Map all coordinates usingOpenStreetMapDownload coordinates asKML
The Rhine–Main–Danube Canal (in the foreground) near NurembergThe Ludwig Canal in the context of the Rhine and Danube The various projects to link the Main and Danube
Projects for connecting the Danube and Rhine basins by canal have a long history. In 793, the EmperorCharlemagne ordered the construction of a canal—theFossa Carolina (German:Karlsgraben)—connecting theSwabian Rezat, atributary of theRednitz, to theAltmühl nearTreuchtlingen. Between 1836 and 1846 theLudwig Canal (German: Ludwigskanal), named for KingLudwig I of Bavaria, was built between Bamberg and Kelheim. This canal had a narrow channel, with manylocks, and a shortage of water in the peak section, so the operation of the waterway soon became uneconomic—especially given the rapidly advancing construction of therailway network in the southern German countryside. The canal finally was abandoned in 1950, after a decision was made to not repair damage it had suffered fromAllied bombing duringWorld War II.
In 1917, theLandtag of Bavaria passed a law calling for the development of a major shipping route "betweenAschaffenburg andPassau", with the capacity to carry the 1,200-ton ships used on theRhine. On 13 June 1921, Bavaria and theGerman Reich concluded an agreement to build the "Main-Donau-Wasserstraße".[1]Under this plan, in addition to the expansion of the Main and Danube, a completely new channel linking the rivers was to be created. The Rhein-Main-Donau AG (RMD-AG) was founded on 30 December 1921 to undertake the project. To finance the waterway, the RMD was given control of the water resources of the Main, Danube,Lech,Altmühl, andRegnitz.[2]
The first concrete plans for the new waterway emerged in 1938, for the so-called Mindorfer Linie south of Nuremberg. As early as 1939 the first preparatory work began atThalmässing inLandkreis Roth. However, after the war this route was dropped. By 1962, the Main's channel had been expanded as far upstream as Bamberg. In 1966, the Duisburger Vertrag, an agreement between Bavaria and theFederal Republic of Germany, was reached for financing the completion of the project. The contract was signed on 16 September of that year inDuisburg by Federal Transport MinisterHans-Christoph Seebohm, Federal Finance MinisterRolf Dahlgrün, Bavarian Prime MinisterAlfons Goppel and the Bavarian Finance Minister Konrad Pöhner.
The last section to be built, between Nuremberg and Kelheim, became politically controversial in the 1970s and 1980s, mainly because of the 34-kilometre (21 mi) long section through the Altmühl valley. On 25 September 1992, the canal was completed. The equivalent of some 2.3 billioneuros were invested in the construction from 1960 to 1992. Almost 20 percent of that went for environmental protection projects.
From Bamberg toFürth the canal follows the valley of theRegnitz, a tributary of the Main. From Fürth to beyondRoth it follows the valley of theRednitz, a tributary of the Regnitz. It crosses theFranconian Jura mountains and joins the riverAltmühl nearDietfurt. From Dietfurt toKelheim on the Danube the canal follows the Altmühl valley.
Today, some 60 kilometers of theLudwig Canal still exists in good condition betweenNuremberg andBerching. Some of the locks still function, and part of the towpath has been converted to a cycle track.[3] The old canal comes close to the new canal atPollanten, and from there the two canals flow downstream in parallel, eventually meeting 5km south ofBerching.
The cross-section of the waterway is normallytrapezoidal, with 31 metres (102 ft) width at the bottom, 55 metres (180 ft) width at the water surface, 4 metres (13 ft) of water depth, and a side grade of 1:3. The channel is aWaterway Class Vb; the largest authorised vessel is 190 metres (620 ft) long and 11.45 metres (37.6 ft) wide. The channel in the Kelheim-bound Bamberg lock has a depth of 2.70 metres (8.9 ft). In the few sections with a rectangular profile, the width is usually 43 metres (141 ft) (i.e., the mean between top and bottom widths).
The length of the canal is 171 kilometres (106 mi); the summit elevation (between theHilpoltstein andBachhausen locks) is 406 metres (1,332 ft) abovesea level. This is thehighest point on Earth that is currently reached by commercial watercraft from the sea.[4]
The height difference along the north ramp of the canal—from the Main atBamberg to the crest elevation—is 175 metres (574 ft), with 11 locks. From the crest elevation down to theAltmühl atDietfurt is a drop of 51 metres (167 ft) through three locks. The further difference in elevation of 17 metres (56 ft) along the Altmühl, with two more locks, makes a total of 68 metres (223 ft) for the south ramp. This means that the Danube end of the canal is 107.3 metres (352 ft) above the level of the Main end.
Along the course of the canal there are 16 locks with lifting heights of up to 25 meters (81 ft). The 16 locks are managed from four remote control centres (Neuses since 2007,Kriegenbrunn, Hilpoltstein, and Dietfurt from the beginning of 2007). These centres are staffed with one worker on the night shift, and two on the day shift. The locks were modernized from 2001 to 2007, replacing the outdatedrelay technology withprogrammable logic controllers (PLC). The cost was approximately $1.3 million per lock.
Thesummit pound is maintained by pumping water from the canal stretches below; and some water is drained into the summit pound from local natural sources. Finally apumped storage artificial lakeDürrlohsee that sits even higher in elevation than the summit pound makes up the difference if the aforementioned sources of water are not sufficient.
Animation demonstrating the operating principle of a water conserving set of locks
Thirteen locks are designed to conserve water, which they do by piping first the top third, and then the middle third of the lock water into side tanks during the down cycle. On the up cycle, these tanks replenish first the bottom third and then the middle third of the lock volume.[5] The remaining top third is supplied by water from the upper level of the canal.
There were different forecasts offreight transport volumes, from whichbenefit–cost ratio could be derived. In 1981, a Federal Minister for Transport cost–benefit account assumed an estimated traffic volume of only 2.7 million tonnes per year for the Main-Danube Canal, and a benefit–cost ratio of 0.52:1. This might have justified the termination of the project. One of the proponents commissioned a study by the Ifo-Institut München, predicting an estimated 5.5 million tonnes per year for the traffic volume on the Main-Danube Canal. In 2004, the freight volume in exchange traffic totalled 5.9 million tonnes and the total transport 6.9 million tonnes.[citation needed]
The course of the planned extension of the Danubewaterway betweenPassau andKelheim is still controversial. Proponents argue that the cost structure ofinland navigation will require larger ship sizes, so that larger lock dimensions, deeper channels and secure minimum water depth will be required. Opponents argue theenvironmental degradation is too great and that inland navigation is falling.[citation needed]
In order to maintain navigable water levels for the waterway in the Main, Regnitz and Rednitz valleys, water must be diverted via the Altmühlüberleiter canal & tunnel from the upper Altmühl to the Brombachsee reservoirs, across theEuropean Watershed between thedrainage basins of the Danube and Rhine.
On the other hand, the canal carriescargo traffic that would otherwise require 250,000 truck trips annually, or as an alternative, 3,000 freight trains on theDeutsche Bahn rail network.
So far about 20 species ofinvertebrates and a number offish have spread from the Danube to the Main, and on to the Rhine andLake Constance. The following list shows some examples:[7][8][9]
Memorial to the dam break in the Main-Danube Canal at Katzwang
The construction work was interrupted on 26 March 1979 by a serious accident in the Nuremberg district ofKatzwang. A dam broke on theEibach–Schwanstetten section, which was still under construction but already flooded. About 350,000 cubic metres (12,000,000 cu ft) of water[10] poured through the 15-metre (49 ft) wide hole and flooded large parts of old Katzwang.
The force of the water was so great that it dug a 10-metre (33 ft) wide crater and swept away cars, people and houses. During the rescue operations, a 12-year-old girl died. The damage was aroundDM 24 million (converted c. 12 millioneuros).[10]
After the disaster, the entire canal line was checked for weaknesses and retrofitted at critical points.
The long-distanceChallenge Rothtriathlon, which is held annually in July, includes a 3.8-kilometre (2.4 mi) swim in the Main-Danube Canal atHilpoltstein. The canal is closed to vessel traffic during the race. An approximately 14-kilometre (8.7 mi)-long section of themarathon route runs along the canal from the Hilpoltstein lock to the Leerstetten lock.
^"Ein Traum wird Wirklichkeit" Die Fertigstellung des Main-Donau-Kanals ('"A Dream Becomes Reality": the Completion of the Main-Danube Canal'), Siegfried Zelnhefer, July 1992.
^TheYukon River in northwesternNorth America is essentially navigable from theBering Sea toWhitehorse at 640 metres (2,100 ft) above sea level, but it is no longer used for commercial navigation.