TheBucharest Ring Motorway (or the Bucharest Belt Motorway,Romanian:Autostrada Centura București), termedA0,[1] is a partially builtmotorwayring around the city ofBucharest, the capital ofRomania. It is serving as a second, outer ring around the city, the first being the existingBucharest Ring Road.
It is split into two major sections: the northern and southern half-rings that are each divided into multiple lots. When fully built, it will have a total length of approximately 101 kilometers and will be a motorway connection between the existingA1,A2 andA3 motorways.[2][3]
As of July 2025, the southern half-ring is fully completed and operational, while on the northern half-ring traffic only one lot is fully completed together with a small portion of the adjacent one. The rest of the northern half-ring is under construction. The parts of the motorway currently in service include the section between DN1 and DN2 on the northern half-ring, while connection between A1 and A2 motorways is possible via the southern half-ring.
The South Ring Motorway (51.3 km) was tendered as aconcession contract in December 2012, that was supposed to be awarded in November 2013.[4] Yet, a new tender was announced in July 2017, that shall be completed between the end of 2017 and the first half of 2018, with an estimated cost of 580 million euros.[5] Construction works should take three years and a half to complete. It will run through the south of Bucharest, along the route of thePan-European Corridor IV.[6]
A tender for a segment of 17.5 km (15.5 km of the South section and 2.5 km of the North section), called lot 3, between theA1 motorway and theDN6 road was launched in July 2017 and awarded in April 2018, to the joint-venture Spedition UMB–Tehnostrade–Artera Proiect, with one year allowed for the design of the motorway and two and a half years for the construction works.[7] However, the bid was challenged and awarded to a new constructor, the Greek companyAktor, in October 2018.[8]
The rest of the South section was tendered on the same date as well, with both of the two bids awarded to the Turkish company Alsim Alarko: the contract for the segment of 16.3 km between the DN6 road and theCFR Line 902 (nearJilava), called lot 2, was signed in March 2019 and is due to be finished in 2022,[9] while the bid for the segment of 16.9 km between the CFR Line 902 and theA2 motorway, called lot 1, was under challenge procedures until July 2019,[10] with the contract being signed one month later.[11]
On 30 December 2023, the first section of the South Ring opened between DN5 and DN6. On 15 April 2024, the second section of the South Ring opened between DN4 and DN5.[12]
Initially, in June 2019, 45 km of the Northern half was tendered for auction into three segments,[13] with a fourth lot included later, up to a total of 49.57 km. On 20 September 2023, the contract for the design and execution of the last segment was signed with theImpresa Pizzarotti – Retter Projectmanagement association.[14] On 29 November 2023, the first section opened on the A0, between the A3 motorway and DN1.