From Wikipedia, the free encyclopedia
Proposed natural gas pipeline through south-eastern Europe

South Stream
Proposed Route of South Stream
Proposed Route of South Stream
Location
CountryRussian Federation
European Union
Republic of Serbia
General directioneast–west
FromRusskaya compressor station nearAnapa
Passes throughBlack Sea
Varna
Pleven
Zaječar
Paraćin
Gospođinci
Bački Breg
Hercegszántó
Tornyiszentmiklós
ToTarvisio,Italy
Baumgarten an der March,Austria
General information
TypeNatural gas
PartnersGazprom
Eni
EDF
Wintershall
Naftna Industrija Srbije
Srbijagas
OperatorSouth Stream Transport AG
National project companies
Technical information
Length2,380 km (1,480 mi)
Maximum discharge63 billion cubic metres per annum (2.2×10^12 cu ft/a)
No. of compressor stations10

South Stream (Russian:Южный поток,romanizedYuzhnyy potok;Bulgarian:Южен поток,romanizedJužen potok;Serbian:Јужни ток;Slovene:Južni tok;Hungarian:Déli Áramlat;Italian:Flusso Meridionale) is a canceled pipeline project to transport natural gas of theRussian Federation through theBlack Sea to Bulgaria and through Serbia, Hungary and Slovenia further to Austria. It was never finished.

The project was found in non-compliance with theEuropean Union'sThird Energy Package legislation, which stipulates the separation of companies' generation and sale operations from their transmission networks.[1][2] The Russian Government cancelled the project on 1 December 2014, seven years after the project was started.[3]

It was seen as rival to theNabucco pipeline project,[4] which was abandoned in favor of theTrans Adriatic Pipeline (TAP). Unlike South Stream, the TAP is fully compliant with EU legislation by way ofhaving obtained EU Third Party Access Exemption.

Construction of the Russian onshore facilities for the South Stream pipeline started in December 2012.[5] The project was cancelled by Russia in December 2014 following obstacles from the European Union, the2014 Russian annexation of Crimea, and the resulting imposition of European sanctions on Russia.[6][7] The project has been replaced by other proposed ones Tesla pipeline andTurkish Stream.[8] The latter, renamed as TurkStream, was approved and later completed, sending gas supplies to Bulgaria on 1 January 2020.[9]

History

[edit]

The South Stream pipeline project was announced on 23 June 2007, when the CEOPaolo Scaroni of the Italian energy companyEni and the Vice-ChairmanAlexander Medvedev of the RussianGazprom signed amemorandum of understanding inRome for the construction of the pipeline.[10] On 22 November 2007, Gazprom and Eni signed inMoscow an agreement on establishing a joint project company for the commissioning of the marketing and technical feasibility studies of the project.[11]

The preliminary agreement between Russia and Bulgaria on Bulgaria's participation in the project was signed on 18 January 2008. It was agreed to set up an equally owned company to build and operate the Bulgarian section of the pipeline.[12] The agreement was ratified by Bulgarian Parliament on 25 July 2008.[13] The first agreement between Russia and Serbia was signed even before the announcement of the South Stream project. On 20 December 2006, Gazprom and the Serbian state-owned gas companySrbijagas agreed to conduct a study on building a gas pipeline running from Bulgaria to Serbia.[14] On 25 January 2008, Russia and Serbia signed an agreement to route a northern line of South Stream through Serbia and to create a joint company to build the Serbian section of the pipeline and a gas storage facility nearBanatski Dvor.[15][16] On the same day, Russia and Hungary agreed to set up an equally owned joint company to build and operate the Hungarian section.[17] On 29 April 2008, Russia and Greece signed an intergovernmental agreement on cooperation in construction and operation of the Greek section.[18]

On 15 May 2009, inSochi, in presence of the Prime Minister of RussiaVladimir Putin and the Prime Minister of ItalySilvio Berlusconi, the gas companies of Russia, Italy, Bulgaria, Serbia and Greece signed an agreement on construction of South Stream.[19][20] On 6 August 2009, Russian Prime Minister Putin and the Prime Minister ofTurkeyRecep Tayyip Erdoğan, in presence the Italian premiere Berlusconi, signed a protocol routing the pipeline through the Turkish territorial waters.[21] On 14 November 2009, followed the talks between Slovenian Prime MinisterBorut Pahor and Russia's Putin, the agreement to run a part of the pipeline through Slovenia to Northern Italy was signed by Russian Energy MinisterSergei Shmatko and Slovenian Economy MinisterMatej Lahovnik in Moscow.[22][23] As per the earlier 2008 agreement between the two countries, on 17 November 2009, Russian Gazprom and Serbian Srbijagas createdSouth Stream Serbia AG in Bern, Switzerland. The joint company was responsible for designing, financing, construction and operation of the Serbia section.[24]

On 2 March 2010, Russian Energy Minister Sergei Shmatko and Croatian Economy, Labor and Entrepreneurship Minister Djuro Popijac in the presence of the Prime Minister of Russia Vladimir Putin and Prime Minister of CroatiaJadranka Kosor signed an agreement on linking Croatia with South Stream.[25][26] On 19 June 2010, Gazprom, Eni, andÉlectricité de France published a joint press release confirming that EDF will join the project.[27] On 21 March 2011, Slovenia and Russia signed an agreement regarding the establishment of a joint venture South Stream Slovenia.[28]

The joint venture South Stream AG, equally owned by Gazprom and Eni, was registered on 18 January 2008 in Switzerland.[29] However, on 16 September 2011, a shareholders' agreement was signed between Gazprom, Eni, Électricité de France and Wintershall to establish the new project company South Stream Transport AG for the Black Sea section of the pipeline.[30] The company was incorporated on 3 October 2011 inZug, Switzerland.

On December 28, 2011 Turkey issued its final agreement for allowing the pipeline to pass through its territorial waters.[31][32] The final investment decision for the Serbian section was signed on 29 October 2012, for the Hungarian section on 2 November 2012, for the Slovenian section on 13 November 2012, and for the Bulgarian section on 15 November 2012.[5][33][34][35] On 15 November 2012, shareholders of South Stream Transport AG signed the final investment decision on the offshore section.[5] The ground-breaking ceremony marking start of construction of the Russian onshore facilities was held on 7 December 2012 at the Russkaya compressor station nearAnapa.[5][36][37]

On 25 July 2013, the Vice PremierRepublic of MacedoniaZoran Stavreski signed the agreement on linking section through Republic of Macedonia with South Stream.[38]

In March and April 2014, the contracts for laying the first and second lines of the offshore section were awarded toSaipem andAllseas.[39][40] Contracts for the third and fourth line were to be signed in December 2014 and January 2015.[41]

On 17 April 2014, amidRussia's annexation of Crimea, theEuropean Parliament adopted a non-binding resolution opposing the South Stream gas pipeline and recommending a search for alternative sources of gas supplies for the European Union.[42] On 29 April 2014 a memorandum on the implementation of the Austrian section was signed in Moscow. Commissioning of the Austrian section is scheduled by January 2018.[43] In June 2014, Bulgaria temporarily stopped construction due to theEuropean Commission'sinfringement procedure against Bulgaria for non-compliance with European rules on energy competition public procurements.[44]

In April 2014, Russia filed a complaint at theWorld Trade Organization against theEuropean Union's energy market laws that were enacted in 2009, claiming that they violate international rules. These laws ban suppliers from owning transit facilities such as gas pipelines, and would force Gazprom to allow third-party gas producers to use the South Stream pipeline.[45]

On 1 December 2014, during a state visit to Turkey, president Putin announced that Russia was withdrawing from the project, blaminginternational sanctions and lack of construction permits in the territory of the European Union.[46] Russia has started to build a pipeline throughTurkey known asTurkish Stream.[47] Renamed as TurkStream, the pipeline was later completed, sending gas supplies to Bulgaria on 1 January 2020.[9]

Along with additional supplied to Turkey, Russian gas, according to Putin, “will be retargeted to other regions of the world, which will be achieved, among other things, through the promotion and accelerated implementation of projects involving liquefied natural gas.” In 2015, the supply of Russian gas to Turkey will be raised by 3 billion cubic meters via the already operating Blue Stream pipeline. Later a new undersea pipeline to Turkey, with an annual capacity around 60 billion cubic metres (bcm) will be built. That will allow Turkey to resell Russian gas to Europe.[citation needed]

In 2018, Bulgaria's presidentRumen Radev proposed that the construction of the South Stream pipeline be resumed.[48]

Route

[edit]
Major existing and planned natural gas pipelines supplying Russian gas to Europe in 2012.

The pipeline was to consist of the Russian onshore pipeline, the Black Sea section and pipelines in the South- East Europe. The Russian onshore section would have run from the Pochinki compressor station to the Russkaya compressor station nearAnapa.[37] The 931-kilometre (578 mi) long offshore section was to run from the Russkaya compressor station through the Black Sea to Galata nearVarna, Bulgaria.[49][41] Because of theRussia–Ukraine gas disputes, the pipeline was to be routed through Turkey's waters to avoid theexclusive economic zone ofUkraine.[21][50][51] At the same time Russia's2014 annexation of Crimea would have allowed more direct route through theCrimean waters.[52]

The 1,455-kilometre (904 mi) long onshore section was to start from Varna and run toPleven.[5][53] From there, the original southwestern route was to continue through Greece andIonian Sea to southern Italy.[53] However, this route was abandoned.[50] The newer northwestern route would have continued from Pleven to Serbia. In Serbia, then running throughZaječar andParaćin toČenta. From Čenta the main pipeline would have continued in direction ofGospođinci while branch-off line would run toRepublika Srpska inBosnia and Herzegovina.[5] Srbijagas planned to construct alongSava river a 480-kilometre (300 mi) long branch pipeline with a capacity of 1.2 billion cubic metres (42 billion cubic feet) toBanja Luka andSarajevo.[54] It was also surmised thatMontenegro could have connected to the pipeline.[55]

Before reaching Gospođinci, the main line was to split. One route would continue through Serbia and Hungary toBaumgarten an der March in Austria. Another route would have continued through Gospođinci andBački Breg also to Hungary with branch-off to Croatia.[5] In Hungary it would have gone throughHercegszántó andTornyiszentmiklós to Slovenia and further in direction ofTarvisio to supply northern Italy.[28][56][57][58]

Technical description

[edit]

The feasibility study of the offshore section was conducted bySaipem, a subsidiary of Eni.[59][60] Planning was done by INTECSEA, a subsidiary ofWorleyParsons. Giprospetsgas, an affiliate ofGazprom, has been appointed as a general design contractor.[61] The offshore pipeline is planned to carry 63 billion cubic metres (2.2 trillion cubic feet) of natural gas per year.[4] It will have four parallel lines with capacity of 15.75 billion cubic metres (556 billion cubic feet) each.[5] The offshore pipeline will use pipes with a diameter of 32 inches (810 mm), designed for 27.73 megapascals (4,022 psi) of working pressure and having the pipe wall thickness of 39 millimetres (1.5 in).[62][63] The first line should be ready by the end of 2015, the second and third lines by the end of 2016, and the fourth line by the end of 2017. The offshore section is expected to cost €10 billion.[5][64]

Pipeline sections in Bulgaria, Serbia, Hungary, and Slovenia would have capacity at least 10 billion cubic metres (350 billion cubic feet) per year.[23] The onshore pipeline will have eight compressor stations and it is expected to cost €6 billion.[5][64]

At least two gas storage facilities would be constructed of which one would be an underground storage facility in Hungary with capacity of minimum 1 billion cubic metres (35 billion cubic feet) and another one in Banatski Dvor, Serbia with capacity of 3.2 billion cubic metres (110 billion cubic feet).[65][66] Hungarian oil and gas companyMOL Group has offered its empty natural gas field atPusztaföldvár as a 9 billion cubic metres (320 billion cubic feet) storage facility.[67] BritishMelrose Resources is planning to convert the Galata offshore field in Bulgaria to a gas storage facility with initial capacity of 1.7 billion cubic metres (60 billion cubic feet) by 2009.[68] There are also allegations that the South Stream pipeline will be connected to theWingas-ownedHaidach gas storage.

Project companies

[edit]

The pipeline would be built and operated by several project companies. For the construction and operation of the offshore section of South Stream originally two companies were established, both in Zug in Switzerland with the share capital of 100,000 CHF.[69][70][71] South Stream AG, a joint venture between Gazprom and Eni was incorporated on 18 January 2008, and South Stream Transport AG, a joint company of Gazprom, Eni, Électricité de France, and Wintershall was incorporated on 3 October 2011.[30][70][71] Head of South Stream Transport AG isMarcel Kramer, formerchief executive officer of the gas transportation companyGasunie.[69][72] Executive director is Oleg Aksyutin.[41] Gazprom owns 50% of shares of South Stream Transport AG, Eni 20%, and Électricité de France and Wintershall 15% both.[30] In November 2012, it was decided to incorporate South Stream Transport B.V., the current project company, inAmsterdam.[73] Earlier Eni had registered inAmsterdam a company named South Stream BV, but in February 2012 it was renamed Eni JPDA 11-106 BV.[69][74]

The Bulgarian section of the pipeline will be built and operated by a joint venture of Gazprom andBulgargaz and the Serbian section by the joint venture of Gazprom andSrbijagas.[16][75][76][77] The Hungarian section will be built and operated by the equally owned joint venture between Gazprom and the state-owned Hungarian Development Bank MFB, which will buy the elaborated feasibility study of Hungarian section from SEP Co., a joint venture of Gazprom and MOL.[65][78] The Slovenia section would be built and operated by an equally owned joint venture of Gazprom andGeoplin Plinovodi.[23] For construction of the Croatian section a 50-50 Russian-Croatian joint company would be established.[26]

Implications

[edit]

Nabucco pipeline project

[edit]
Map of the planned Nabucco and South Stream pipelines.

The South Stream project was seen as a rival to theNabucco pipeline project.[4] Some experts like Alan Riley fromLondon City University were claiming that the South Stream pipeline is a political project to counter Nabucco and to expand Russian presence in the region.[79]

CEO of EniPaolo Scaroni proposed to merge Nabucco and South Stream projects to "reduce investments, operational costs and increase overall returns".[80][81] This proposal was rejected by energy minister of Russia Sergei Shmatko saying that "South Stream is more competitive than Nabucco" and that "Nabucco and South Stream are far from being competitors".[82] AlsoOMV, a partner in both projects, has said that there were no ongoing discussions about merging the projects.[83]

Conflict with Ukraine

[edit]

South Stream has been seen as diverting some gas transported through Ukraine, instead of providing a new source of gas for Europe.[79] To avoid Ukraine's exclusive economic zone, the pipeline was re-routed through Turkish waters.[21]

Offer to Romano Prodi

[edit]

Before stepping down from the premiership, Italian Prime MinisterRomano Prodi received an offer from Gazprom to become the Chairman of South Stream AG. This move was compared with the appointment of the former Chancellor of GermanyGerhard Schröder to leadNord Stream AG, a consortium operating theNord Stream 1 pipeline. Prodi has declined this offer.[84] According to the Prodi's spokesman "Prodi was extremely flattered, but reiterated that he wants to take some time off to ponder after leaving Italian politics."[85]

Stroytransgaz contract

[edit]

In May 2014, it was disclosed that the contract for construction of the Bulgarian section was awarded to Stroytransgaz, a company controlled byGennady Timchenko through hisVolga Group. Earlier Timchenko was included in thesanctions list in the wake of the Russian annexation of Crimea due to his close ties with President Putin.[86]

See also

[edit]

References

[edit]
  1. ^"EU calls for South Stream suspension".Upstream Online.NHST Media Group. 28 May 2014. Retrieved24 June 2014.
  2. ^Overland, Indra. "The Hunter Becomes the Hunted: Gazprom Encounters EU Regulation". In Anderson, Svein; Goldthau, Andreas; Sitter, Nick (eds.).Energy Union: Europe's New Liberal Mercantilism?. Blasingstoke: Palgrave MacMillan. pp. 115–130.
  3. ^"Putin drops South Stream gas pipeline to EU, courts Turkey".Reuters. 1 December 2014. Retrieved4 September 2020.
  4. ^abc"Gazprom Agrees To Boost Pipeline Capacity". Downstream Today.Deutsche Presse-Agentur. 15 May 2009. Retrieved16 May 2009.
  5. ^abcdefghijRodova, Nadia (15 November 2012)."Russia, Bulgaria sign final investment decision on South Stream gas pipeline".Platts. Retrieved17 November 2012.
  6. ^Putin drops South Stream gas pipeline to EU, courts Turkey, Reuters, Darya Korsunskaya
  7. ^By Jim Yardley and Jo Becker (30 December 2014)."How Putin Forged a Pipeline Deal That Derailed".The New York Times. Retrieved31 December 2014.Mr. Putin, on a state visit to Turkey, announced that South Stream was dead
  8. ^Geropoulos, Kostis (20 August 2015)."Greece, Serbia, Hungary, FYROM to sign memorandum on the construction of the pipeline, which should connect the Turkish Stream pipeline with Austria".New Europe. Retrieved24 November 2015.
  9. ^ab"Russia begins TurkStream gas flows to Greece, North Macedonia".Reuters. 5 January 2020. Retrieved28 November 2020.
  10. ^"Eni and Gazprom sign gas pipeline accord for EU". Energy Publisher. 23 June 2007. Archived fromthe original on 28 September 2007. Retrieved26 June 2007.
  11. ^"Eni and Gazprom sign the agreement for the South Stream Project".Scandinavian Oil-Gas Magazine. 23 November 2007. Retrieved24 February 2008.
  12. ^"Eni: Agreement Russia and Bulgaria on South Stream". AGI News. 18 January 2008. Archived fromthe original on 13 January 2009. Retrieved18 January 2008.
  13. ^[Bulgaria Parliament Ratifies South Stream Gas Pipeline Agreement "Bulgarian Parliament Ratifies South Stream Deal"].Novinite. 25 July 2008. Retrieved4 November 2018.{{cite news}}:Check|url= value (help)
  14. ^"Serbia signs up for gas pipe study".Upstream Online. NHST Media Group. 20 December 2006. Retrieved26 February 2008.
  15. ^"Serbia signs strategic energy deal with Russia".Reuters. 25 January 2008. Archived fromthe original on 4 January 2013. Retrieved25 January 2008.
  16. ^ab"Russia, Serbia Sign Gas Pipeline Deal".RIA Novosti. 25 February 2008. Retrieved4 November 2018.
  17. ^Shchedrov, Oleg; Solovyov, Dmitry (25 February 2008)."Russia wins Hungary for South Stream gas project".Reuters. Archived fromthe original on 15 July 2012. Retrieved25 February 2008.
  18. ^"Russia, Greece Sign South Stream Deal". Downstream Today. Xinhua. 29 April 2008. Retrieved10 May 2008.
  19. ^Zhdannikov, Dmitry (15 May 2009)."Russia seeks to speed up South Stream with new deals".Reuters. Archived fromthe original on 1 February 2013. Retrieved16 May 2009.
  20. ^"South Stream Flows out of Sochi with New Pipes Cutting through Bulgaria".Standart. 15 May 2009. Archived fromthe original on 16 July 2011. Retrieved16 May 2009.
  21. ^abcLyubov Pronina, Ali Berat Meric (6 August 2009)."Turkey Offers Route for Gazprom's South Stream Gas Pipeline".Bloomberg. Retrieved6 August 2009.
  22. ^Marja Novak (9 November 2009)."Slovenia to sign South Stream deal on Saturday".Reuters. Archived fromthe original on 1 February 2013. Retrieved9 November 2009.
  23. ^abcStephen Bierman, Anna Shiryaevskaya (14 November 2009)."Russia, Slovenia Sign South Stream Gas Pipe Accord".Bloomberg. Retrieved14 November 2009.
  24. ^"Gazprom and Srbijagas Create South Stream Serbia AG Joint Venture" (Press release).Gazprom. 17 November 2009. Retrieved18 November 2009.
  25. ^Korsunskaya, Dasha; Soldatkin, Vladimir (2 March 2010)."Slovenia to sign South Stream deal on Saturday".Reuters. Archived fromthe original on 1 February 2013. Retrieved3 March 2010.
  26. ^abAnatoly Medetsky (2 March 2010)."Croatia Agrees to Join South Stream".The Moscow Times. Retrieved3 March 2010.
  27. ^Soldatkin, Vladimir (19 June 2010)."France's EDF to get South Stream stake from ENI".Reuters. Archived fromthe original on 1 February 2013. Retrieved7 July 2010.
  28. ^ab"Sporazum o Južnem toku je podpisan" [The agreement on South Stream has been signed] (in Slovenian). MMC RTV Slovenia. 22 March 2011. Retrieved14 October 2011.
  29. ^"Eni, Gazprom set up company for South Stream gas pipeline".Forbes. 18 January 2008. Archived fromthe original on 4 June 2011. Retrieved24 February 2008.
  30. ^abcGronholt-Pedersen, Jacob (16 September 2011)."Companies Sign South Stream Deal".The Wall Street Journal. Retrieved16 September 2011.
  31. ^Rozova, Anna (28 December 2011).Турция впустила "Южный поток" [Turkey allowed the South Stream in].Kommersant (in Russian). Retrieved28 December 2011.
  32. ^Akkan, Faruk (29 January 2012)."Turkey and Russia develop strategic alliance".Today's Zaman. Archived fromthe original on 21 December 2011. Retrieved20 February 2012.
  33. ^"Gazprom and Serbia sign final investment decision on South Stream" (Press release). Gazprom. 29 October 2012. Retrieved17 November 2012.
  34. ^"Final investment decision approved for South Stream in Hungary". Europétrole. 2 November 2012. Retrieved17 November 2012.
  35. ^"Final investment decision made for South Stream in Slovenia".Russia Behind The Headlines.Interfax. 13 November 2012. Retrieved17 November 2012.
  36. ^Assenova, Margarita (16 November 2012)."EU and US Policy on South Stream Remains Ambiguous".Eurasia Daily Monitor.The Jamestown Foundation. Retrieved17 November 2012.
  37. ^ab"Gazprom starts work on South Stream".Upstream Online.NHST Media Group. 7 December 2012. Retrieved10 December 2012.
  38. ^"Macedonia Shrugs Over Halt to South Stream Pipeline".Balkan Insight. BIRN. 10 June 2014. Retrieved24 June 2014.
  39. ^"Saipem clinches first-phase South Stream offshore pipelay".Offshore Magazine.Pennwell Corporation. 18 March 2014. Retrieved24 June 2014.
  40. ^"South Stream returning to Austria".Pipeline International. 8 May 2014. Retrieved24 June 2014.
  41. ^abc"South Stream prepares deals for Black Sea lines".Upstream Online.NHST Media Group. 30 May 2014. Retrieved24 June 2014.
  42. ^"MEPs Oppose South Stream, Seek Sanctions against Russian Energy Firms".Novinite. 17 April 2014. Retrieved24 June 2014.
  43. ^"Gazprom lures Austria with South Stream branch".EurActiv. 30 April 2014. Retrieved30 April 2014.
  44. ^"Austria pleads for South Stream pipeline".EurActiv. 24 June 2014. Retrieved24 June 2014.
  45. ^"Russia challenges EU energy market rules". Yahoo News.Associated Press. 1 May 2014. Retrieved2 May 2014.
  46. ^"Russia drops South Stream gas pipeline plan".BBC News. 1 December 2014. Retrieved1 December 2014.
  47. ^Reed, Stanley; Arsu, Sebnem (21 January 2015)."Russia Presses Ahead With Plan for Gas Pipeline to Turkey".New York Times. Retrieved23 January 2015.
  48. ^"Radev pleads in Moscow for 'Bulgarian Stream' pipeline". 22 May 2018.
  49. ^D. Dimitrov, P. Dimitrov, V. Peychev, M. Tsaneva. (2014).Physical - geographical and geological - lithological characteristic a trace of the pipeline South stream in the Bulgarian economical zone of the Black Sea. Konstantin Preslavsky Publishing House, Shumen. 7-15.doi:10.13140/RG.2.2.31954.71367.
  50. ^abSocor, Vladimir (12 February 2009)."Gazprom Reveals Unaffordable Costs of South Stream Project".Eurasia Daily Monitor.The Jamestown Foundation. Retrieved13 February 2009.
  51. ^"Russia seeks Turkey's permission for South Stream studies".Today's Zaman. 11 February 2009. Retrieved13 February 2009.[permanent dead link]
  52. ^Broad, William J. (17 May 2014)."In taking Crimea, Putin gains a sea of fuel reserves".The New York Times. Retrieved24 June 2014.
  53. ^ab"Greece steps up for South Stream".Upstream Online.NHST Media Group. 15 April 2008. Retrieved19 April 2008.
  54. ^Sekularac, Ivana (15 October 2009)."Serbia's gas monopoly eyes pipeline in Bosnia".Reuters. Retrieved28 October 2009.
  55. ^"Montenegro Joins South Stream Gas Pipeline".Turkish Weekly. 3 February 2012. Archived fromthe original on 31 May 2012. Retrieved12 October 2012.
  56. ^"OMV calls for South Stream through Austria".Upstream Online.NHST Media Group. 17 April 2008. Retrieved19 April 2008.
  57. ^"Slovenia eyes South Stream berth".Upstream Online.NHST Media Group. 11 April 2008. Retrieved19 April 2008.
  58. ^"Gazprom: South Stream To Cross Slovenia". Downstream Today.STA. 11 June 2008. Retrieved12 June 2008.
  59. ^Ilieva, Tsvetelia; Shchedrov, Oleg (18 January 2008)."Bulgaria signs up for Russian natural gas project".Reuters. Archived fromthe original on 5 March 2016. Retrieved19 January 2008.
  60. ^"South Stream price tag hits $20bn".Upstream Online. NHST Media Group. 30 July 2008. Retrieved30 July 2008.
  61. ^Mayants, Alex (2009)."Gazprom's South Stream project crossing the Black Sea"(PDF).INTECSEA Quarterly Journal (Q3). INTECSEA. Archived fromthe original(PDF) on 5 July 2010. Retrieved25 October 2011.
  62. ^"Gazprom says large diameter pipe purchases to rise 30 percent in 2011".LNG World News. 22 September 2011. Retrieved22 September 2011.
  63. ^"VSW Produces a Qualification Batch of LDP for the South Stream Project" (Press release). OMK. 21 March 2011. Retrieved25 October 2011.[permanent dead link]
  64. ^ab"Ukrainian gas transmission system may cost more than South Stream construction" (Press release). Gazprom. 30 December 2011.| accessdate = 2012-02-20
  65. ^ab"Ukraine Surfaced in South Stream Project".Kommersant. 29 February 2008. Archived fromthe original on 6 March 2008. Retrieved2 March 2008.
  66. ^Socor, Vladimir (9 January 2008)."Gazprom set to pounce on Serbia as Putin moves into the Balkans".Eurasia Daily Monitor.The Jamestown Foundation. Archived fromthe original on 13 March 2008. Retrieved1 June 2008.
  67. ^"MOL offers reserve for South Stream". Hungary Around the Clock. 5 May 2008. Retrieved18 May 2008.
  68. ^"Melrose leaps on Bulgarian gas storage news". ShareCast. 25 June 2008. Archived fromthe original on 16 July 2011. Retrieved25 July 2008.
  69. ^abc"South Stream might move from Switzerland to Holland".Interfax. 6 August 2012.(subscription required). Retrieved15 September 2012.
  70. ^ab"South Stream AG, Zug" (in German). itonex ag. Retrieved27 February 2008.
  71. ^ab"South Stream Transport AG, Zug" (in German). itonex ag. Retrieved20 February 2012.
  72. ^"Marcel Kramer: I am absolutely confident in South Stream's future" (Press release).Gazprom. 15 October 2010. Archived fromthe original on 24 October 2010. Retrieved28 October 2010.
  73. ^"Final investment decision adopted for South Stream offshore section" (Press release).Gazprom. 15 November 2012. Retrieved17 November 2012.
  74. ^Socor, Vladimir (15 August 2012)."Moscow Can Use West-European Partners in South Stream Project".Eurasia Daily Monitor. Vol. 9, no. 156.Jamestown Foundation. Retrieved15 September 2012.
  75. ^"South Stream project gets new momentum in Bulgaria".The Southeast European Times. 18 October 2010. Retrieved18 October 2010.
  76. ^Shchedrov, Oleg; Tzortzi, Ellie (25 February 2008)."Russia and Serbia firm up gas pipeline deal".Reuters. Archived fromthe original on 9 March 2008. Retrieved25 February 2008.
  77. ^MacDonald, Neil (25 February 2008)."Medvedev shows support for Serbia".Financial Times. Retrieved26 February 2008.
  78. ^"Budapest does South Stream sums".Upstream Online. NHST Media Group. 28 February 2008. Retrieved1 March 2008.
  79. ^abPop, Valentina (14 February 2008)."Energy security: South Stream vs. Nabucco gas pipelines".The Southeast European Times. Archived fromthe original on 19 February 2008. Retrieved27 February 2008.
  80. ^"ENI calls for South Stream, Nabucco links".United Press International. 11 March 2010. Retrieved20 March 2010.
  81. ^Martinez, Andres R.; Resnick-Ault, Jessica (10 March 2010)."Europe Needs to Push Gas Infrastructure Spending, Scaroni Says".Bloomberg. Retrieved20 March 2010.
  82. ^Shiryaevskaya, Anna (15 March 2010)."Russia Rejects Eni Call to Merge Europe Gas Pipelines".Bloomberg. Retrieved20 March 2010.
  83. ^Grove, Thomas (18 March 2010)."OMV says no ongoing talks to merge rival pipelines".Reuters. Archived fromthe original on 4 January 2013. Retrieved20 March 2010.
  84. ^Dempsey, Judy (28 April 2008)."Gazprom courts Prodi as pipeline chief".The New York Times. Retrieved14 October 2011.
  85. ^Di Leo, Luca; Moloney, Liam (28 April 2008)."Outgoing Italian Premier Turns Down Top Job for South Stream". Downstream Today.Dow Jones Newswires. Retrieved10 May 2008.
  86. ^"Sanctioned Russian Tycoon Wins Bulgaria's South Stream Bid".Novinite. 27 May 2014. Retrieved24 June 2014.

External links

[edit]
Wikimedia Commons has media related toSouth Stream.
Pipeline systems ofRussia by year of launch
Natural gas pipelines
Petroleum (oil) pipelines
Other pipelines
Black Sea energy
Oil fields
Black Sea map
Natural gas
fields
Pipelines