R.E. Burger Power Station | |
---|---|
![]() | |
Country | United States |
Location | Mead Township,Belmont County, nearShadyside,Ohio |
Coordinates | 39°54′34″N80°45′37″W / 39.90944°N 80.76028°W /39.90944; -80.76028 |
Status | Decommissioned |
Commission date | Unit 1: 1944 Unit 2: 1947 Unit 3: 1950 Units 4–5: 1955 |
Decommission date | Units 1–2: 1995 Units 4–5: 2010 Unit 3: 2011 |
Owner | FirstEnergy |
Operator | FirstEnergy |
Thermal power station | |
Primary fuel | Coal |
Cooling source | Ohio River |
Power generation | |
Nameplate capacity | 568MW |
R.E. Burger Power Station was a 568 megawatt (MW),coal power plant located south ofShadyside, Ohio inBelmont County, Ohio. The plant closed in 2011. It was operated byFirstEnergy.
R.E. Burger was constructed in the 1940s to meet industrial demand for power generation duringWorld War II.[1] Unit 1 went into operation in 1944 and Unit 2 came online in 1947 at a cost of $5 million.[2][3][4] Both units had a capacity of 65 MW.[3] Unit 3, which went into operation in 1950 after two years of construction, had a generating capacity of 100 MW.[5] The unit cost $12 million to construct and was financed from the issuing ofOhio Edison stock byLehman Brothers.[1][5] Units 4 and 5 started generating electricity in 1955 and each had a generating capacity of 135 MW. The cost to construct both units totaled $43.2 million.[6] The plant is named after R.E. Burger, a former chairman of Ohio Public Service Company and later Ohio Edison.[5]
In 1991, R.E. Burger was an experimental site forclean coal technology by Ohio Edison with sponsorship from theUnited States Department of Energy. A SOx-NOx Rox Box (SNRB) developed byBabcock & Wilcox simultaneously removedsulfur dioxide (SO
2),nitrogen oxide (NOx), and particulates at the same time in a 5 MW unit.[7] Sorbent Technologies developed and demonstrated a jet-engine filter for pollution control at R.E. Burger in 1994.[8] In that same year, R.E. Burger incineratedrefuse-derived fuel in Unit 2 as a test run to see if fuel costs and emissions could be reduced.[9] FirstEnergy assumed ownership of R.E. Burger in 1997 following a merger between Ohio Edison and Centerior Energy.[10] In 2004, an Electro-Catalytic Oxidation (ECO)scrubber, designed by Powerspan to reduceSO
2 andmercury emissions, was tested at R.E. Burger with a generating capacity of 50 MW.[11] FirstEnergy announced in 2007 to install ECO scrubbers to Units 4 and 5 with a planned start-up scheduled for 2011.[12] Between 2006 and 2010, R.E. Burger was a test site for the Midwest Regional Carbon Sequestration Partnership's (MRCSP)carbon sequestration project. The project tested the potential of capturingcarbon dioxide (CO2) emissions and injecting it into geologic rock acting as a storage well.[13]
Ohio Edison shut down Units 1 and 2 in 1995 as the enforcement of theClean Air Act's 1990 amendments meant that both units were in non-compliance and the cost to retrofit outweighed the benefits.[14][15] FirstEnergy had plans in 2009 to convert R.E. Burger into abiomass plant to remain profitable in the face of cheaper natural gas prices and lower demand for electricity during theGreat Recession.[16][17] The costs to convert into a biomass plant was $130 million cheaper compared to installing industrial scrubbers to reduce pollution. Unfortunately, the economics to continue running R.E. Burger remained futile and FirstEnergy closed two units at the end of 2010.[17] The final unit, Unit 3, retired in 2011 due to stricter environmental rules.[2]
Demolition of R.E. Burger began in 2015 after four years of decommissioning.[2] Demolition was completed in July 2016 when the plant's 854 feet (260.3 m) smokestack wasimploded using explosive charges.[18] Thailand-based chemical companyPTT Global Chemical bought 168 acres of the former remediated R.E. Burger site from FirstEnergy for $13.8 million in 2017 to construct anethane cracker plant.[19]
{{cite news}}
:External link in|via=
(help){{cite news}}
:External link in|via=
(help){{cite news}}
:External link in|via=
(help)