Red Line (Chennai Metro)

From Wikipedia, the free encyclopedia
(Redirected fromLine 5 (Chennai Metro))
Transit line in Chennai, India

Red Line (Line 5)
Overview
Other nameMadhavaram - Sholinganallur Line
Native nameசிவப்பு வழித்தடம் (Sivappu vaḻittaṭam)
StatusUnder Construction
LocaleChennai,Tamil Nadu, India
Termini
Connecting linesOperational (5):
Blue LineGreen Line Chennai Suburan West Line , Chennai Suburan South Line , Chennai MRTS 
Upcoming (2):
Purple LineYellow Line
Stations45(Under Construction)
19(Proposed)
Websitechennaimetrorail.org
Service
TypeRapid transit
SystemChennai Metro
Operator(s)Delhi Metro Rail Corporation (DMRC)[1]
Depot(s)Madhavaram(U/C)
Pattabiram(Proposed)
Rolling stockBEML andAlstom
Technical
Line length68.76 km (42.73 mi)
Number of tracks2
Character5.8 km (3.6 mi) Underground(U/C)
41.2 km (25.6 mi) Elevated(U/C)
21.76 km (13.52 mi) Elevated (Proposed)
Track gauge1,435 mm (4 ft 8+12 in)standard gauge
Electrification25 kV 50 Hz ACoverhead catenary
SignallingCBTC Signalling System
Route map

Pattabiram Depot
Pattabiram
Hindu College
Kasturibai Nagar
Madhavaram Milk ColonyPurple Line
Avadi railway stationAvadi
Madhavaram Depot
Murugappa College
Assisi Nagar
Vaishnavi Nagar
Manjambakkam
Thirumullaivoyal
Velmurugan Nagar
Stedford Hospital
Bus interchangeMadhavaram Bus Terminal
Ambattur OT
Sastri Nagar
Retteri Junction
Ambattur
Kolathur
Dunlop
Srinivasa Nagar
Villivakkam
Ambattur Bypass
Bus interchangeAmbattur Estate
Villivakkam Bus Terminus
Vavin 1st Main Road
Villivakkam CTH Road
Golden Colony
Anna Nagar West
Park Road
ThirumangalamGreen Line
Padi Pudhu Nagar
Anna Nagar KV
KoyambeduGreen Line
Koyambedu Market
Natesan Nagar
Virugambakkam
AlwarthirunagarYellow Line
ValasaravakkamYellow Line
KarambakkamYellow Line
Alapakkam JunctionYellow Line
Mugalivakkam
Ramapuram
Manapakkam
Chennai Trade Centre
Butt Road
AlandurBlue LineGreen Line
St. Thomas MountGreen Line
Adambakkam
Vanuvampet
Ullagaram
Madipakkam
Kilkattalai
Echangadu
Kovilambakkam
Vellakkal
Medavakkam I
Medavakkam II
Perumbakkam
Classical Tamil Institute
Elcot
SholinganallurPurple Line

TheRed Line orLine 5 is one of the under construction lines ofChennai Metro Phase-II stretching fromMadhavaram Milk Colony toSholinganallur. The 47 km (29 mi) long line will consist of 45 stations, out of which six will be underground and 39 will be at grade or elevated. A branch line of corridor five, known as Line 5B, fromKoyambedu toPattabiram has been proposed with its Detailed Project Report approved byGovernment of Tamilnadu on May 2025.[2] The 21.76 km (13.52 mi) branch line will consist of 19 elevated stations.[3]

Planning and construction

[edit]

Phase II

[edit]

The construction of the first phase ofChennai Metro started in June 2009.[4] Commercial operations started on thegreen line in June 2015.[5][6][7] On 10 February 2019, the extension ofblue line was opened, completing the first phase of the metro.[8]

In July 2016,Government of Tamil Nadu announced that the second phase would have three lines totaling 104 km (65 mi) in length with 104 stations.[9][10] Two corridors would extend fromMadhavaram connecting withSiruseri andSholinganallur respectively (lines 3 and 5) with the third corridor connectingKoyambedu withLighthouse (line 4). The fifth line connectingMadhavaram Milk Colony and Sholinganallur will extend to 47 km (29 mi) of which 41.2 km (25.6 mi) would beelevated and 5.8 km (3.6 mi)underground. It will consist of 48 stations including six undergrounds stations.[11][12] The stations for the second phase were designed to be smaller than the existing stations operational in the first phase.[13]

On 20 November 2020, foundation stone for the second phase was laid and construction commenced.[14] In November 2022, Alstom was awarded the contract to supply metro coaches for the phase II expansion.[15] In May 2023, CMRL announced a revised plan for the second phase revising the station count on the fifth line to 45.[16] As per the final plan, the line will extend for 47 km (29 mi).[17]

Chennai Metro - Phase II[18]
Line NameTerminalsLength (km)StationsStatus
Red LineMadhavaram Milk ColonySholinganallur4745Under construction

The second phase is estimated to cost63,246 crore (US$7.5 billion) of which initially4,710 crore (US$560 million) was loaned by JICA.[11][19][20] On 14 February 2021,Prime Minister of India announced that the government has set aside63,000 crore (US$7.5 billion) for the construction of phase II and further extension.[21] The line is expected to be completed by 2028.[22]

Phase II extension

[edit]

In 2022, the state government proposed a branch extension for the fifth line fromKoyambedu toAvadi, covering an approximate 16.1 km (10.0 mi).[23] In early 2024, feasibility report was submitted by CMRL for the proposed expansion of the line, green lighting the same.[24] It was later decided to extend the line tillPattabiram. Detailed Project Report is approved byGovernment of Tamil Nadu on May 2025 and forwarded toGovernment of India for final approval.[2] A depot nearPattabiram stretch ofOuter Ring Road is also planned.

Chennai Metro - Phase II Extension - Line 5B[24][3]
LineTerminalsLengthStationsStatus
Red LineKoyambeduPattabiram21.76 km (13.52 mi)19DPR approved

Stations

[edit]
Red Line
S.NoStation Name[18]Expected Opening[25]ConnectionsLayout
EnglishTamil
1Madhavaram Milk Colonyமாதவரம் பால் பண்ணைMarch 2027 Purple Line  (Under Construction)Underground
2Madhavaram Depotமாதவரம் பணிமனைMarch 2027At-grade
3Assisi Nagarஅசிசி நகர்March 2027Elevated
4Manjambakkamமஞ்சம்பாக்கம்March 2027Elevated
5Velmurugan Nagarவேல்முருகன் நகர்March 2027Elevated
6Madhavaram Bus Terminusமாதவரம் பேருந்து நிலையம்March 2027Madhavaram Mofussil Bus TerminusElevated
7Shastri Nagar, Chennaiசாஸ்திரி நகர்March 2027Elevated
8Retteri Junctionரெட்டேரி சந்திப்புMarch 2027Elevated
9Kolathur Junctionகொளத்தூர் சந்திப்புMarch 2027Underground
10Srinivasa Nagarசீனிவாச நகர்March 2027Underground
11Villivakkamவில்லிவாக்கம்March 2027Mainline rail interchangeWest Line, Chennai Suburban (Villivakkam)Underground
12Villivakkam Bus Terminusவில்லிவாக்கம் பேருந்து நிலையம்March 2027Underground
13Villivakkam CTH Roadவில்லிவாக்கம் சி.டி.எச் சாலைMarch 2027Underground
14Anna Nagar Westஅண்ணா நகர் மேற்குDecember 2026Elevated
15Thirumangalamதிருமங்கலம்December 2026 Green Line Elevated
16Anna Nagar KVஅண்ணா நகர் கே.விDecember 2026Elevated
17Koyambeduகோயம்பேடுDecember 2026 Green Line Elevated
18Koyambedu Marketகோயம்பேடு அங்காடிDecember 2026Elevated
19Natesan Nagarநடேசன் நகர்December 2026Elevated
20Virugambakkamவிருகம்பாக்கம்December 2026Elevated
21Alwarthirunagarஆழ்வார்திருநகர்June 2026 Yellow Line  (Under Construction)Elevated
22Valasaravakkamவளசரவாக்கம்June 2026 Yellow Line  (Under Construction)Elevated
23Karambakkamகாரம்பாக்கம்June 2026 Yellow Line  (Under Construction)Elevated
24Alapakkam Junctionஆலப்பாக்கம் சந்திப்புJune 2026 Yellow Line  (Under Construction)Elevated
25Mugalivakkamமுகலிவாக்கம்June 2026Elevated
26Ramapuramராமாபுரம்June 2026Elevated
27Manapakkamமணப்பாக்கம்June 2026Elevated
28Chennai Trade Centreசென்னை வர்த்தக மையம்June 2026Elevated
29Butt Roadபட் சாலைDecember 2026Elevated
30Alandurஆலந்தூர்December 2026 Blue Line 
 Green Line 
Elevated
31St. Thomas Mountபரங்கிமலைDecember 2026 Green Line 
Mainline rail interchangeSouth Line, Chennai Suburban (St. Thomas Mount)
Mainline rail interchangeChennai MRTS[§] (St. Thomas Mount)
Elevated
32Adambakkamஆதம்பாக்கம்December 2026Mainline rail interchangeChennai MRTS[§] (Adambakkam)Elevated
33Vanuvampetவானுவம்பேட்டைDecember 2026Elevated
34Ullagaramஉள்ளகரம்December 2026Elevated
35Madipakkamமடிப்பாக்கம்December 2026Elevated
36Kilkattalaiகீழ்க்கட்டளைDecember 2026Elevated
37Echangaduஈச்சங்காடுDecember 2026Elevated
38Kovilambakkamகோவிலம்பாக்கம்December 2026Elevated
39Vellakkalவெள்ளக்கல்December 2026Elevated
40Medavakkam Iமேடவாக்கம் IDecember 2026Elevated
41Medavakkam IIமேடவாக்கம் IIDecember 2026Elevated
42Perumbakkamபெரும்பாக்கம்December 2026Elevated
43Classical Tamil Instituteசெம்மொழித் தமிழாய்வு நிறுவனம்December 2026Elevated
44Elcotஎல்காட்December 2026Elevated
45Sholinganallurசோழிங்கநல்லூர்December 2026 Purple Line  (Under Construction)Elevated

§ under construction

See also

[edit]

References

[edit]
  1. ^Sampath, Nirupa (3 April 2025)."Chennai Metro Rail outsources phase 2 to Delhi Metro". DT Next. Retrieved18 April 2025.
  2. ^abSundaram, Ram (2 May 2025)."TN govt gives in-principle nod for Chennai Metro link from Koyambedu to Pattabiram".The Times of India. Retrieved2 May 2025.
  3. ^ab"Chennai Metro Rail submits DPR for 21.76 km extension from Koyambedu to Pattabiram".The New Indian Express. 22 February 2025. Retrieved22 February 2025.
  4. ^"Work commences on Chennai Metro". Projects Today. 11 June 2009.Archived from the original on 25 August 2017. Retrieved16 August 2010.
  5. ^"Chennai Metro one stop short of dream run".Deccan Chronicle. 31 August 2014.Archived from the original on 4 March 2016. Retrieved6 June 2016.
  6. ^"Conditional clearance for Metro Rail".The Hindu. 28 April 2015.Archived from the original on 14 January 2016. Retrieved7 June 2016.
  7. ^Chennai Metro Newsletter - August 2015(PDF) (Report). Chennai Metro. 29 June 2015.Archived(PDF) from the original on 20 October 2023. Retrieved7 June 2023.
  8. ^Simhan, TE Raja (10 February 2019)."PM Modi inaugurates Chennai Metro Rail's final leg".The Hindu Businessline.Archived from the original on 26 October 2020. Retrieved13 February 2019.
  9. ^Sekar, Sunitha (2 August 2016)."1800 km, 180 stations: Unveiling Phase II of Metro".The Hindu.Archived from the original on 26 December 2016. Retrieved24 January 2017.
  10. ^Sekar, Sunitha."Detailed project report for Phase II of Metro Rail ready".The Hindu.Archived from the original on 27 December 2016. Retrieved24 January 2017.
  11. ^ab"Project status of Chennai Metro". Chennai Metro Rail Limited.Archived from the original on 26 September 2016. Retrieved16 August 2010.
  12. ^"Metro's second phase to go up to Poonamallee".The Hindu. 20 July 2017.Archived from the original on 26 February 2020. Retrieved1 October 2017.
  13. ^U, Tejonmayam (28 December 2016)."Chennai: Metro rail to trim stations under phase 2".The Times of India.Archived from the original on 8 February 2017. Retrieved24 January 2017.
  14. ^"Amit Shah to lay foundation for Chennai Metro's phase II project".The Hindu. 17 November 2020.Archived from the original on 28 April 2024. Retrieved1 December 2023.
  15. ^"Alstom wins €98 million contract to design and manufacture 78 metro coaches for Chennai Metro Phase-II" (Press release). Alstom. 11 November 2022.Archived from the original on 16 December 2023. Retrieved1 December 2023.
  16. ^"Chennai metro scraps nine stations in phase 2".The Times of India. 14 May 2023. Retrieved1 May 2024.
  17. ^"Phase II– S98 (Anaimalai) TBM Breakthrough at Venugopal Nagar Shaft"(PDF) (Press release).Chennai Metro Rail Limited. 7 June 2023. Archived fromthe original(PDF) on 2 June 2024. Retrieved1 May 2024.
  18. ^abChennai Metro rail phase II(PDF) (Report).Chennai Metro Rail Limited. Retrieved1 May 2024.
  19. ^"Phase-II Chennai metro project to cost Rs 36,000 cr".Business Standard. 2 March 2014.Archived from the original on 16 December 2023. Retrieved1 December 2023.
  20. ^"JICA extends ODA Loan of INR 4710 Cr for Chennai Metro Rail Project Phase 2 (II)". JICA. 21 June 2022.Archived from the original on 16 December 2023. Retrieved1 December 2023.
  21. ^Dipak K, Dash."Ground work for Chennai metro rail phase-2 hit".Times of India.Archived from the original on 18 February 2021. Retrieved19 February 2021.
  22. ^"Metro Rail second phase likely to be completed in six years".The New Indian Express. 26 April 2019. Retrieved26 April 2019.
  23. ^"Detailed feasibility report for Chennai Metro Rail's Phase 2 extension to be ready in three months".The Hindu. 26 March 2023.Archived from the original on 28 April 2024. Retrieved1 December 2023.
  24. ^ab"CMRL submits Detailed Feasibility Reports for Phase II project extension".The Financial Express. 22 September 2023.Archived from the original on 29 April 2024. Retrieved30 April 2024.
  25. ^Sekar, Sunitha (20 January 2024)."Work on elevated stretches of corridor 5 of Metro Rail phase II project gains momentum".The Hindu.ISSN 0971-751X. Retrieved22 March 2025.
Under
Construction
(Main Line)
Extension
During Phase-2
(Branch Line)
  • Padi Pudhu Nagar
  • Park Road
  • Golden Colony
  • Vavin 1st Main Road
  • Ambattur Estate
  • Ambattur Bypass
  • Dunlop
  • AmbatturAmbattur railway station
  • Ambattur OT
  • Stedford Hospital
  • Thirumullaivoyal
  • Vaishnavi Nagar
  • Murugappa College
  • AvadiAvadi railway station
  • Kasturibai Nagar
  • Hindu CollegeHindu College railway station
  • Pattabiram
  • Pattabiram Outer Ring Road
Depot(s)
  • Madhavaram (U/C) & Pattabiram (TBC)
See also
Bold represents terminal station on the respective main or branch line
Stations initalics are Proposed/Under Construction
Stations inBold and italics are terminal stations Proposed/Under Construction