0.9
Operations1.7
Total R&D20.2
Tracking and data acquisition0.9
Ground facilities1.8
Operation of installations2.5
Total25.4

Accurate estimates of human spaceflight costs were difficult in the early 1960s, as the capability was new and management experience was lacking. Preliminary cost analysis by NASA estimated $7 billion – $12 billion for a crewed lunar landing effort. NASA Administrator James Webb increased this estimate to $20 billion before reporting it to Vice President Johnson in April 1961.[138]

Project Apollo was a massive undertaking, representing the largest research and development project in peacetime. At its peak, it employed over 400,000 employees and contractors around the country and accounted for more than half of NASA's total spending in the 1960s.[139] After the first Moon landing, public and political interest waned, including that of President Nixon, who wanted to rein in federal spending.[140] NASA's budget could not sustain Apollo missions which cost, on average, $445 million ($2.66 billion adjusted)[141] each while simultaneouslydeveloping the Space Shuttle. The final fiscal year of Apollo funding was 1973.

Apollo Applications Program

[edit]
Main article:Apollo Applications Program

Looking beyond the crewed lunar landings, NASA investigated several post-lunar applications for Apollo hardware. The Apollo Extension Series (Apollo X) proposed up to 30 flights to Earth orbit, using the space in theSpacecraft Lunar Module Adapter (SLA) to house a small orbital laboratory (workshop). Astronauts would continue to use the CSM as a ferry to the station. This study was followed by design of a larger orbital workshop to be built in orbit from an empty S-IVB Saturn upper stage and grew into the Apollo Applications Program (AAP). The workshop was to be supplemented by theApollo Telescope Mount, which could be attached to the ascent stage of the lunar module via a rack.[142] The most ambitious plan called for using an empty S-IVB as an interplanetary spacecraft for aVenus fly-by mission.[143]

The S-IVB orbital workshop was the only one of these plans to make it off the drawing board. DubbedSkylab, it was assembled on the ground rather than in space, and launched in 1973 using the two lower stages of a Saturn V. It was equipped with an Apollo Telescope Mount. Skylab's last crew departed the station on February 8, 1974, and the station itself re-entered the atmosphere in 1979 after development of theSpace Shuttle was delayed too long to save it.[144][145]

TheApollo–Soyuz program also used Apollo hardware for the first joint nation spaceflight, paving the way for future cooperation with other nations in theSpace Shuttle andInternational Space Station programs.[145][146]

Recent observations

[edit]
Tranquility Base, imaged in March 2012 by the Lunar Reconnaissance Orbiter

In 2008,Japan Aerospace Exploration Agency'sSELENE probe observed evidence of the halo surrounding the Apollo 15 Lunar Module blast crater while orbiting above the lunar surface.[147]

Beginning in 2009, NASA'sroboticLunar Reconnaissance Orbiter, while orbiting 50 kilometers (31 mi) above the Moon, photographed the remnants of the Apollo program left on the lunar surface, and each site where crewed Apollo flights landed.[148][149] All of the U.S. flags left on the Moon during the Apollo missions were found to still be standing, with the exception of the one left during the Apollo 11 mission, which was blown over during that mission's lift-off from the lunar surface; the degree to which these flags retain their original colors remains unknown.[150] The flags cannot be seen through a telescope from Earth.

In a November 16, 2009, editorial,The New York Times opined:

[T]here's something terribly wistful about these photographs of the Apollo landing sites. The detail is such that if Neil Armstrong were walking there now, we could make him out, make out his footsteps even, like the astronaut footpath clearly visible in the photos of the Apollo 14 site. Perhaps the wistfulness is caused by the sense of simple grandeur in those Apollo missions. Perhaps, too, it's a reminder of the risk we all felt after the Eagle had landed—the possibility that it might be unable to lift off again and the astronauts would be stranded on the Moon. But it may also be that a photograph like this one is as close as we're able to come to looking directly back into the human past ...There the [Apollo 11] lunar module sits, parked just where it landed 40 years ago, as if it still really were 40 years ago and all the time since merely imaginary.[151]

Legacy

[edit]

Science and engineering

[edit]
Further information:NASA spin-off technologies
Margaret Hamilton standing next to the navigation software that she and her MIT team produced for the Apollo project

The Apollo program has been described as the greatest technological achievement in human history.[152] Apollo stimulated many areas of technology, leading to over 1,800 spinoff products as of 2015, including advances in the development ofcordless power tools,fireproof materials,heart monitors,solar panels,digital imaging, and the use ofliquid methane as fuel.[153][154][155] Theflight computer design used in both the lunar and command modules was, along with thePolaris andMinuteman missile systems, the driving force behind early research intointegrated circuits (ICs). By 1963, Apollo was using 60 percent of the United States' production of ICs. The crucial difference between the requirements of Apollo and the missile programs was Apollo's much greater need for reliability. While the Navy and Air Force could work around reliability problems by deploying more missiles, the political and financial cost of failure of an Apollo mission was unacceptably high.[156]

Technologies and techniques required for Apollo were developed by Project Gemini.[157] The Apollo project was enabled by NASA's adoption of new advances insemiconductorelectronic technology, includingmetal–oxide–semiconductor field-effect transistors (MOSFETs) in theInterplanetary Monitoring Platform (IMP)[158][159] andsiliconintegrated circuit chips in theApollo Guidance Computer (AGC).[160]

Cultural impact

[edit]
The Blue Marble photograph taken on December 7, 1972, during Apollo 17. "We went to explore the Moon, and in fact discovered the Earth." —Eugene Cernan

The crew of Apollo 8 sent the first live televised pictures of the Earth and the Moon back to Earth, and read from the creation story in theBook of Genesis, on Christmas Eve 1968.[161] An estimated one-quarter of the population of the world saw—either live or delayed—the Christmas Eve transmission during the ninth orbit of the Moon,[162] and an estimated one-fifth of the population of the world watched the live transmission of the Apollo 11 moonwalk.[163]

The Apollo program also affectedenvironmental activism in the 1970s due to photos taken by the astronauts. The most well known includeEarthrise, taken byWilliam Anders on Apollo 8, andThe Blue Marble, taken by the Apollo 17 astronauts.The Blue Marble was released during a surge in environmentalism, and became a symbol of the environmental movement as a depiction of Earth's frailty, vulnerability, and isolation amid the vast expanse of space.[164]

According toThe Economist, Apollo succeeded in accomplishing President Kennedy's goal of taking on the Soviet Union in theSpace Race by accomplishing a singular and significant achievement, to demonstrate the superiority of thefree-market system. The publication noted the irony that in order to achieve the goal, the program required the organization of tremendous public resources within a vast, centralized government bureaucracy.[165]

Apollo 11 broadcast data restoration project

[edit]
Main article:Apollo 11 missing tapes

Prior to Apollo 11's 40th anniversary in 2009, NASA searched for the original videotapes of the mission's live televised moonwalk. After an exhaustive three-year search, it was concluded that the tapes had probably been erased and reused. A new digitally remastered version of the best available broadcast television footage was released instead.[166]

Depictions on film

[edit]

Documentaries

[edit]

Numerous documentary films cover the Apollo program and the Space Race, including:

Docudramas

[edit]

Some missions have beendramatized:

Fictional

[edit]

The Apollo program has been the focus of several works of fiction, including:

  • Apollo 18 (2011),horror movie which was released to negative reviews.
  • Men in Black 3 (2012), Science Fiction/Comedy movie.Agent J played byWill Smith goes back to the Apollo 11 launch in 1969 to ensure that a global protection system is launched in to space.
  • For All Mankind (2019), TV series depicting analternate history in which the Soviet Union was the first country to successfully land a man on the Moon.
  • Indiana Jones and the Dial of Destiny (2023), fifthIndiana Jones film, in which Jürgen Voller, a NASA member and ex-Nazi involved with the Apollo program, wants to time travel. The New York City parade for the Apollo 11 crew is portrayed as a plot point.[173]

See also

[edit]

Notes

[edit]
  1. ^Full text Wikisource has information on "Special Message to the Congress on Urgent National Needs"
  2. ^Full text Wikisource has information on "We choose to go to the moon"

References

[edit]

Citations

[edit]
  1. ^ab"How much did the Apollo program cost?".The Planetary Society. RetrievedMarch 25, 2024.
  2. ^"July 20, 1969: One Giant Leap for Mankind - NASA". July 20, 2019.
  3. ^Murray & Cox 1989, p. 55
  4. ^"Release 69-36" (Press release). Cleveland, OH:Lewis Research Center. July 14, 1969. RetrievedJune 21, 2012.
  5. ^"Project Olympus (1962)".WIRED. September 2, 2013. RetrievedOctober 12, 2023.
  6. ^Brooks, Grimwood & Swenson 1979, Ch. 1.7:"Feasility Studies". pp. 16–21.
  7. ^Preble, Christopher A. (2003). ""Who Ever Believed in the 'Missile Gap'?": John F. Kennedy and the Politics of National Security".Presidential Studies Quarterly.33 (4): 813.doi:10.1046/j.0360-4918.2003.00085.x.JSTOR 27552538.
  8. ^Beschloss 1997
  9. ^Sidey 1963, pp. 117–118
  10. ^Beschloss 1997, p. 55
  11. ^87th Congress 1961
  12. ^Sidey 1963, p. 114
  13. ^Kennedy, John F. (April 20, 1961)."Memorandum for Vice President".The White House (Memorandum). Boston, MA:John F. Kennedy Presidential Library and Museum. Archived fromthe original on July 21, 2016. RetrievedAugust 1, 2013.
  14. ^Launius, Roger D. (July 1994)."President John F. Kennedy Memo for Vice President, 20 April 1961"(PDF).Apollo: A Retrospective Analysis(PDF). Monographs in Aerospace History. Washington, D.C.: NASA.OCLC 31825096.Archived(PDF) from the original on October 9, 2022. RetrievedAugust 1, 2013.Key Apollo Source DocumentsArchived November 8, 2020, at theWayback Machine.
  15. ^abJohnson, Lyndon B. (April 28, 1961)."Memorandum for the President".Office of the Vice President (Memorandum). Boston, MA: John F. Kennedy Presidential Library and Museum. Archived fromthe original on July 1, 2016. RetrievedAugust 1, 2013.
  16. ^Launius, Roger D. (July 1994)."Lyndon B. Johnson, Vice President, Memo for the President, 'Evaluation of Space Program,' 28 April 1961"(PDF).Apollo: A Retrospective Analysis(PDF). Monographs in Aerospace History. Washington, D.C.: NASA.OCLC 31825096.Archived(PDF) from the original on October 9, 2022. RetrievedAugust 1, 2013.Key Apollo Source DocumentsArchived November 8, 2020, at theWayback Machine.
  17. ^Kennedy, John F. (May 25, 1961).Special Message to Congress on Urgent National Needs (Motion picture (excerpt)). Boston, MA: John F. Kennedy Presidential Library and Museum. Accession number: TNC:200; digital identifier: TNC-200-2. RetrievedAugust 1, 2013.
  18. ^Murray & Cox 1989, pp. 16–17
  19. ^Sietzen, Frank (October 2, 1997)."Soviets Planned to Accept JFK's Joint Lunar Mission Offer".SpaceDaily. SpaceCast News Service. RetrievedAugust 1, 2013.
  20. ^"Soyuz – Development of the Space Station; Apollo – Voyage to the Moon". RetrievedJune 12, 2016.
  21. ^Brooks, Grimwood & Swenson 1979, Ch. 2.5:"Contracting for the Command Module". pp. 41–44.
  22. ^Johnston, Louis; Williamson, Samuel H. (2023)."What Was the U.S. GDP Then?".MeasuringWorth. RetrievedNovember 30, 2023. United StatesGross Domestic Product deflator figures follow theMeasuringWorth series.
  23. ^Allen, Bob (ed.)."NASA Langley Research Center's Contributions to the Apollo Program".Langley Research Center. NASA. RetrievedAugust 1, 2013.
  24. ^"Historical Facts".MSFC History Office. Archived fromthe original on June 3, 2016. RetrievedJune 7, 2016.
  25. ^Swenson, Loyd S. Jr.; Grimwood, James M.; Alexander, Charles C. (1989) [Originally published 1966]."Chapter 12.3: Space Task Group Gets a New Home and Name".This New Ocean: A History of Project Mercury. The NASA History Series. Washington, D.C.: NASA.OCLC 569889. NASA SP-4201. Archived fromthe original on July 13, 2009. RetrievedAugust 1, 2013.
  26. ^Dethloff, Henry C. (1993). "Chapter 3: Houston – Texas – U.S.A.".Suddenly Tomorrow Came ... A History of the Johnson Space Center. National Aeronautics and Space Administration.ISBN 978-1502753588.
  27. ^Kennedy, John F. (September 12, 1962)."Address at Rice University on the Nation's Space Effort". Boston, MA: John F. Kennedy Presidential Library and Museum. Archived fromthe original on May 6, 2010. RetrievedAugust 1, 2013.
  28. ^Nixon, Richard M. (February 19, 1973)."50—Statement About Signing a Bill Designating the Manned Spacecraft Center in Houston, Texas, as the Lyndon B. Johnson Space Center".The American Presidency Project.University of California, Santa Barbara. RetrievedJuly 9, 2011.
  29. ^"Dr. Kurt H. Debus".Kennedy Biographies. NASA. February 1987. RetrievedOctober 7, 2008.
  30. ^"Executive Orders Disposition Tables: Lyndon B. Johnson – 1963: Executive Order 11129".Office of the Federal Register.National Archives and Records Administration. RetrievedApril 26, 2010.
  31. ^The building was renamed "Vehicle Assembly Building" on February 3, 1965."VAB Nears Completion".NASA History Program Office. NASA. Archived fromthe original on April 28, 2015. RetrievedFebruary 12, 2023.The new name, it was felt, would more readily encompass future as well as current programs and would not be tied to the Saturn booster.
  32. ^Craig, Kay (ed.)."KSC Technical Capabilities: O&C Altitude Chambers".Center Planning and Development Office. NASA. Archived fromthe original on March 28, 2012. RetrievedJuly 29, 2011.
  33. ^"1976 Standard Atmosphere Properties".luizmonteiro.com (CompleteInternational Standard Atmosphere calculator (1976 model)). Luizmonteiro, LLC. RetrievedAugust 1, 2013.
  34. ^Johnson 2002
  35. ^"Stages to Saturn".history.nasa.gov. p. 443. SP-4206. RetrievedFebruary 12, 2023.
  36. ^Narvaez, Alfonso A. (February 1, 1990)."Samuel C. Phillips, Who Directed Apollo Lunar Landing, Dies at 68".The New York Times. RetrievedApril 14, 2010.
  37. ^Davies, Dave (June 12, 2019)."'One Giant Leap' Explores The Herculean Effort Behind The 1969 Moon Landing".NPR. US. RetrievedJuly 5, 2023.
  38. ^Using the Apollo 11 lunar lander's mass ratio of 22,667-pound (10,282 kg) descent stage to 10,042-pound (4,555 kg) ascent stage, scaled up to Nova's 163,000-pound (74,000 kg) payload.
  39. ^Brooks, Grimwood & Swenson 1979,Ch. 2.6, "Influences on Booster Determination".
  40. ^Brooks, Grimwood & Swenson 1979, Chapter 3.2:Early Reaction to LOR. pp. 61–67.
  41. ^Orloff, Richard W. (September 2004).Apollo by the Numbers: A Statistical Reference. Launch Vehicle/Spacecraft Key Facts – 2nd table. Washington DC: NASA History Division.ISBN 016-050631-X. RetrievedAugust 8, 2018.
  42. ^Brooks, Grimwood & Swenson 1979, Ch. 3.4:"Early Reaction to LOR". p. 71.
  43. ^Hansen 1999, p. 32
  44. ^Hansen 1999, pp. 35–39
  45. ^Brooks, Grimwood & Swenson 1979, Ch. 3.6:"Settling the Mode Issue". pp. 81–83.
  46. ^"2: The Lunar Landing Decision and Its Aftermath".Managing NASA in the Apollo Era.history.nasa.gov (Report). RetrievedFebruary 12, 2023.
  47. ^Brooks, Grimwood & Swenson 1979,Ch. 3.7, "Casting the Die".
  48. ^Brooks, Grimwood & Swenson 1979,Ch. 4.4, "Pressures by PSAC".
  49. ^Hansen 1999, p. 42
  50. ^Letterman, John B. (2003). "Explosion on Apollo 13; April 1970: From the Earth to the Moon and Back".Survivors: True Tales of Endurance: 500 Years of the Greatest Eyewitness Accounts. New York: Simon & Schuster. p. 404.ISBN 0-7432-4547-4.Lovell writes, 'Naturally, I'm glad that view didn't prevail, and I'm thankful that by the time of Apollo 10, the first lunar mission carrying the LM, the LM as a lifeboat was again being discussed.'
  51. ^abDumoulin, Jim (June 29, 2001)."Apollo-13 (29)".Historical Archive for Manned Missions. NASA. Archived fromthe original on August 19, 2011. RetrievedSeptember 12, 2012.
  52. ^ab"Apollo Program Summary Report"(PDF). Houston, TX: NASA. April 1975. pp. 3–66 to 4–12. JSC-09423.Archived(PDF) from the original on October 9, 2022. RetrievedAugust 1, 2013.
  53. ^abc"Launch Vehicle".history.nasa.gov. RetrievedFebruary 12, 2023.
  54. ^Wilford 1969, p. 167
  55. ^Leary, Warren E. (March 27, 2002)."T. J. Kelly, 72, Dies; Father of Lunar Module".The New York Times. RetrievedAugust 1, 2013.
  56. ^"Aerospace Alphabet: ABMA, ARPA, MSFC".history.nasa.gov. RetrievedFebruary 12, 2023.
  57. ^"Missions, Modes, and Manufacturing".history.nasa.gov. RetrievedFebruary 12, 2023.
  58. ^abc"Apollo 11 30th Anniversary: Manned Apollo Missions". NASA History Office. 1999.Archived from the original on February 20, 2011. RetrievedMarch 3, 2011.
  59. ^Townsend 1973, p. 14
  60. ^Townsend 1973, p. 22
  61. ^Dawson & Bowles 2004, p. 85. See footnote 61.
  62. ^Brooks, Grimwood & Swenson 1979, Ch. 7.6:"Portents for Operations".
  63. ^Apollo Systems Description(PDF) (Technical Memorandum). Vol. II: Saturn Launch Vehicles. NASA. February 1, 1964. p. 3. NASA TM-X-881.Archived(PDF) from the original on October 9, 2022. RetrievedAugust 1, 2013.
  64. ^Wade, Mark."Apollo SA-11".Encyclopedia Astronautica. Archived fromthe original on June 17, 2012. RetrievedJune 21, 2012.
  65. ^"Influences on Booster Determination"(PDF).NASA HQ. pp. 44–46. RetrievedNovember 11, 2022.
  66. ^"Saturn IB Design Features".Saturn IB News Reference(PDF). NASA;Chrysler Corporation;McDonnell Douglas Astronautics Company;International Business Machines Corporation;Rocketdyne. December 1965.OCLC 22102803. RetrievedAugust 1, 2013.
  67. ^ab"Origin of NASA's Names: Manned Spaceflight". RetrievedJuly 19, 2016.
  68. ^"Launch Vehicle".history.nasa.gov. RetrievedFebruary 12, 2023.
  69. ^"Astronaut Bio: Deke Slayton 6/93". NASA. June 1993. Archived fromthe original on September 29, 2006. RetrievedAugust 1, 2013.
  70. ^"Astronaut Bio: Harrison Schmitt". NASA. December 1994. Archived fromthe original on March 17, 2011. RetrievedSeptember 12, 2012.
  71. ^Pearlman, Robert Z. (October 20, 2008)."First Apollo flight crew last to be honored".collectSPACE. Robert Pearlman. RetrievedJune 12, 2014.
  72. ^Gatland, Kenneth (1976).Manned Spacecraft. New York: MacMillan. pp. 75–85,88–89.
  73. ^McDivitt, James A. (March 1970).Apollo 12 Mission Report(PDF). Houston, Texas: NASA Manned Spacecraft Center. p. 5–4.
  74. ^"Apollo 12 Lunar Module / ALSEP".NASA Space Science Data Coordinate Archive. RetrievedJune 15, 2016.
  75. ^Williams, David R."Apollo: Where are they now?".National Space Science Data Center. NASA. RetrievedDecember 2, 2011.
  76. ^"Apollo 13's Booster Impact".NASA. RetrievedJune 16, 2016.
  77. ^McDivitt, James A. (April 1971)."7.0 Command and Service Module Performance".Apollo 14 Mission Report. Houston, Texas: NASA Manned Spacecraft Center. RetrievedMay 19, 2016.
  78. ^Postlaunch Report for Mission AS-201 (Apollo Spacecraft 009)(PDF). Houston, TX: NASA. May 6, 1966. MSC-A-R-66-4. RetrievedAugust 1, 2013.
  79. ^Postlaunch Report for Mission AS-202 (Apollo Spacecraft 011)(PDF). Houston, TX: NASA. October 12, 1966. MSC-A-R-66-5. RetrievedAugust 1, 2013.
  80. ^Chrysler Corp. (January 13, 1967).Evaluation of AS-203 Low Gravity Orbital Experiment (Technical report). NASA.
  81. ^"Apollo flight crew nomenclature changes".Astronautix. Archived fromthe original on February 1, 2010. RetrievedJuly 8, 2016.
  82. ^"A1C".Astronautix. Archived fromthe original on August 20, 2016. RetrievedJuly 8, 2016.
  83. ^Brooks, Grimwood & Swenson 1979, Plans and Progress in Space Flight.
  84. ^abLutz, Charles C.; Carson, Maurice A. (November 1975)."Apollo Experience Report – Development of the Extravehicular Mobility Unit"(PDF).NASA Technical Note. TN D-8093:22–25.Archived(PDF) from the original on October 9, 2022. RetrievedMay 18, 2016.
  85. ^abTeitel, Amy Shira (December 4, 2013) [2013]."How Donn Eisele Became "Whatshisname," the Command Module Pilot of Apollo 7".Popular Science.
  86. ^Brooks, Grimwood & Swenson 1979, Ch. 8.7:"Preparations for the First Manned Apollo Mission".
  87. ^"Apollo 1: The Fire".history.nasa.gov. January 27, 1967. RetrievedFebruary 12, 2023.
  88. ^Benson, Charles D.; Faherty, William Barnaby (1978)."Delay after Delay after Delay".Moonport: A History of Apollo Launch Facilities and Operations. The NASA History Series. Washington, D.C.: Scientific and Technical Information Office, NASA.LCCN 77029118.OCLC 3608505. NASA SP-4204.Archived from the original on January 23, 2008. RetrievedAugust 1, 2013.
  89. ^NASA never volunteered the tiger team findings to the US Congress in the course of its regular oversight, but its existence was publicly disclosed as "the Phillips report" in the course of the Senate investigation into the Apollo 204 fire."The Phillips Report". NASA History Office. October 22, 2004.Archived from the original on April 15, 2010. RetrievedApril 14, 2010.
  90. ^Brooks, Grimwood & Swenson 1979, Ch. 7.4:"The LEM Test Program: A Pacing Item".
  91. ^Seamans, Robert C. Jr. (April 5, 1967). "Description of Test Sequence and Objectives".Report of Apollo 204 Review Board. NASA History Office. RetrievedOctober 7, 2007.
  92. ^abSeamans, Robert C. Jr. (April 5, 1967). "Findings, Determinations And Recommendations".Report of Apollo 204 Review Board. NASA History Office. Archived fromthe original on November 5, 2015. RetrievedOctober 7, 2007.
  93. ^Gray 1994
  94. ^Ertel et al. 1978, p. 119
  95. ^abBrooks, Grimwood & Swenson 1979,"The Slow Recovery"
  96. ^Ertel & al. 1978, Part 1(H)
  97. ^Ertel et al. 1978, p. 157
  98. ^Low, George M. (1975)."Testing and Retesting To Get Ready For flight". InCortright, Edgar M (ed.).Apollo Expeditions to the Moon. Washington, D.C.: Scientific and Technical Information Office, NASA.LCCN 75600071.OCLC 1623434. NASA SP-350. Archived fromthe original on February 19, 2008. RetrievedAugust 1, 2013.
  99. ^Brooks, Grimwood & Swenson 1979, Ch. 10.5:"Apollo 6: Saturn V's Shaky Dress Rehearsal".
  100. ^"Mission Objective". July 8, 2015. RetrievedJuly 8, 2016.
  101. ^"Mission Objective". July 8, 2009. RetrievedJuly 8, 2016.
  102. ^Chaikin, Andrew (1994).A Man on the Moon: The Voyages of the Apollo Astronauts. New York: Viking.ISBN 978-0-670-81446-6.LCCN 93048680.
  103. ^"Poised for the Leap".Time. New York. December 6, 1968. Archived fromthe original on February 4, 2013. RetrievedDecember 15, 2011.
  104. ^Brooks, Grimwood & Swenson 1979, Ch. 11.6:"Apollo 8: The First Lunar Voyage". pp. 274–284.
  105. ^"Apollo 9".NASA Space Science Data Coordinated Archive. RetrievedJuly 8, 2016.
  106. ^"Apollo 10".NASA JSC. RetrievedJuly 8, 2016.
  107. ^ab"Extravehicular Activity". RetrievedJune 11, 2016.
  108. ^"Apollo 11 Mission Overview".NASA. April 17, 2015. RetrievedJuly 8, 2016.
  109. ^Mikkelson, Barbara; Mikkelson, David P. (October 2006)."One Small Misstep: Neil Armstrong's First Words on the Moon".Snopes.com.Urban Legends Reference Pages. RetrievedSeptember 19, 2009.
  110. ^Jones, Eric."That may have been a small one for Neil..."Apollo 12 Lunar Surface Journal. NASA. RetrievedFebruary 5, 2018.
  111. ^Conrad, Charles Jr.;Shepard, Alan B Jr. (1975)."Tan Dust On Surveyor". InCortright, Edgar M (ed.).Apollo Expeditions to the Moon. Washington, D.C.: Scientific and Technical Information Office, NASA.LCCN 75600071.OCLC 1623434. NASA SP-350. Archived fromthe original on February 19, 2008. RetrievedAugust 1, 2013.
  112. ^"Where No Man Has Gone Before, Ch12-4".www.hq.nasa.gov. Archived fromthe original on February 12, 2023. RetrievedFebruary 12, 2023.
  113. ^"Where No Man Has Gone Before, Ch11-7".www.hq.nasa.gov. Archived fromthe original on February 12, 2023. RetrievedFebruary 12, 2023.
  114. ^"Where No Man Has Gone Before, Ch12-2".www.hq.nasa.gov. Archived fromthe original on February 12, 2023. RetrievedFebruary 12, 2023.
  115. ^Wright, Mike."Three Saturn Vs on Display Teach Lessons in Space History". Marshall Space Flight Center History Office. Archived fromthe original on November 15, 2005. RetrievedJuly 19, 2016.
  116. ^Williams, David (December 11, 2003)."Apollo 18 through 20 – The Cancelled Missions".NASA Space Science Data Coordinated Archive. RetrievedJune 11, 2016.
  117. ^ab"Apollo 14".NASA. July 8, 2009. RetrievedJune 11, 2016.
  118. ^"Apollo 14 Command and Service Module (CSM)".NASA Space Science Data Coordinated Archive. RetrievedJune 11, 2016.
  119. ^"MEMORANDUM FOR THE PRESIDENT" by Caspar Weinberger (via George Shultz), Aug 12, 1971, Page32(of 39)[1]
  120. ^"Apollo 15".NASA. July 8, 2009. RetrievedJune 9, 2016.
  121. ^"Apollo 16".NASA. July 8, 2009. RetrievedJune 9, 2016.
  122. ^ab"Apollo 17".NASA. July 30, 2015. RetrievedJune 9, 2016.
  123. ^Grinter, Kay (September 28, 2011)."Apollo 18' Myths Debunked, NASA-style".NASA. RetrievedJune 10, 2016.
  124. ^Howell, Elizabeth (April 23, 2013)."Harrison Schmitt: Geologist on the Moon".Space.com. RetrievedJune 10, 2016.
  125. ^"Apollo 13". US: NASA. July 9, 2009. RetrievedNovember 7, 2019.
  126. ^ab"Extravehicular Activity".history.nasa.gov. RetrievedFebruary 12, 2023.
  127. ^"NASA Lunar Sample Laboatory Facility".NASA Curation Lunar. NASA. September 1, 2016. RetrievedFebruary 15, 2017.A total of 382 kilograms of lunar material, comprising 2200 individual specimens returned from the Moon ...
  128. ^Chaikin, Andrew (2007).A Man On the Moon: The Voyages of the Apollo Astronauts (Third ed.). New York: Penguin Books. pp. 611–613.
  129. ^Kristen Erickson (July 16, 2009). Amiko Kauderer (ed.)."Rock Solid: JSC's Lunar Sample Lab Turns 30".40th Anniversary of Apollo Program. NASA. RetrievedJune 29, 2012.
  130. ^Papike et al. 1998, pp. 5-001–5-234
  131. ^Harland 2008, pp. 132–133.
  132. ^Harland 2008, p. 171.
  133. ^Harland 2008, pp. 49–50.
  134. ^Harland 2008, pp. 323–327.
  135. ^Harland 2008, pp. 330–332.
  136. ^Burrows 1999, p. 431
  137. ^Dreier, Casey (May 1, 2022)."An Improved Cost Analysis of the Apollo Program".Space Policy.60: 101476.Bibcode:2022SpPol..6001476D.doi:10.1016/j.spacepol.2022.101476.ISSN 0265-9646.
  138. ^Butts, Glenn; Linton, Kent (April 28, 2009)."The Joint Confidence Level Paradox: A History of Denial"(PDF).2009 NASA Cost Symposium. Cost Analysis Division. pp. 25–26. Archived fromthe original(PDF) on October 26, 2011. RetrievedDecember 15, 2021.
  139. ^Skolnikoff, Eugene B.; Hoagland, John H. (1968).The World-wide Spread of Space Technology. 69-5. Cambridge, MA:MIT Center for Space Research.OCLC 14154430.
  140. ^Callahan, Jason."How Richard Nixon Changed NASA".planetary.org. The Planetary Society. RetrievedJune 20, 2019.
  141. ^1974 NASA authorization hearings, Ninety-third Congress, first session, on H.R. 4567 (superseded by H.R. 7528). Washington: U.S. Govt. Print. Off. 1973.
  142. ^Compton, W. D.; Benson, C. D. (January 1983)."A Science Program for Manned Spaceflight". RetrievedJune 11, 2016.
  143. ^"Manned Venus Flyby". NASA. February 1, 1967. RetrievedJuly 19, 2016.
  144. ^Compton, W. D.; Benson, C. D. (January 1983)."What Goes Up ..." RetrievedJune 11, 2016.
  145. ^ab"Legacy".history.nasa.gov. RetrievedFebruary 12, 2023.
  146. ^"Apollo-Soyuz: An Orbital Partnership Begins". NASA. July 10, 2015. RetrievedJuly 19, 2016.
  147. ^"The 'halo' area around Apollo 15 landing site observed by Terrain Camera on SELENE(KAGUYA)" (Press release). Chōfu, Tokyo:Japan Aerospace Exploration Agency. May 20, 2008.Archived from the original on December 12, 2009. RetrievedNovember 19, 2009.
  148. ^Hautaluoma, Grey; Freeberg, Andy (July 17, 2009). Garner, Robert (ed.)."LRO Sees Apollo Landing Sites". NASA.Archived from the original on November 16, 2009. RetrievedNovember 19, 2009.
  149. ^Townsend, Jason (ed.)."Apollo Landing Sites Revisited". NASA.Archived from the original on November 13, 2009. RetrievedNovember 19, 2009.
  150. ^Robinson, Mark (July 27, 2012)."Question Answered!".LROC News System.Arizona State University. Archived fromthe original on October 24, 2012. RetrievedOctober 28, 2012.
  151. ^"The Human Moon".The New York Times. November 16, 2009.Archived from the original on December 31, 2012. RetrievedNovember 19, 2009.
  152. ^"Apollo 11 30th Anniversary: Introduction". NASA History Office. 1999. RetrievedApril 26, 2013.
  153. ^O'Rangers, Eleanor A. (January 26, 2005)."NASA Spin-offs: Bringing Space Down to Earth".Space.com. RetrievedApril 23, 2024.
  154. ^"Benefits from Apollo: Giant Leaps in Technology"(PDF).NASA.Archived(PDF) from the original on October 9, 2022.
  155. ^"Search".NASA Spinoff. National Aeronautics and Space Administration. RetrievedApril 24, 2024.
  156. ^Mindell 2008, pp. 125–131.
  157. ^Brooks, Grimwood & Swenson 1979, pp. 181–182, 205–208.
  158. ^Butler, P. M. (August 29, 1989).Interplanetary Monitoring Platform(PDF).NASA. pp. 1, 11, 134.Archived(PDF) from the original on October 9, 2022. RetrievedAugust 12, 2019.
  159. ^White, H. D.; Lokerson, D. C. (1971). "The Evolution of IMP Spacecraft Mosfet Data Systems".IEEE Transactions on Nuclear Science.18 (1):233–236.Bibcode:1971ITNS...18..233W.doi:10.1109/TNS.1971.4325871.ISSN 0018-9499.
  160. ^"Apollo Guidance Computer and the First Silicon Chips".National Air and Space Museum.Smithsonian Institution. October 14, 2015. RetrievedSeptember 1, 2019.
  161. ^"Apollo 8: Christmas at the Moon".NASA. February 19, 2015. RetrievedJuly 20, 2016.
  162. ^Chaikin 1994, p. 120
  163. ^Burrows 1999, p. 429
  164. ^Petsko, Gregory A (2011)."The blue marble".Genome Biology.12 (4): 112.doi:10.1186/gb-2011-12-4-112.PMC 3218853.PMID 21554751.
  165. ^Lexington, ed. (May 21, 2011)."Apollo plus 50".The Economist. London:The Economist Newspaper Limited. p. 36. RetrievedAugust 1, 2013.
  166. ^Greenfieldboyce, Nell (July 16, 2009)."Houston, We Erased The Apollo 11 Tapes".NPR. Washington, D.C.: National Public Radio, Inc. RetrievedAugust 1, 2013.
  167. ^Jones, Sam (May 25, 2009)."The moon shoot: film of Apollo mission on show again after 35 years in the can".The Guardian. RetrievedSeptember 5, 2019.
  168. ^Hastings, Julianne (August 13, 1984)."TV World;NEWLN:Race to moon reviewed with NASA film on PBS".UPI. RetrievedMay 2, 2023.
  169. ^Goodsell, Luke (July 17, 2019)."Apollo 11 documentary is a time capsule for the fleeting optimism of mankind's first Moon landing".ABC. RetrievedSeptember 5, 2019.
  170. ^Gleiberman, Owen (August 29, 2007)."Movie Review: In the Shadow of the Moon".Entertainment Weekly. Archived fromthe original on November 7, 2014. RetrievedSeptember 5, 2019.
  171. ^Kenny, Glenn (February 27, 2019)."'Apollo 11' Review: The 1969 Moon Mission Still Has the Power to Thrill".The New York Times. Archived fromthe original on January 1, 2022. RetrievedFebruary 28, 2019.
  172. ^Rubin, Rebecca (February 13, 2019)."'Apollo 11' Documentary Gets Exclusive Imax Release".Variety. RetrievedJuly 20, 2019.
  173. ^Travis, Ben (November 11, 2022)."Indiana Jones 5 Will Pit Indy Against Nazis Again, In 1969 – Exclusive".Empire. RetrievedDecember 24, 2022.

Sources

[edit]

Further reading

[edit]

External links

[edit]
Wikimedia Commons has media related toApollo program.
Wikinews has news related to:
Library resources about
Apollo program

NASA reports

[edit]

Multimedia

[edit]
Launch complexes
Emblem of the Apollo program
Ground facilities
Launch vehicles
Spacecraft and rover
Flights
Uncrewed
Crewed
Saturn
development
Abort tests
Pegasus flights
Apollo 8 specific
Apollo 11 specific
Apollo 12 specific
Apollo 13 specific
Apollo 14 specific
Apollo 15 specific
Apollo 16 specific
Apollo 17 specific
Post-Apollo
capsule use
Related
  • Symbol indicates failure or partial failure
Launch vehicles
Launch vehicle
components
Spacecraft
Spacecraft
components
Space suits
Lunar surface
equipment
Ground support
Ceremonial
Related
Walked on the Moon
Flew to the Moon
without landing
Active
Completed
Canceled
Active
Retired
In development
Cancelled
Policy and history
History
(creation)
General
Human spaceflight
programs
Past
Current
Robotic programs
Past
Current
Individual featured
missions
(human and robotic)
Past
Currently
operating
Future
Communications
and navigation
NASA lists
NASA images
and artwork
Related
Physical
properties
A full moon
Orbit
Surface and
features
Science
Exploration
Time-telling
andnavigation
Phases and
names
Daily phenomena
Related
Active
Past
Lunokhod
Apollo
CLEP
Chandrayaan
Rashid
CLPS
JAXA
Planned
Proposed
Cancelled
Related
Missions are ordered by launch date. Sign indicates failure en route or before intended mission data returned.
Exploration
programs
Active
missions
Orbiters
Landers
Rovers
Flybys
Past
missions
Crewed landings
Orbiters
Impactors
Landers
Rovers
Sample return
Failed landings
Flybys
Planned
missions
Artemis
CLPS
Luna-Glob
CLEP
Chandrayaan
KLEP
Others
Proposed
missions
Robotic
Crewed
Cancelled /
concepts
Related
  • Missions are ordered by launch date. Crewed missions are initalics.
General
Applications
Human spaceflight
General
Programs
Health issues
Spacecraft
Destinations
Space launch
Ground segment
Events
Pre-Colonial
Colonial
1776–1789
1789–1815
1815–1849
1849–1865
1865–1917
1917–1945
1945–1964
1964–1980
1980–1991
1991–2016
2016–present
Topics
Groups
Places
Territorial evolution
Regions
States
Federal District
Insular areas
Outlying islands
Cities
International
National
Other
Portals: