Silver Line (Washington Metro)

Route map:
This is a good article. Click here for more information.
From Wikipedia, the free encyclopedia
Washington Metro rapid transit line

Silver Line
A Silver Line train atGreensboro in April 2024
Overview
LocaleWashington metropolitan area
Termini
Stations39
Service
TypeRapid transit
SystemWashington Metro
Operator(s)Washington Metropolitan Area Transit Authority
Rolling stock3000-series,6000-series,7000-series
History
OpenedJuly 26, 2014 (2014-07-26) (Phase 1)
November 15, 2022 (2022-11-15) (Phase 2)
Technical
Line length48.5 mi (78.1 km)
Number of tracks2
CharacterAt-grade, elevated, and underground
Track gauge4 ft 8+14 in (1,429 mm)
ElectrificationThird rail750 V DC
Route map
Map Silver Line highlighted in silver
Show interactive map
Ashburn
Loudoun Gateway
Dulles Yard
Dulles International AirportDulles International Airport
Innovation Center
Herndon
Reston Town Center
Wiehle–Reston East
Spring Hill
Greensboro
Tysons
McLean
Falls Church Yard
East Falls Church
Ballston–MU
Virginia Square–GMU
Clarendon
Court House
Rosslyn
Foggy Bottom–GWU
Farragut West
McPherson Square
Metro Center
Federal Triangle
Smithsonian
RF&P Subdivision
to Virginia
L'Enfant Plaza
Federal Center SW
Capitol South
Eastern Market
Potomac Avenue
Stadium–Armory
Minnesota Avenue
Deanwood
Cheverly
Landover
New Carrollton
Amtrak
New Carrollton Yard
Benning Road
Capitol Heights
Addison Road
Morgan Boulevard
Largo
Multiple services sharing track

Handicapped/disabled access All stations are accessible
This diagram:
Show route diagram

TheSilver Line is arapid transit line of theWashington Metro system, consisting of 39stations inLoudoun County,Fairfax County andArlington County,Virginia,Washington, D.C., andPrince George's County,Maryland. The Silver Line runs fromAshburn in Loudoun County, Virginia toLargo andNew Carrollton in Prince George's County, Maryland. Five stations, from both lines' eastern terminus at Largo toBenning Road, are shared with theBlue Line alone; five stations are shared with theOrange Line alone from both lines eastern terminus at New Carrollton toMinnesota Avenue; thirteen stations, fromStadium–Armory toRosslyn, with both theOrange Line and Blue Lines; and five stations fromCourt House toEast Falls Church with the Orange Line alone. Only the 11 stations fromMcLean toAshburn are exclusive to the Silver Line. Five of these 11 stations began service on July 26, 2014 as Phase 1, and six began service as Phase 2 on November 15, 2022.

The 11.7-mile (18.8 km) portion of the Silver Line between its split from the Orange Line andWiehle–Reston East is entirely in Fairfax County, Virginia and was constructed as Phase 1 of the Dulles Corridor Metrorail Project.[1] Phase 2 expanded the line another 11.5 miles (18.5 km) to Ashburn in Loudoun County viaDulles International Airport. The $6.01 billion, 23.1-mile Dulles Corridor Metrorail Project is Metro's largest expansion by route mileage since its inception in 1976.[2][3]

Trains run every 10 minutes during weekday rush hours, every 12 minutes during weekday off-peak hours and weekends, and every 15 minutes daily after 9:30pm.[4]

History

[edit]

Planning

[edit]

Early Dulles extension proposals

[edit]

TheU.S. federal government, which owned and operatedDulles International Airport beforeCongress created theMWAA, built theDulles Access Road in the 1960s to connect the airport toWashington, D.C., by way ofVirginia State Route 267. As the access road was built, the authorities opted to reserve themedian of the road for some form of rail transit,[5] and the nearbyWest Falls Church was designed so that the line could eventually be extended in this direction.[6] The original 1968 Metrorail plan included an eventual extension to Dulles airport.[7] In 1969, U.S. Senator from VirginiaWilliam B. Spong Jr. tried unsuccessfully to have the extension to Dulles be built as part of an early stage of the system rather than having it be built some time in the future.[8] A $130,000 study of the feasibility of a Metrorail extension to Dulles was authorized that year;[9][10] the study, published in 1971, estimated that 30,000 people would ride the extension each day.[11]

In the 1980s, U.S. SenatorPaul Trible and U.S. RepresentativeFrank R. Wolf again proposed that the federal government study extending Metrorail to Dulles Airport.[12] A $500,000 grant to study the feasibility of extending Metrorail to Dulles was announced in late 1994.[13] TheVirginia General Assembly authorized the Commonwealth Transportation Board (CTB) in 1995 to provide for "additional improvements to the Dulles Toll Road and Dulles Access Road corridor including, but not limited to, mass transit, including rail and capacity-enhancing treatments from surplus net revenues of the Dulles Toll Road".[14] The same year, a panel composed of Virginia state and municipal officials proposed a $1.6 billion Metrorail extension to Dulles Airport, which would also include stops inLoudoun County,Herndon,Reston, andTysons.[15] This extension, if built, would branch off theOrange Line.[16] The Loudoun County government also proposed setting aside space for a rail maintenance yard in an attempt to convince Metrorail officials to approve the extension.[17]

In 1998,Raytheon engineers and constructors proposed to build and operate a Dulles CorridorBus Rapid Transit (BRT) system.[18] In January 1999, the Tysons-Dulles Corridor Group (which includedBechtel Corporation and West*Group) offered a competing BRT proposal that would ultimately extend the rail line to Ashburn.[18] There was also a proposal for a 7-mile (11 km) circular Metrorail extension with seven stops in Tysons, along with an express bus traveling from Tysons to Dulles.[19] These proposals prompted the Virginia Department of Transportation (VDOT) to evaluate the merits of BRT and heavy rail public transit in the corridor.

Significant progress and approval

[edit]
As originally planned, Silver Line trains were to reverse course using the D98pocket track east of theStadium–Armory station. However, safety concerns raised in December 2012 required service to be extended toLargo.

Local residents and officials had talked of a Metro extension to Dulles since the Washington Metro began service in 1976,[18] but significant planning did not begin until 2000. The Dulles Corridor Rapid Transit Project "scoping" process began in April 2000 with a series of meetings with local and federal officials, designed to collect the necessary authorities for the project. Local and federal law required extensiveAnalysis of Alternatives – the two most likely being bus lanes or inaction – and of the environmental impact. The rail-only line won over the other alternatives. Initial environmental hearings, which closed on August 28, 2002, were positive. Although planners originally considered ending the first phase at Tysons, state officials decided that the first phase would end at Reston's Wiehle Avenue, partially to reassure the Metropolitan Washington Airports Authority that the line would eventually run to Dulles Airport.[20] The project received formal approval on June 10, 2004.[18]

In February 2005, the CTB approved a 50 cent increase in the Dulles Toll Road toll rates, effective May 22, 2005, and "reaffirm[ed] that no less than 85% of existing surplus Dulles Toll Road net revenues shall be dedicated for mass transit and rail in the [Dulles] Corridor" and provided "that all additional toll revenue generated from the May 22, 2005 toll adjustment shall be dedicated to the [Metrorail] Project."[21] Between July 1, 2003, and November 1, 2008, when the toll road was transferred to MWAA, over $138 million in net surplus toll revenue (together with accumulated interest) was provided to MWAA for the Silver Line project.[22]

Financing

[edit]

Although the original financing plan called for a 50-cent toll increase on the Dulles Toll Road to finance the Silver Line (25 cents at the main plaza and 25 cents at the ramp plazas), the increase in projected costs resulted in the MWAA Board approving an increase in the surcharges. Effective January 1, 2010, the fare surcharge was increased to 50 cents at both the main plaza and ramp plazas, with additional 25-cent increases in main-plaza tolls set for 2011 and 2012.[23] These toll surcharges are designed to support MWAA's 52.6% share of the projected $5.25 billion combined cost of Phase 1 and Phase 2. MWAA has justified these toll increases as necessary to meet an estimated $220 million in annual debt-service costs projected by 2020.[24] These toll revenue requirements were based on the assumption that the federal government, although it contributed $900 million to Phase 1, would not contribute funds for Phase 2.[24]

As a result of the surcharge increases, the toll in 2012 was $2.25,[25] or 16 cents per mile (1.6 km). The toll increase proposal drew 221 public comments and opponents outnumbered supporters by about 3 to 1.[25] However, as the cost estimate grew from $5.25 billion to $6.8 billion, no final decisions have been reached to address the projected shortfall.

Tysons Corner tunnel dispute

[edit]

As part of the preliminary engineering process from 2000 to 2004, WMATA explored the possibility of twin tunnels running from the east of theMcLean station to the west of theSpring Hill station, with all four stations on that stretch to be below ground. Planners rejected that option (Alignment T13) on the grounds that "it would cost $3.5 billion, which is approximately $422 million higher than the cost for [mostly aerial] Alignment T6. Alignment T13 would also have a greater potential for cost escalation than other alignments evaluated in the Draft EIS because underground construction poses risks that cannot be completely identified prior to construction. Most of the significant risks relate to unknown subsurface conditions such as soil conditions, utilities, hazardous materials, and archaeological resources."[26] Instead, they favored an alignment that relied on aerial structures, with just a short tunnel, running only between the Tysons Corner (nowTysons) andGreensboro stations (underneath higher ground) with all four stations being at or above ground.[27]

Starting in 2005, WMATA engineers explored the possibility of tunneling under Tysons with a large-bore tunneling machine, providing space for two tracks and stations within a bore with a diameter of 40 feet or more.[28] The contractor found that there would not be a significant cost reduction and proposed staying with the short tunnel option.[29]

After allegations that the design contractor had inflated costs for the tunnel in order to avoid sharing the job with an outside tunneling contractor, the long tunnel concept was revived in April 2006. The allegations led to calls for an outside cost estimate to determine more realistic tunnel costs.[30] On May 15, 2006, Virginia Transportation SecretaryPierce Homer announced the creation of an advisory panel headed by theAmerican Society of Civil Engineers. The panel had about two months to evaluate options for completing the line through Tysons,[31] with the results presented to the state on July 27, 2006[32] and published on July 31, 2006.[33]

On September 6, 2006,Virginia GovernorTim Kaine announced his decision in favor of an elevated track through Tysons. In his statement, Kaine said he believed a tunnel would be the best option, but decided against it, citing a fear of losing federal funding for the project.[34]

Shortly after Governor Kaine's decision, the GreaterMcLeanChamber of Commerce formed a coalition of tunnel supporters, called Tysons Tunnel, Inc. and put forth a technical proposal to help revive consideration of building a tunnel through Tysons.[35] TheVirginia Department of Rail and Public Transportation hired an independent consultant to assess the coalition's proposal. However, the consultant's report – sent to Secretary Homer on March 7, 2007, stated that "[t]here is a significant risk that the project cost of a Large Bore Tunnel would not meet theFederal Transit Administration'scost-effectiveness ratio criteria, which could compromise federal funding for the project".[36][37]

On November 26, 2007, Tysons Tunnel, Inc. filed a lawsuit against theUnited States Department of Transportation and theFederal Transit Administration (FTA) in theEastern District of Virginia challenging the denial of their petition to reopen and consider additional evidence regarding the benefits of a tunnel over the aerial option. Gary Baise, theRepublican challenger toGerry Connolly'sFairfax County Board of Supervisors Chairmanship, represented Tysons Tunnel.[38] By 2010, Tysons Tunnel, Inc. ceased operations.[39]

Start of construction was delayed as approval of the $900 million federal contribution to project costs awaited the conclusion of FTA's review of the proposal submitted by Virginia. Elected officials of the state, including GovernorTim Kaine and U.S. SenatorsJohn Warner andJim Webb, arrived at the FTA on January 24, 2008, to address last minute concerns by FTA staff and administrators. FTA AdministratorJames Simpson presented Governor Kaine with a letter that contained stark criticisms of the project as presented. The project as presented was given a "medium–low" rating (projects must receive a "medium" or higher rating to be approved under the Federal New Starts Funds project) and determined ineligible to receive the $900 million in federal funding. FTA's concerns included the Metropolitan Washington Airports Authority's inexperience in large design-build contracts, an exaggeration of funding numbers from theDulles Toll Road and an inability for Metro to maintain the 23-mile (37 km) line once it had been built. Virginian leaders vowed to address the concerns by January 28, 2008, as several fixed price contracts for building materials costs were due to expire on February 1.[40][41] Governor Kaine requested an extension of the deadline to February 1, which was granted by the FTA.[42]

On April 30, 2008, the FTA reversed the earlier decision and approved the above-ground project, saying that it met standards for cost efficiency, construction and ridership, moving it closer to receiving the $900 million in federal funding. Officials toldThe Washington Post that the project would move into the final design stage.[43] The FTA approved funding for the project on December 4, 2008.[44]

On March 10, 2009, U.S. Transportation SecretaryRay LaHood signed the formal agreement that awarded the $900 million promised by the federal government for construction of the Silver Line, with major construction expected to begin in several weeks. Utility relocation work started at Tysons in mid-2008.[45]

Construction

[edit]
Project logo

MWAA planned to award a separate design-build contract for Phase 2.[46] The Phase 2 contract was awarded in May 2013 and the projected completion date was to be in 2018.[47] However, it was later extended to 2022.[48]

Although construction was planned to begin in 2005, the delays in approval of funding pushed back the start date. To facilitate Silver Line construction, responsibility for the project was transferred on November 1, 2008, from theVirginia Department of Transportation (VDOT) to the MWAA. Utility relocation work began in 2008, and construction began on March 12, 2009.[18][49] The full line to Ashburn, including a station at Dulles International Airport, was at the time expected to be completed in 2016.[50]

Pier support

[edit]
2010 view of a then unused bridge pier nearWest Falls Church station, intended to support a Silver Line bridge
The same bridge pier after construction completed

When the Orange Line was originally constructed in 1977, foundations for the bridges to carry the Silver Line over I-66 to the median of the Dulles Access Road were built up to ground level. These foundations included steel piles that were driven into the ground and capped with concrete. However, detailed records for these original foundations were lost. As a result, engineers asked for the foundations to be inspected by digging around them to determine the condition of each pile under the concrete foundation caps.[51]

Some of the foundations are located in confined spots adjacent to I-66 and the electrifiedthird rail of the Orange Line, making access difficult. Dulles Transit Partners offered to inspect seven foundations that were easily accessible, but the FTA insisted that all foundations be tested. Dulles Transit Partners and MWAA agreed to test all foundations before the bridge piers were built upon them. This required the portion of the Orange Line between the West Falls Church and East Falls Church Metro stations to be taken out of service on weekends while the tests were conducted.[51] All foundations were acceptable and the bridge construction proceeded using the existing foundations.[52]

Controversy

[edit]

There has been controversy over the contract between the MWAA and Dulles Transit Partners, which consists ofBechtel andWashington Group International. The $2.7 billion project was originally awarded by the Virginia Department of Rail and Public Transportation (DRPT) under the Virginia Public-Private Partnership Act, rather than by using conventional competitive bidding based upon a detailed specification. As a result, the contractor is allowed to both design and build the project with no upper cap on its cost. Problems could arise from the arrangement where MWAA is supervising the design and construction but ultimately WMATA must operate the Silver Line.[53] The contract provides for price escalation of $3 million to $6 million a month for delays.[54] VDRPT transferred the contract to MWAA when MWAA took over the project in June 2007.[55]

Opening of Phase 1

[edit]
Pennant given to users of the Silver Line on its grand opening, July 26, 2014.

The original schedule planned for revenue service to begin in 2013. The contractor reported to MWAA on February 7, 2014, that construction was complete. MWAA had fifteen days to review the documentation and decide whether it agreed, but on February 24 they announced that the contractor had failed to meet seven of twelve criteria outlined in the contract.[56][57]

On March 19, 2014, MWAA announced additional delays in the project due to public address speakers and a communications cable that did not meet code and did not offer a new completion date. They hoped to turn it over to WMATA by April 9, 2014.[58][59] WMATA requires an additional 90 days for testing and training.[60] The system then underwent 90 days of testing and staff training. This suggested, at the time, that the line could open as early as July 4, 2014.[61] On May 27, 2014, WMATA was handed over control of the line, with service to begin "within 90 days".[62] Finally, on June 24, 2014, it was revealed that the official opening date for the first five stations had been set for July 26.[58][63]

After a set of speeches and announcements prior to opening, which were televised on local cable television stationNews Channel 8, and attended by theGovernor of Virginia,Terry McAuliffe, Metro General Manager Richard Sarles, the entire Metroboard of directors, District of Columbia MayorVincent C. Gray, and other regional politicians, a ribbon cutting took place atWiehle–Reston East, and shortly after noon on July 26, 2014, the five new stations were opened for passenger service.[64][65][66] Service initially traveled between Wiehle–Reston East andLargo.[64]

Although the Silver Line attracted riders, its average weekday boarding was 17,100 during its first year of operations instead of the projected 25,000 riders.[67]

Effect on the Metro map

[edit]

Metro's iconic rail map, in distribution sinceLance Wyman and Bill Cannan (Wyman & Cannan) designed it in 1976, takes – according to some observers – a "pop art" approach to representing its subway network.[68] The Metro rail map uses thick strokes to mark its radial lines. To fit in the current space and make use of the iconography as currently proportioned, the map relies upon the fact that no more than two lines overlap at any single location.[69] The addition of the Silver Line creates a three-line overlap from Rosslyn to Stadium–Armory, a fact that led WMATA to publicly announce in 2010 that it was considering a new map design.[70] A number of unofficial attempts by graphic designers to redraw the Washington Metro map to include the Silver Line have done so by thinning the strokes throughout.[71]

In 2003, predating Booth's attempt, WMATA released a professionally designed graphic that displayed the Silver Line on an unofficial map that resembled the current version, but with thin lines. The interplay between Metro's unofficial proposal and those of other designers received attention in a number of press outlets.[68][71][72] A poster displaying a map of similar design has been hanging in DC CouncilmanJack Evans' office for a number of years, but received scant attention until 2008.[73] Wyman, one of the original designers of the map, was confirmed as the layout specialist who would be redesigning the map byThe Washington Post on June 4, 2011.[74]

A thick-line version of the map, released as part of Metro's Rush Plus plan, showed the Silver Line spurring off the Orange Line between theBallston andEast Falls Church stations in a northwesterly direction, with five unlabeled stops (the Phase 1 stations).[75] The final map released for the Silver Line's Phase 1 opening features the stations shared by the three lines as normal stations, with the dots signifying stations located on the colored line in the center and small white stubs extending from the center dots into the adjoining colored lines.[76]

Phase 2: Dulles extension

[edit]
Unofficial Washington Metro system map with the Dulles extension

While construction of Phase 1 to Wiehle–Reston East was under way, the funding and planning of Phase 2 through Dulles Airport continued. This included the adoption of a special taxing district by the Town of Herndon[77] and a public planning forum.[78] Early cost estimates for Phase 2 had been $2.75 billion; however, a group of consultants increased the estimate in 2010 from $3.44 billion to $4.1 billion.[79]

On April 6, 2011, the MWAA Board voted 9 to 4 to build an underground station located 550 feet (170 m) from the airport terminal rather than an above-ground station 1,150 feet (350 m) away from the terminal. The underground station would be more convenient to travelers, but would come at an additional cost of $330 million and would extend the construction time of the project, delaying the expected opening to mid-2017.[80] Republican former Virginia GovernorBob McDonnell opposed the decision to build a more expensive underground station and threatened to withhold support for the project. U.S. Secretary of TransportationRay LaHood offered to mediate the dispute.[81] On March 7, 2012, the projected $3.8 billion cost for Phase 2 was reduced to $2.7 billion with the elimination of the underground station at Dulles Airport and other cost savings.[82]

The extension of the Silver Line to Dulles and Loudoun County was in jeopardy until July 3, 2012, when theLoudoun County Board of Supervisors voted 5 to 4 to extend the line to Dulles Airport and into the county.[83] On April 25, 2013, the Phase 2 contract was issued at a cost of $1.177 billion.[84] On August 20, 2014, theUnited States Department of Transportation announced that Phase 2 would be funded with a $1.28 billion Transportation Infrastructure Financial Innovation Act (TIFIA) loan. This delivers part of an approximately $1.87 billion combined commitment of TIFIA loans for Phase 2, which represents the largest TIFIA assistance for a single project in the program's history.[85]

Cracks were discovered in some concrete supportgirders in July 2015, causing work to be temporarily halted.[86] By July 2016, 30% of the Phase 2 project had been completed. The contractors reported that significant progress was made with regard to the structure of the line.[87] By March 2017, completion of Phase 2 construction had reached 56% with work on therail yard at Dulles Airport reaching 46%, 76% of deck spans being poured, and all aerial guideway girders over the Dulles Access Road near Saarinen Circle being set in place. MWAA reported that crews would soon begin installation of pedestrian bridges at the five stations under construction in the median of the Dulles Access Road and the Dulles Greenway.[88]

By January 2018, it was reported that 76% of Phase 2 construction was completed.[89] However, a few months later it was discovered that multiple sections of cement walls of the new Metro stations were poorly designed, making them prone to water infiltration. Construction contractors took action to fix the problem and said it would not impact the extension's projected 2020 opening.[90] The contractor Capital Rail Constructors (CRC) and the supplier Universal Concrete pledged to fix the problem, and CRC also committed to spraying the concrete with a special sealant every 10 years as needed. Later, in May 2018, the federal district court inAlexandria, Virginia unsealed allegations by a former employee at Universal Concrete Corporation that precast concrete used in five of the six Phase 2 Silver Line stations had been produced from aggregate from a different quarry than the one specified in construction contracts.[91] Officials took four core samples from each of the five affected stations for microscopic testing to determine whether the panels complied with project requirements.[91] That July, the governments of Virginia and the United States sued Universal Concrete for providing false records and defective materials.[92] In September 2018, it was revealed that about 400 of the concrete rail ties on Phase 2 were defective, in that they caused the rails to bend outward. However, Metro and CRC were not able to agree on a solution before that December.[93]

Despite these controversies, progress of the extension's construction steadily approached completion throughout the rest of the year, reaching 78% in June,[91] 86% in September[94] and 92% by January 2019.[95] A month later, it was deemed that the extension would be ready for testing that would last for several months, starting with tworecently retired 5000 series railcars towed by a diesel to clean the third rail while it is disabled, before energizing it to allow for more dynamic train testing.[96] Despite reports of trouble that prevented early test trains from going so far,[97] testing eventually continued throughout the expansion and into Dulles Airport in March.[98] The following month, progress of construction reached 95%.[99]

In June 2019, an updated estimation of Phase 2's completion was made, stating that it could be ready for service at about the third quarter of 2020.[100] In August 2019, MWAA announced that Phase 2 would open around mid July 2020 but WMATA expressed some doubts.[101] Towards the end of the year, after considering the pace of the work being done and efforts to address outstanding issues, Metro officials then announced that the second phase may not be ready for service until about September 2020.[102] During a Metro board meeting in December 2019, officials floated the idea of fully replacing the defective concrete panels provided by the MWAA during construction, instead of just repairing them. Should these plans go through, Phase 2's launch date may be pushed back by another year from September 2020.[103]

By early February 2020, it was reported that construction was 98% complete.[104] However, by the end of March 2020, while determining a budget for the 2020–2021 fiscal year (and having taken theimpact of theCOVID-19 pandemic into consideration), Metro re-evaluated the timetable for the second phase's launch and anticipated it would be ready for service on April 1, 2021.[105]

From March 26, 2020, until June 28, 2020, trains were bypassingGreensboro,McLean,East Falls Church,Virginia Square–GMU,Clarendon,Federal Triangle,Smithsonian,Federal Center SW, andMorgan Boulevard stations due tothe local impact of the coronavirus pandemic in the Washington D.C. area.[106][107][108] All stations reopened on June 28, 2020.

On April 23, 2020, WMATA announced that Silver Line service would be suspended beginning on May 23, 2020, in order to rebuild stations west ofBallston–MU and to complete the second phase of the Silver Line. This was in part due to the historically low ridership numbers for the transit agency due to the ongoing COVID-19 pandemic, traffic free highways, and WMATA wanting to get around the clock maintenance done; it would be easier for work to be done without any riders or trains interfering with the workers. They offered local bus service from Wiehle, Greensboro, Spring Hill, Tysons, McLean, and East Falls Church to Ballston. Originally, WMATA planned on reducing Orange and Silver Line trains while continuously single tracking at East Falls Church instead of a full closure.[109][110] Later that summer, while the Silver Line was closed, work began on integrating Phase 2's computerized control systems with those of the rest of the Metrorail system, a crucial step towards its completion. Phase 2's train control systems were finally integrated with that of the Metrorail system by the end of August and three more days of closures took place in November and December for final dynamic testing.[111] On June 24, 2020, WMATA announced that Silver Line service would resume three weeks early when trains are able to bypassEast Falls Church.[112][113] All Silver Line service resumed on August 16, 2020, when Silver and Orange Line trains were able to bypass East Falls Church.[114] East Falls Church reopened on August 23, 2020.[115]

In September 2020, the Metro Office of Inspector General (OIG) reported that more cracks were discovered in five of the six new stations on the second phase and wants the concrete panels to be replaced before the WMATA Board accepts responsibility and opens the new extension. In light of ongoing issues, as well as budget cuts resulting from declining ridership caused by the COVID-19 pandemic, Metro pushed back the opening of the Phase 2 extension first to July 2021,[116][117] and on December 15, 2020, to Fall of 2021.[118]

On December 14, 2020, WMATA announced that Blue Line service would be suspended between February 13 to May 23, 2021, in order to rebuild the platforms at bothArlington Cemetery andAddison Road. Silver Line trains would run in place of the Blue Line every 12 minutes during the weekdays and 15 minutes on weekends while bypassing Addison Road.[119] In early 2021, construction completion of Phase 2 reached 99 percent.[120] As of March 2021, Phase 2 was projected to open to passenger service in early 2022.[121]

Ashburn on opening day, November 15, 2022

On November 4, 2021, MWAA declared the work on the rail line to be "substantially complete"; however, WMATA estimated that it could take five months of testing and other preparations before passenger service could begin.[122][123] The expansion took another major step towards completion and opening for service the following month with the completion of the rail yard,[124] followed by initial tests of the full Phase 2 route days later. WMATA took control of the expansion in mid-January and is conducting a final round of testing for several months before it can be opened for service.[125] After all the tie-in procedures were completed, WMATA took control of all remaining work to be done for Phase 2 and conducted a final round of testing before it could be ready for service. In January 2022, the opening was to be ready for service in May 2022 after four months of testing.[126] In early March 2022, Phase 2 was projected to open in July 2022.[127] However, on March 24, 2022, general managerPaul Wiedefeld announced that the projected opening would be delayed once again and declined to give an estimated date of completion.[128]

In June 2022, interim general manager Andy Off announced that WMATA was moving closer to announcing a completion date and expected to takeover the Phase 2 project in the next coming weeks.[129] On June 23, 2022, WMATA announced that it had taken over control of the Phase 2 project from theMetropolitan Washington Airports Authority.[130] Final testing of Phase 2 was scheduled to occur throughout early October via the actual running of empty trains throughout its course, and Metro expected all safety certification for this expansion to be completed around the same time before it finally opened for service.[131] On September 22, Metro's board of directors voted unanimously in a meeting to authorize current general managerRandy Clarke to determine the opening date for Phase 2.[132] Simulated service testing began operating along the Phase 2 tracks between October 3 and 17, 2022.[133][134][135]

Following these simulated runs, WMATA announced that the extension would likely open before Thanksgiving, with one final impediment towards opening of service being a shortage of available 7000-series trains that could service it after a derailment near the Rosslyn station a year prior put most of them out of service, with plans to restore them hampered by conflicts with theWashington Metrorail Safety Commission.[136][137]

The extension opened on November 15, 2022,[138][139] with an opening ceremony held atDulles International Airport.[140]

Later changes

[edit]

On June 3, 2023, service was temporarily suspended betweenMcLean andBallston-MU stations for track replacement and resumed on June 26, 2023.[141][142]

Automatic train operation on the Silver Line began in June 2025. ATO on the Washington Metro had ceased following the2009 Red Line train collision (at which time the Silver Line did not exist), but had gradually been re-introduced to the other lines during late 2024 and early 2025.[143][144] Half of Silver Line trains have been rerouted fromLargo (sharing tracks with the Blue Line) toNew Carrollton (sharing tracks with the Orange Line) starting on June 22, 2025.Short turns have been added during weekday peak hours, with trains operating betweenWiehle-Reston East and New Carrollton in the morning, andStadium–Armory and Wiehle-Reston East in the afternoon.[145]

Route

[edit]
Westbound Silver Line train departingSmithsonian in April 2019

The Silver Line has two primary goals. The first is to linkWashington, D.C. by rail toDulles International Airport and the Northern Virginiaedge cities ofTysons,Reston,Herndon, andAshburn. The second is to spur urban development in Tysons and reduce overall reliance on highway traffic in the business district, Virginia's largest and the 12th-largest in the country. The district's area is comparable in size to downtown Washington, D.C., but is rather insulated from its surrounding neighborhoods and its streets have no existing grid pattern.[146] The Silver Line also improves public access to theUdvar-Hazy Center, an annex ofNational Air and Space Museum located near Dulles Airport; after the opening of the first phase of the Silver Line,Fairfax Connector began running shuttles to the museum fromWiehle–Reston East.[147]

The pre-existing portions of the Silver Line opened as the Orange and Blue Lines on July 1, 1977, fromStadium–Armory toRosslyn, on December 11, 1979, from Rosslyn toBallston, November 22, 1980, from Stadium–Armory toAddison Road, June 7, 1986, from Ballston-MU throughEast Falls Church and December 18, 2004, from Addison Road toLargo. Unlike all prior segments of the Metrorail system, which were designed and constructed by theWashington Metropolitan Area Transit Authority (WMATA), the Silver Line was designed and constructed by theMetropolitan Washington Airports Authority (MWAA) and is operated by WMATA. The first phase of the project was funded 43% by $900 million of federal funding, 28% by a special tax district on commercial property proximate to the Silver Line route and 28% by a $0.50 toll increase on theDulles Toll Road (State Route 267, SR 267).[148] Funding for the second phase of the project is shared by Loudoun County, Fairfax County, the Commonwealth of Virginia and the MWAA.[148]

While the Silver Line's eastern terminus was originally planned atStadium–Armory, the plan was changed in 2012 for the line to instead originate at Largo because Stadium-Armory'spocket track is too short for trains to turn around.[149] Traveling westward through the District of Columbia, the Silver Line shares the Blue and Orange Line tracks. It continues through Arlington along the Orange Line and branches off immediately east of the Orange Line'sWest Falls Church station. The new tracks run in the median of theDulles Connector Road (SR 267) to an elevated bridge, which takes them overSR 123. Two elevated stops along the west side of Route 123 serve the national headquarters ofCapital One,SAIC and two enclosed Tysons Corner shopping malls. The tracks then enter a tunnel which emerges in the median ofSR 7. Two elevated stations above SR 7 serve the western section of Tysons. The elevated track then swings back into the median of the Dulles Access Road and Phase 1 terminated at Wiehle-Reston East.[150]

In Phase 2, the Silver Line continues west in the Dulles Access Road's median until the airport. Along the way, four additional stations were built with platforms in the median of the road and a faregate and pedestrian bridges to parking areas elevated above the highway. In anticipation of theHerndon station being built, Fairfax County constructed a 1,750-space parking garage with ramps to Dulles Access Road's toll lanes in 1999, and this facility was used for bus commuters on an interim basis during Phase 2 construction. The garage drew criticism because of alleged construction flaws.[151] Upon reaching the airport, the track rises up on a viaduct which follows the path of the arrivals driveway of the airport terminal to a station located away from the terminal that is accessible by a pedestrian tunnel. The track leaves the station near the airport hotel and economy parking lots and heads north parallel to the main runways. A storage yard and maintenance facility branches off to the west occupying the airport's buffer zone north of the end of its major runways. The final two stops are in the median of theDulles Greenway, serving theAshburn suburb.[150] Hence, the line is expected to draw both airport traffic and commuters from the far western suburbs of Washington. D.C.. Buses previously provided these users with limited public transportation. In contrast, the Silver Line will eventually provide trains once every six minutes during rush hours and once every fourteen minutes during non-rush hours.[152]

Rolling stock

[edit]

Metro's new7000-series cars were ordered at a price of $3 million per car,.[153] The Dulles Corridor Metrorail Project required 128 new cars: 64 for Phase 1, and another 64 for Phase 2. Additional cars were ordered to replace aging 1000-series cars and to accommodate ridership growth.[154] The contract was signed on July 2, 2010, for 428 cars.[155]

Panoramic view of Silver Line Phase 1 project under construction in July 2012 between the Tysons Corner (nowTysons) station onSR 123 at Tysons Boulevard and the overpass on theCapital Beltway (I-495).

Stations

[edit]

Stations are listed by their approved names.[156][157][158][159]

StationCodeOpenedOther Metro
Line(s)
Notes
AshburnN12November 15, 2022Western terminus
Planning names:Route 772, Ryan Road
Loudoun GatewayN11Planning names:Route 606, Morgan Road
Dulles International AirportN10
Innovation CenterN09Planning names:Route 28, Herndon – Dulles East
HerndonN08Planning names:Herndon–Monroe, Herndon – Reston West
Reston Town CenterN07Planning name:Reston Parkway
Wiehle–Reston EastN06July 26, 2014Previous western terminus
Planning name:Wiehle Avenue
Spring HillN04Planning names:Tysons West, Spring Hill Road
GreensboroN03Planning names:Tysons Central 7, Pike Seven
TysonsN02Originally opened asTysons Corner. Changed in 2022
McLeanN01Planning names:Tysons East, Tysons McLean, West Park
East Falls ChurchK05June 7, 1986Transfer station for theOrange Line (Western)
Ballston-MUK04December 11, 1979
Virginia Square–GMUK03
ClarendonK02
Court HouseK01
RosslynC05July 1, 1977Transfer station for theBlue Line
Foggy Bottom–GWUC04
Farragut WestC03Walking transfer toRed Line atFarragut North (branded as "Farragut Crossing")
McPherson SquareC02
Metro CenterC01March 29, 1976Transfer station for theRed Line
Federal TriangleD01July 1, 1977
SmithsonianD02
L'Enfant PlazaD03Virginia Railway Express at L'Enfant
Transfer station for theGreen andYellow Lines
Federal Center SWD04
Capitol SouthD05
Eastern MarketD06
Potomac AvenueD07
Stadium–ArmoryD08Transfer station for theOrange andBlue Lines (Eastern)
Minnesota AvenueD09November 20, 1978
DeanwoodD10
CheverlyD11
LandoverD12
New CarrolltonD13AmtrakAmtrakNortheast Regional,Palmetto,Vermonter
MARCPenn Line
 MTAPurple Line (planned)
Eastern terminus for half of Silver Line Trains
Benning RoadG01November 22, 1980
Capitol HeightsG02
Addison RoadG03
Morgan BoulevardG04December 18, 2004
LargoG05Eastern terminus for half of Silver Line Trains

Future

[edit]

AWolf Trap station was considered as part of Phase 1 betweenSpring Hill andWiehle-Reston East, but that station was excluded from the project due to cost effectiveness concerns.[160]

A study published in 2013 overseeing a long-term plan for the system subsequent to the Phase 2 extension plans to Ashburn included a possible three-station extension of the Silver Line northwest toLeesburg, which is the seat ofLoudoun County.[161] The stations from northwest to southeast areVA 7 Bypass,Crosstrail Blvd andBelmont Ridge. The same study included either adding aninfill station between Tysons Corner (nowTysons) andMcLean, or renaming the former, to allow transfer with aloop line that would parallel theCapital Beltway, named the "Beltway Line". This station would be namedBeltway and 123.

In December 2019, WMATA began to study changes to the Orange, Blue, and Silver lines to relieve congestion atRosslyn. Each proposed option would involve the construction of a new Rosslyn II station that would be connected to the existing Rosslyn station, allowing one of the three lines to be separated from the other two lines, increasing capacity of the station. Two of the options proposed would involve that line being the Silver Line. In one option, from west to east, the Silver Line would run express from West Falls Church to the Rosslyn II station, with a single intermediate stop at a new Ballston II station. Then, the Silver Line would run along new tracks to a new station at Georgetown, followed by several new stations underM Street NW to Union Station. The Silver Line would then travel north-east to new stations in Ivy City, Port Towns, Hyattsville, and finally to new College Park II and Greenbelt II stations. In the second option, from west to east, the Silver Line would remain unchanged in Virginia until reaching the Rosslyn II station, after which point it would travel along new tracks to Georgetown, followed by several new stations under M Street NW to Union Station. Then, the Silver Line would travel north-east through Ivy City, Port Towns, Landover Hills, and finally intersect the Orange Line at New Carrollton.[162][163]

See also

[edit]

References

[edit]
  1. ^"About". Silver Line Metro.Archived from the original on January 18, 2015. RetrievedApril 21, 2015.
  2. ^Holeywell, Ryan; Lippman, Daniel (April 2012)."The 5 Biggest U.S. Infrastructure Projects, Plus 5 at Risk".Governing.Archived from the original on April 12, 2012. RetrievedApril 15, 2012.;
  3. ^Neibauer, Michael (March 9, 2012)."30 Years: Construction Begins on Dulles Metrorail Extension".Washington Business Journal. RetrievedApril 15, 2012.;"Dulles Metro Overview".Metropolitan Washington Airports Authority.Archived from the original on February 16, 2025. RetrievedFebruary 10, 2025.
  4. ^"Timetables | WMATA".WMATA.Archived from the original on January 24, 2018. RetrievedOctober 6, 2024.
  5. ^"Dulles Metrorail History".Virginia Department of Rail and Public Transportation. Archived fromthe original on May 13, 2006. RetrievedAugust 12, 2006.
  6. ^Lynton, Stephen (July 17, 1983). "Metro's Behind Schedule, but Expansion is in View".The Washington Post. p. B1.
  7. ^"Metro to Have Eight Major Routes in District, Suburbs: Plan Is Result of Ten Years of Study, Discussions, Revisions by Areas".The Washington Post. March 2, 1968. p. B7.ProQuest 143458136.
  8. ^Eisen, Jack (June 10, 1969). "Metro Link To Dulles Is Spong's Aim".The Washington Post. p. A9.ProQuest 143579965.
  9. ^Eisen, Jack (December 19, 1969). "Senate Votes Study On Fast Rail Link To Dulles Airport".The Washington Post. p. B5.ProQuest 143676469.
  10. ^"WMATA, BART study airport lines".Railway Age. Vol. 169, no. 3. August 10, 1970. p. 14.ProQuest 877728947.
  11. ^"D.C.-Dulles Metro Use Is Estimated".The Washington Post. September 12, 1971. p. A15.ProQuest 147983506.
  12. ^Burgess, John (February 8, 1984)."New Study Of Dulles Rail Link Urged".The Washington Post.Archived from the original on August 28, 2017. RetrievedOctober 20, 2025.
  13. ^"Metro Dulles Link Gets $500,000 Grant".The Washington Post. October 4, 1994. RetrievedOctober 20, 2025.
  14. ^Chapter 560 of the 1995 Acts of the Assembly. Commonwealth of Virginia.
  15. ^Fehr, Stephen C. (November 19, 1995)."More Stops Make More Sense To Dulles Rail Line Panel; Tysons Corner, Loudoun Seen as Missing Links".The Washington Post. RetrievedOctober 20, 2025.
  16. ^Middleton, William D. (November 1999). "Smart growth and rail transit".Railway Age. Vol. 200, no. 11. pp. G1 –G4.ProQuest 203735886.
  17. ^Pae, Peter (December 14, 1995)."Loudoun Seeks Rail Yard Site to Lure Metrorail".The Washington Post. RetrievedOctober 20, 2025.
  18. ^abcde"Project Timeline". MWAA. Archived fromthe original on April 21, 2015. RetrievedDecember 17, 2013.
  19. ^Finucan, Karen (April 1999). "Tysons Corner may edge its way into a center".Planning. Vol. 65, no. 4. p. 27.ProQuest 206716423.
  20. ^Layton, Lyndsey; Shear, Michael D. (August 1, 2003). "Metrorail Plan May Be Tough Sell for Va.: Officials See Possible Difficulties in Gaining U.S. Funds for Extension to Reston Area".The Washington Post. p. B1.ProQuest 409611748.
  21. ^Shear, Michael D.; Ginsberg, Steven (March 27, 2006)."Toll Road To Fund Rail Line To Dulles".The Washington Post. p. A01.
  22. ^"Recommendation Paper to the Dulles Corridor and Finance Committees"(PDF). October 2009. p. 5.Archived(PDF) from the original on December 16, 2010. RetrievedDecember 19, 2009.
  23. ^"Airports Authority Board Approves Toll Rate Increases on Dulles Toll Road"(PDF). November 4, 2009.Archived(PDF) from the original on December 16, 2010. RetrievedNovember 30, 2010.
  24. ^ab"Exhibit 3 to MWAA Toll Rate Increase Hearing"(PDF).Archived(PDF) from the original on December 16, 2010. RetrievedDecember 19, 2009.
  25. ^abFreeman, Sholnn (November 5, 2009)."Airport board raises rates for Dulles Toll Road: Commuters' objections fail to derail plan to help finance Metro extension".The Washington Post.Archived from the original on November 9, 2012. RetrievedDecember 19, 2009.
  26. ^Federal Transit Administration, Virginia Department of Rail and Public Transportation, and Washington Metropolitan Area Transit Authority, Dulles Corridor Rapid Transit Project: Addendum to Final Alternatives Analysis Report (November 2004), 13.
  27. ^Thorp, Gene (April 26, 2006)."Rail Tunnel Graphic".The Washington Post.Archived from the original on October 20, 2012. RetrievedNovember 30, 2010.
  28. ^Lisa Rein, “Metro Considers Tysons Options,” Washington Post, January 19, 2006,https://www.washingtonpost.com/archive/local/2006/01/19/metro-considers-tysons-options-span-classbankheadtunneling-might-be-more-affordablespan/bd764d17-17b4-44de-a7ec-e959de375776/Archived August 27, 2017, at theWayback Machine
  29. ^MacGillis, Alec (March 24, 2006)."Cost Dooms Metro Plan For Tunnel At Tysons".The Washington Post. p. A01.Archived from the original on October 11, 2008. RetrievedMay 23, 2010.
  30. ^MacGillis, Alec (April 26, 2006)."Tunnel Back On Table for Dulles Rail".The Washington Post. p. A01.Archived from the original on November 4, 2012. RetrievedNovember 30, 2010.
  31. ^MacGillis, Alec (May 16, 2006)."Tunnel Decision Delayed 2 Months".The Washington Post. p. B01.Archived from the original on October 20, 2012. RetrievedMay 23, 2010.
  32. ^MacGillis, Alec (July 27, 2006)."Wolf, Davis Say Tunnel May Delay Dulles Rail".The Washington Post. p. A01.Archived from the original on December 1, 2010. RetrievedMay 23, 2010.
  33. ^"Panel Says Tunnel is Feasible for Tysons Corner" (Press release).American Society of Civil Engineers. July 31, 2006. Archived fromthe original on October 29, 2007. RetrievedNovember 30, 2010.
  34. ^MacGillis, Alec (September 7, 2006)."No Tunnel For Tysons, Kaine Says".The Washington Post. p. A01.Archived from the original on October 24, 2012. RetrievedNovember 30, 2010.
  35. ^"TysonsTunnel". TysonsTunnel. December 1, 2006. Archived fromthe original on June 18, 2010. RetrievedNovember 30, 2010.
  36. ^Carter & Burgess, Inc. (January 22, 2007)."Review of Large Bore Tunnel Engineering and Environmental Studies from Tysons Tunnel, Inc"(PDF). p. 41. Archived fromthe original(PDF) on February 6, 2012. RetrievedNovember 30, 2010.
  37. ^Tucker, Matthew O. (March 7, 2007)."Cover letter to consultant report, transmitted to Virginia Secretary of State"(PDF).Department of Rail and Public Transportation,Commonwealth of Virginia. Archived fromthe original(PDF) on July 31, 2007. RetrievedMarch 19, 2007.
  38. ^Tayloe, Monty (November 27, 2007)."Tysons Tunnel sues FTA".Fairfax Times. Archived fromthe original on February 19, 2008. RetrievedJanuary 6, 2008.
  39. ^"Letter from Tatyana Schum  – formerly with TysonsTunnel". dcurbanmon.com.Archived from the original on July 24, 2012. RetrievedNovember 28, 2010.
  40. ^"Letter to Virginia Governor Tim Kaine"(PDF).Federal Transit Administration. January 24, 2008. Archived fromthe original(PDF) on June 27, 2008. RetrievedNovember 30, 2010.
  41. ^"FTA Says Dulles Metrorail Project Full of Uncertainties".WRC-TV NBC 4, Washington, D.C. January 24, 2008. Archived fromthe original on June 1, 2008. RetrievedNovember 30, 2010.
  42. ^"FTA Grants Extension". WTOP News. January 29, 2008. Archived fromthe original on April 1, 2011. RetrievedJanuary 29, 2008.
  43. ^Gardner, Amy (April 30, 2008)."Dulles Rail Set to Get Federal Approval".The Washington Post. RetrievedApril 30, 2008.
  44. ^Gardner, Amy (December 4, 2008)."Silver Line To Dulles Wins Crucial Federal Okay".The Washington Post. p. A01.Archived from the original on July 29, 2009. RetrievedDecember 7, 2008.
  45. ^Gardner, Amy (March 10, 2009)."Officials Formalize Funding for Dulles Metro Extension".The Washington Post. Archived fromthe original on March 22, 2016. RetrievedMarch 10, 2009.
  46. ^Kravitz, Derek (November 9, 2010). "Metro stop's location could mar view of Dulles".The Washington Post. p. B5.
  47. ^"Dulles Corridor Metrorail Project Newsletter". November 2012. Archived fromthe original on January 10, 2016. RetrievedMarch 11, 2016.
  48. ^"FHWA - Center for Innovative Finance Support - Project Profiles".Federal Highway Administration (FHWA). RetrievedApril 14, 2022.
  49. ^Flook, William C. (March 23, 2009)."Commuters, employers prep for Tysons traffic nightmares". WTOP.Archived from the original on June 11, 2011. RetrievedMarch 24, 2009.
  50. ^Kravitz, Derek (April 23, 2009)."Dulles Rail's Completion Date Delayed".Washington Post.
  51. ^abRein, Lisa (December 4, 2009)."Extensive testing in new safety plan for Metro bridge".The Washington Post. p. B4.Archived from the original on June 29, 2011. RetrievedDecember 19, 2009.
  52. ^Rein, Lisa (July 2, 2010)."Aging pier footings pass safety tests for Dulles Metrorail Project".The Washington Post. p. B4. RetrievedNovember 30, 2010.
  53. ^Assistant Inspector General of Surface and Maritime Programs, Department of Transportation (July 27, 2007)."Baseline Report on the Major Project Monitoring of the Dulles Corridor Metrorail Project". Archived fromthe original on July 2, 2009. RetrievedNovember 30, 2010.
  54. ^Kravitz, Derek (August 5, 2007)."Costs to Rise for Metrorail to Dulles".The Washington Post. p. C4. RetrievedApril 14, 2012.
  55. ^Department of Rail and Public Transportation and Metropolitan Washington Airports Authority, Assignment and Assumption Agreement, June 28, 2007, box 176, folder Transfer Documents, Frank Wolf papers, C0279, Special Collections Research Center, George Mason University Libraries
  56. ^Aratani, Lori (February 7, 2014)."Contractor says Silver Line is complete; MWAA now has 15 days to decide".The Washington Post. photograph by Matt McClain. RetrievedFebruary 8, 2014.
  57. ^Aratani, Lori (February 24, 2014)."Metro Silver Line faces another delay".The Washington Post.Archived from the original on March 24, 2014. RetrievedMarch 23, 2014.
  58. ^abAratani, Lori (March 19, 2014)."Problems with speakers, cable add to Silver Line delays".The Washington Post. RetrievedMarch 24, 2014.
  59. ^Schumitz, Kali (March 19, 2014)."The scramble to complete the Silver Line: MWAA officials still not prepared to share timeline for completion".Fairfax Times. Archived fromthe original on March 22, 2014. RetrievedMarch 22, 2014.
  60. ^Cushman & Wakefield."Silver Line".Washington Business Journal.Archived from the original on October 27, 2014. RetrievedMarch 26, 2014.Construction of the five Metro stations was recently completed and developers are working on software testing. The system will go under 90 days of testing and staff training.
  61. ^Smith, Max; Ash, Ari (April 4, 2014)."Silver Line on track to open by July 4".WTOP.Archived from the original on April 7, 2014. RetrievedApril 5, 2014.
  62. ^"Metro takes control, Silver Line could open in 90 days".ABC 7. May 27, 2014. Archived fromthe original on May 27, 2014. RetrievedMay 28, 2014.
  63. ^"Silver Line Service". Silver Line Metro.Archived from the original on July 31, 2014. RetrievedJune 28, 2014.
  64. ^ab"All aboard! Metro's new Silver Line rolls down the tracks for the first time".Washington Post.Archived from the original on June 8, 2019. RetrievedMay 28, 2018.
  65. ^"After fanfare, long-awaited Silver Line debuts shortly after noon".WJLA. Associated Press. July 26, 2014. Archived fromthe original on July 29, 2014. RetrievedJuly 26, 2014.
  66. ^"The Silver Line Opens".DCist. July 26, 2014.Archived from the original on July 29, 2014. RetrievedJuly 26, 2014.
  67. ^Lazo, Luz (July 27, 2015)."Year-old Silver Line is celebrated as a catalyst for change in Tysons Corner".The Washington Post.Archived from the original on August 14, 2015. RetrievedJuly 28, 2015.
  68. ^abDePillis, Lydia (October 21, 2010)."Metrobusted: D.C.'s subway system needs a new map. Is anything worth saving?". Washington City Paper. Archived fromthe original on October 28, 2010. RetrievedNovember 26, 2010.
  69. ^Alpert, David (October 7, 2008)."Brown Line: We don't need a new color". Greater Greater Washington. RetrievedFebruary 2, 2011.As several commenters mentioned, the thick lines take up a lot of room and, with the Silver Line [and Brown Line], we'd have six lines going through L'Enfant. Metro can alleviate this by thinning out the colors, but that's still a lot.
  70. ^Tuss, Adam (October 5, 2010)."Metro prepping map for makeover".WTOP-FM. RetrievedNovember 28, 2010.
  71. ^abMalouff, Dan (February 19, 2010)."The Booth Map: Redesigning WMATA's map". Greater Greater Washington. RetrievedNovember 26, 2010.[dead link]
  72. ^Hammond, J.D. (October 26, 2010). "Fixing WMATA's Metrorail Map". The Washington Examiner.
  73. ^Alpert, David (September 5, 2008)."2003 WMATA expansion map". Greater Greater Washington. Archived fromthe original on February 8, 2011. RetrievedNovember 26, 2010.
  74. ^Hedgpeth, Dana (June 4, 2011)."After more than 30 years, Metro map is being redesigned by creator, Lance Wyman".The Washington Post.Archived from the original on December 9, 2017. RetrievedJune 4, 2011.
  75. ^"Rush+".WMATA. Archived fromthe original on April 30, 2012. RetrievedApril 29, 2012.
  76. ^"System Map"(PDF). Silver Line Metro. Archived fromthe original(PDF) on October 17, 2016. RetrievedOctober 22, 2014.
  77. ^Kravitz, Derek (December 22, 2009)."Self-tax allowed for N.Va. businesses to fund Metro stations".The Washington Post. RetrievedNovember 9, 2010.
  78. ^Hosh, Kafia A. (July 19, 2010)."Development near Herndon's future Metro station topic of public forum Monday".The Washington Post.Archived from the original on November 11, 2012. RetrievedNovember 9, 2010.
  79. ^Kravitz, Derek (September 16, 2010). "Silver Line costs soars for 2nd phase". p. B1.
  80. ^Hosh, Kafia (April 7, 2011)."Dulles to get underground Metro station".The Washington Post. p. B1.Archived from the original on September 19, 2015. RetrievedApril 14, 2012.
  81. ^Fabel, Leah (May 10, 2011). "LaHood offers to mediate Dulles Rail funding fight". The Washington Examiner. p. 5.
  82. ^"Projected cost of Dulles rail project decreases". Railway Track and Structures. March 7, 2012. Archived fromthe original on April 27, 2016. RetrievedApril 10, 2016.
  83. ^Jacobson Moore, Erika (July 3, 2012)."Loudoun's In: Split Board Backs Silver Line Extension". Leesburg Today Media Services. Archived fromthe original on July 8, 2012. RetrievedJuly 9, 2012.
  84. ^"Airports Authority Intends to Award Phase 2 Construction Contract to Capital Rail Constructors" (Press release). April 25, 2013.Archived from the original on March 11, 2016. RetrievedMarch 22, 2014.
  85. ^"U.S. Transportation Secretary Foxx Announces $1.28 Billion Loan for Phase Two Silver Line to Dulles" (Press release).Washington. August 20, 2014.Archived from the original on January 14, 2016. RetrievedOctober 23, 2014.
  86. ^Aratani, Lori (August 27, 2015)."Crews resume some girder work on Silver Line, phase 2".The Washington Post.Archived from the original on September 5, 2015. RetrievedSeptember 13, 2015.
  87. ^"Phase 2 Construction Reaches 30 Percent Completion".dullesmetro.com. Dulles Corridor Metrorail Project. July 2016.Archived from the original on August 7, 2016. RetrievedAugust 2, 2016.
  88. ^"Construction Passes 56 Percent During Very Mild Winter".dullesmetro.com. Dulles Corridor Metrorail Project. March 2017. RetrievedApril 16, 2017.
  89. ^Waseem, Fatimah (January 18, 2018)."Silver Line Phase 2 Construction is Nearly 76 Percent Complete".Reston Now. RetrievedMay 2, 2018.
  90. ^Artani, Lori (April 25, 2018)."Silver Line officials rush to replace defective panels at five Phase 2 stations".The Washington Post.Archived from the original on April 28, 2018. RetrievedMay 2, 2018.
  91. ^abc"Phase 2 Rail Construction Hits 78 Percent".dullesmetro.com. Dulles Corridor Metrorail Project. June 2018.Archived from the original on July 3, 2018. RetrievedJuly 2, 2018.
  92. ^"Virginia, U.S. sue company behind defective Metro Silver Line concrete".Washington Post. July 10, 2018. RetrievedFebruary 19, 2019.
  93. ^"New problems for the Silver Line Phase 2: Officials say rail ties are flawed".Washington Post. December 12, 2018.Archived from the original on February 20, 2019. RetrievedFebruary 19, 2019.
  94. ^"Dulles Metro Update". MWAA.Archived from the original on September 21, 2018. RetrievedSeptember 21, 2018.
  95. ^"Dulles Metro Update". MWAA.Archived from the original on January 26, 2019. RetrievedJanuary 25, 2019.
  96. ^Wanek-Libman, Mischa (February 6, 2019)."Test trains begin on Silver Line Phase 2 to Dulles".Mass Transit magazine.Archived from the original on February 9, 2019. RetrievedFebruary 9, 2019.
  97. ^Tuss, Adam; Paz, Christian (February 6, 2019)."First Silver Line Test Train Only Made It 1,000 Feet Out of Station".NBC4 Washington. RetrievedMarch 25, 2019.
  98. ^Taylor, Dan (March 21, 2019)."Metro Test Trains Spotted Near Reston, Herndon".Patch.com.Archived from the original on March 25, 2019. RetrievedMarch 25, 2019.
  99. ^Parsons, Jim (April 24, 2019)."Concrete Quality Is Latest Setback for Virginia Rail Line".Engineering News Record.Archived from the original on May 5, 2019. RetrievedMay 5, 2019.
  100. ^Smith, Max (June 13, 2019)."Construction on Silver Line extension hits a new snag".WTOP.Archived from the original on June 21, 2019. RetrievedJune 21, 2019.
  101. ^Smith, Max (August 6, 2019)."First potential opening date set for Silver Line into Loudoun County".WTOP.Archived from the original on April 5, 2020. RetrievedAugust 5, 2019.
  102. ^Pascale, Jordan (November 25, 2019)."The Silver Line's Second Phase Is Looking At A Potential September Opening Date".DCist.Archived from the original on December 11, 2019. RetrievedDecember 11, 2019.
  103. ^"Silver Line Extension Could Maybe, Possibly Open in September?".Archived from the original on December 12, 2019. RetrievedDecember 12, 2019.
  104. ^Smith, Max (February 6, 2020)."Silver Line to Dulles looks done, but may not open until 2021".WTOP.Archived from the original on April 11, 2020. RetrievedApril 2, 2020.
  105. ^Smith, Max (March 30, 2020)."Metro sets fare hikes, bus cuts in budget — with coronavirus caveat".WTOP.Archived from the original on April 2, 2020. RetrievedApril 2, 2020.
  106. ^"Special Covid-19 System Map"(PDF).Washington Metropolitan Area Transit Authority. Archived fromthe original(PDF) on March 27, 2020. RetrievedApril 14, 2020.
  107. ^"Metrorail stations closed due to COVID-19 pandemic".Washington Metropolitan Area Transit Authority. March 23, 2020.Archived from the original on August 25, 2021. RetrievedApril 14, 2020.
  108. ^"Metro to reopen 15 stations, reallocate bus service to address crowding, starting Sunday". WMATA.Archived from the original on December 17, 2021. RetrievedJune 22, 2020.
  109. ^"Metro to use upcoming low-ridership summer to maximum effect, expands Orange, Silver line shutdown".www.wmata.com.Archived from the original on May 22, 2020. RetrievedApril 23, 2020.
  110. ^George, Justin (April 23, 2020)."Metro extends summer shutdown to include the Silver Line to take advantage of pandemic slowdown".The Washington Post.Archived from the original on June 4, 2020. RetrievedMay 25, 2020."The change to the shutdown schedule, which begins Memorial Day and lasts through LaborDay, means there will be no Silver Line service."
  111. ^Taylor, Madeline (August 24, 2020)."Silver Line Extension Clears Major Hurdle".RestonNow.Archived from the original on August 29, 2020. RetrievedAugust 28, 2020.
  112. ^"Silver Line service will return August 16, along with reopening of six stations in Fairfax County".www.wmata.com. WMATA.Archived from the original on July 12, 2020. RetrievedJuly 11, 2020.
  113. ^Pascale, Jordan."Metro To Reopen Silver Line Stations In August".DCist.Archived from the original on July 13, 2020. RetrievedJuly 11, 2020.
  114. ^"Metro to add more buses, trains and extended hours as part of Covid-19 Recovery Plan beginning Sunday, August 16".www.wmata.com. WMATA.Archived from the original on August 13, 2020. RetrievedAugust 16, 2020.
  115. ^"Metro announces reopening of East Falls Church and Arlington Cemetery stations on Aug. 23".WJLA. August 17, 2020.Archived from the original on August 25, 2021. RetrievedSeptember 8, 2020.
  116. ^"More cracks were found at Silver Line stations. Here's what needs to happen before Metro opens Phase 2".Greater Greater Washington. September 11, 2020.Archived from the original on March 8, 2021. RetrievedSeptember 18, 2020.
  117. ^"Metro forced to make budget cuts, Silver Line expansion delayed".LocalDVM. September 21, 2020. Archived fromthe original on February 6, 2021. RetrievedSeptember 29, 2020.
  118. ^"Silver Line Phase II Pushed to At Least Fall 2021".Reston Now. December 15, 2020.Archived from the original on February 10, 2021. RetrievedFebruary 10, 2021.
  119. ^"Metro announces travel alternatives during spring platform reconstruction work".www.wmata.com. WMATA.Archived from the original on August 25, 2021. RetrievedDecember 15, 2020.
  120. ^Fields, Scott (January 26, 2021)."Silver Line Phase II On Track for Fall Opening Despite Metro Financial Concerns".Reston Now.Archived from the original on February 27, 2021. RetrievedFebruary 23, 2021.
  121. ^Aratani, Lori (March 5, 2021)."Silver Line's second phase should reach 'substantial completion' by Labor Day, project director says".Washington Post.Archived from the original on March 7, 2021. RetrievedMarch 5, 2021.
  122. ^<Silver Line extension to Dulles inches closer to completion after years of delay,The Washington Post, November 4, 2021
  123. ^Tom Roussey (November 5, 2021)."Long-awaited extension of Metro's Silver Line could open early next spring or summer".wjla.com. ABC 7 News.Archived from the original on March 25, 2025. RetrievedMarch 6, 2025.
  124. ^Artani, Lori (December 1, 2021)."Silver Line extension takes a large step forward with completion of rail yard at Dulles Airport".The Washington Post.Archived from the original on December 2, 2021. RetrievedDecember 6, 2021.
  125. ^Potter, Bruce (December 14, 2021)."Trains running on Silver Line extension as testing begins; opening date not set yet".Inside NoVa.Archived from the original on December 19, 2021. RetrievedDecember 19, 2021.
  126. ^Waseem, Fatimah (June 22, 2020)."Silver Line Extension Takes Big Step Toward Completion".RestonNow.Archived from the original on June 23, 2020. RetrievedJuly 2, 2020.
  127. ^"Silver Line extension opening date pushed once again to summer 2022".FFXnow. March 2, 2022.Archived from the original on March 2, 2022. RetrievedMarch 3, 2022.
  128. ^"'Extreme disappointment' — Metro revises plan to bring back 7000 Series cars; Silver Line delayed".WTOP News. March 24, 2022.Archived from the original on March 26, 2022. RetrievedMarch 27, 2022.
  129. ^"Metro's Silver Line extension moves closer to finish line".Washington Post.Archived from the original on July 7, 2022. RetrievedJune 16, 2022.
  130. ^"Silver Line Extension transferred to Metro's control".wmata.com. WMATA.Archived from the original on June 23, 2022. RetrievedJune 23, 2022.
  131. ^Murillo, Mike (September 20, 2022)."Metro trains to start test runs on new phase of Silver Line".WTOP.Archived from the original on September 23, 2022. RetrievedSeptember 23, 2022.
  132. ^Waseem, Fatimah (September 22, 2022)."Metro board takes key step to setting opening date of Silver Line Phase II".FFXNow.Archived from the original on September 27, 2022. RetrievedSeptember 27, 2022.
  133. ^"Simulated service for Silver Line Phase Two to begin next month but opening date uncertain".FFXnow. September 8, 2022.Archived from the original on October 6, 2022. RetrievedOctober 7, 2022.
  134. ^"Your new Silver Line stations coming soon with a new Metrorail map".www.wmata.com. WMATA.Archived from the original on October 7, 2022. RetrievedOctober 7, 2022.
  135. ^"Next Phase of Silver Line to Open Soon".NBC4 Washington.Archived from the original on October 7, 2022. RetrievedOctober 7, 2022.
  136. ^Waseem, Fatimah (October 19, 2022)."BREAKING: Silver Line Phase II could start 'in time' for Thanksgiving, but more trains needed, Metro says".FFXNow. RetrievedOctober 20, 2022.
  137. ^"Metro approved for more trains, plans to open Silver Line by Thanksgiving".Washington Post.Archived from the original on October 26, 2022. RetrievedOctober 26, 2022.
  138. ^George, Justin; Laris, Michael; Aratani, Lori (November 15, 2022)."Silver Line extension opens, adding six stations, Dulles connection after years of delays".The Washington Post. RetrievedOctober 28, 2025.
  139. ^Massimo, Rick (November 15, 2022)."FAQ: Metro's Silver Line extension opens".WTOP News. RetrievedOctober 28, 2025.
  140. ^"Metro launches Silver Line Extension with opening ceremony; welcomes customers to #RideSilver to six new stations" (Press release). Washington Metropolitan Area Transit Authority. November 15, 2022.Archived from the original on May 19, 2024. RetrievedDecember 14, 2022.
  141. ^"Metro Closes 4 Orange, Silver Line Stations in Virginia for Weeks, Impacting Travel to Dulles Airport". June 2023.
  142. ^"Metro to reopen two Orange and Silver line stations, second phase of Orange Line work continues through July 16".WMATA.Archived from the original on July 25, 2023. RetrievedJuly 25, 2023.
  143. ^"Metro's Blue, Orange and Silver lines start running on automatic train operation".NBC4 Washington. June 15, 2025.Archived from the original on June 16, 2025. RetrievedJune 16, 2025.
  144. ^Leon, Jeffery (June 13, 2025)."Metro expanding full train automation to all lines for the first time in 16 years".WTOP News. RetrievedJune 16, 2025.
  145. ^"Metro Board of Directors approves $4.957 billion FY2026 budget that improves service without raising fares" (Press release). Washington Metropolitan Area Transit Authority. April 10, 2025.Archived from the original on April 11, 2025. RetrievedApril 10, 2025.
  146. ^"Silver Line Activation Plan"(PDF).WMATA. Archived fromthe original(PDF) on February 9, 2014. RetrievedJune 28, 2014.
  147. ^Thomson, Robert (June 19, 2014)."New bus to the air and space museum in Virginia".The Washington Post.Archived from the original on January 26, 2018. RetrievedJanuary 25, 2018.
  148. ^ab"Frequently Asked Questions".Virginia Department of Rail and Public Transportation.Archived from the original on April 7, 2015. RetrievedJanuary 14, 2008.
  149. ^Kahn, Nikki (December 5, 2012)."Metro details Silver Line service changes".The Washington Post.Archived from the original on July 8, 2018. RetrievedSeptember 11, 2017.
  150. ^ab"Full Route Map". MWAA. Archived fromthe original(PDF) on May 7, 2015. RetrievedNovember 30, 2010.
  151. ^Turque, Bill (January 27, 2008)."Authorities Cringe as Va. Garage Crumbles".The Washington Post.Archived from the original on October 12, 2008. RetrievedDecember 19, 2009.
  152. ^"Metro Core Capacity Study"(PDF). WMATA. Archived fromthe original(PDF) on December 3, 2010. RetrievedNovember 30, 2010.
  153. ^Tuss, Adam (March 22, 2010)."Metro's oldest rail cars will be rolling out of service".WTOP-FM.Archived from the original on October 15, 2011. RetrievedNovember 30, 2010.
  154. ^WMATA Board Action/Information Summary, "7K Series Railcar Procurement," December 18, 2008 | url=https://wmata.com/about/board/meetings/board-pdfs/upload/121808_FAOAInitiateAdvertisementof7000Series.pdfArchived August 12, 2025, at theWayback Machine
  155. ^Rein, Lisa; Kumar, Anita (July 2, 2010)."Metro's directors back $300 million accord with Va".The Washington Post. p. B4.Archived from the original on December 1, 2010. RetrievedApril 14, 2012.
  156. ^"Board of Supervisors Approves Proposed Silver Line Station Names". April 10, 2012. Archived fromthe original on May 15, 2012. RetrievedApril 11, 2012.
  157. ^Hosh, Kafia (March 29, 2011)."Fairfax OKs names for new Metrorail stations".The Washington Post.Archived from the original on November 12, 2012. RetrievedMarch 29, 2011.
  158. ^Hosh, Kafia (March 30, 2011). "Fairfax names new Metro stations".The Washington Post. p. B5.
  159. ^Neibauer, Michael (April 27, 2015)."Loudoun Silver Line station names finalized with Metro board approval".Washington Business Journal.Archived from the original on April 30, 2015. RetrievedApril 28, 2015.
  160. ^Yates, Steven."Ask GGW: Why is there no Silver Line station at Wolf Trap?".Greater Greater Washington.Archived from the original on September 25, 2022. RetrievedSeptember 25, 2022.
  161. ^"Regional Transit System Plan (RTSP)"(PDF).planitmetro.com. Washington Metropolitan Area Transit Authority. December 2013.Archived(PDF) from the original on January 20, 2019. RetrievedFebruary 19, 2019.
  162. ^"Blue/Orange/Silver Capacity & Reliability Study"(PDF). Washington Metropolitan Area Transit Authority. September 9, 2021.Archived(PDF) from the original on September 7, 2021. RetrievedSeptember 12, 2021.
  163. ^Denham, Hannah (September 7, 2021)."Here's how Metro could transform the Blue, Orange and Silver lines in the coming decades".Washington Business Journal. American City Business Journals. RetrievedSeptember 25, 2022.

External links

[edit]
Template:Attached KML/Silver Line (Washington Metro)
KML is from Wikidata

Media related toSilver Line (Washington Metro) at Wikimedia Commons

Subsidiaries
Metrorail lines
Bus rapid transit
Other topics
Related topics
Administration
Seal of Fairfax County, Virginia
Organizations
Landmarks
Transportation
Air
Roads
Transit
Culture
Battles
Education
Administration
Landmarks
Transportation
Culture
Battles
Education
Agencies
Washington Metro
Commuter rail
Inter-city rail
Bus
Bus rapid transit
DC Streetcar
Aviation
Former services
Future projects
Agencies
Metrorail
Rail
Commuter
Interregional
Bus
Aviation
Highways
State
U.S.
Interstate
Future projects
Retrieved from "https://en.wikipedia.org/w/index.php?title=Silver_Line_(Washington_Metro)&oldid=1322854784"
Categories:
Hidden categories:

[8]ページ先頭

©2009-2025 Movatter.jp