This articleneeds additional citations forverification. Please helpimprove this article byadding citations to reliable sources. Unsourced material may be challenged and removed. Find sources: "Cross City Tunnel" – news ·newspapers ·books ·scholar ·JSTOR(July 2024) (Learn how and when to remove this message) |
![]() Cross City Tunnel exit at Sir John Young Crescent,Woolloomooloo | |
Overview | |
---|---|
Location | Sydney |
Coordinates | 33°52′23″S151°12′13″E / 33.873001°S 151.203602°E /-33.873001; 151.203602 |
Start | ![]() Darling Harbour |
End | New South Head Road Bayswater Road Rushcutters Bay |
Operation | |
Work begun | January 2003 |
Opened | August 2005 |
Owner | Transport for NSW |
Operator | Transurban |
Toll | SeeTolls section below |
Technical | |
Length | 2.2 km (1.4 mi) |
No. oflanes | 4 |
Operating speed | 80 km/h (variable) |
Tunnel clearance | 4.4 metres |
TheCross City Tunnel is a 2.2-kilometre long (1.4 mi)[1] twin-road tunneltollway located inSydney,New South Wales, Australia. The tunnel linksDarling Harbour on the western fringe of thecentral business district toRushcutters Bay in theEastern Suburbs. Each of the twin tunnels has a different alignment, with the westbound tunnel running underneathWilliam andPark streets and the eastbound tunnel running underneathBathurst Street.
The tunnel is owned by theGovernment of New South Wales and is operated byTransurban under a toll concession until 2035.
In early 2002, a year before construction began, transport planner Michelle Zeibots was quoted in local newspapers saying the tunnel would not reach its traffic targets.[2]
The tunnel comprises two road tunnels – one eastbound and one westbound – each with two traffic lanes, in addition to a third small ventilation tunnel. The Cross City Tunnel also links with theEastern Distributor, enabling vehicles travelling from the West to travel to theAirport and Southern Suburbs. From the Eastern Distributor, northbound motorists can connect to the Cross City Tunnel Westbound, avoiding the CBD once again.
The tunnel was Sydney's first completely electronic tollway requiring the driver to have an electronic tolling tag installed in their car or register for an electronic pass (for casual or less frequent users).
Sydney's Cross City Tunnel was predicted to fail before construction even began. In February 2002, a year before tunnelling commenced and four years before it ultimately fell into receivership due to low traffic volumes, Sydney traffic planner Michelle Zeibots told local media that the tunnel was incapable of carrying the volume of cars that the Transport Minister,Carl Scully had predicted. She said it was "physically impossible" for the tunnel to carry the predicted 95,000 cars each day. While theNRMA was enthusiastic about building the new motorway, Dr Zeibots was scathing. "It's not a serious transport project," she said at the time. "The inputs and outputs just don't add up."[2]
Despite the warnings of a traffic shortfall, in 2002, the government ofBob Carr awarded Cross City Motorways the contract to build, own and operate an east–west tunnel underneath the Sydney CBD.[3]
The passing of theRoads Act of 1993[4] updated road classifications and the way they could be declared within New South Wales. Under this act, theRoads & Traffic Authority declared the Cross City Tunnel as Tollway 6010, from its interchange withWestern Distributor inDarling Harbour toRushcutters Bay, on 16 December 2002, nearly three years before it had officially opened;[5] the tollway still retains this declaration today.[6]
Construction work for the Cross City Tunnel commenced in January 2003, and the tunnel was originally scheduled to open in October 2005. In April 2005 the NSW government announced that the tunnel would open four months early on 12 June 2005. The opening day was subsequently postponed due to detailed commissioning works, with the official opening going ahead on 28 August 2005. The tunnel was opened by thePremier of New South Wales,Morris Iemma, using the same pair of scissors used to open theSydney Harbour Bridge in 1932, theSydney Harbour Tunnel in 1992 and theAnzac Bridge in 1995.[7] Prior to the vehicular opening there was a charity walk-through, as is customary for new roadways in Sydney, which attracted a large number of public visitors. The first traffic passed through the tunnel late on 28 August.
Later a three-week toll-free period was announced by the operators.[8] At the same time, the operators announced a freeze on toll increases for twelve months and the fee for casual (non-electronic tag) users was waived.
In February 2006, media speculation of a "buy-out" by the New South Wales government began. The rumoured price would exceed AUD$1 billion while the tunnel only cost AUD$680 million to build.[citation needed] The government stated no discussions had taken place, and the Cross City Tunnel Consortium stated that they were not considering selling the tunnel and were "in for the long haul". At the time the average trips per day was approximately 30,000.[citation needed]
This was shortly followed by a report from the NSW Upper House committee headed by MPFred Nile recommending that the toll be reduced, and surface road closures reversed. While the recommendations could not be enforced, the Cross City Tunnel Consortium did consult with the government before announcing a discount to the toll, as well as other changes on 3 March 2006.[citation needed] Specifically, the Consortium announced that the toll would be halved to $1.78 for three months, that some planned road closures would not be pursued, and that some existing road closures would be reversed.[citation needed] Two days prior to the end of the half-price toll period, the Premier of NSW, Morris Iemma, ended negotiations with the Cross City Tunnel Consortium without an agreement, announcing the immediate reversal of some road closures, contrary to the contract.[citation needed]
In April 2006, a Reclaim The Streets protest was held at the Cross City Tunnel. Attendees called for greater investment in public transport and cycle paths, with partygoers occupying the tarmac and enjoying performances by the ShittyRail Transit Cop dance troupe.[9]
In November 2006, it was reported that the motorway was in financial difficulties, and that additional equity would be required from the tunnel's investors in order to avoid placing the tunnel in administration. At the same time, it was suggested that traffic volumes of between 60,000 and 90,000 per day were needed in order for the consortium to meet the tunnel interest payments.[10] The NSW government responded to the reports by indicating that it would not buy out the tunnel, nor assist in its financing.
The A$680 million tunnel was originally financed by a combination of international equity and both locally and internationally sourced debt.[citation needed]
Equity of $220 million was provided by three international companies,Cheung Kong Infrastructure (50%),DB Capital Partners (30%) andBilfinger Berger (20%). The remaining $580 million was financed through a syndicate of Australian and international banks led byWestpac andDeutsche Bank.[10] It was built by aBaulderstone Hornibrook / Bilfinger Berger joint venture.[11]
In December 2006, the tollway became insolvent due to low traffic volumes, accumulating debts of over A$500 million. On 27 December 2006, a syndicate of 16 Australian and International banks appointed the insolvency firmKordaMentha as receivers and managers for Cross City Motorway Limited after the project accrued debts exceeding A$560 million.[12]
On 20 June 2007,ABN AMRO (94%) andLeighton Contractors (6%) were chosen as preferred purchasers of the Cross City Tunnel Group for $700 million.[13][14]
On 13 September 2013, the new owners placed itself in voluntary administration, saying that it was unable to refinance its debt due to action by the New South Wales government to claim $64 million in stamp duty on the original sale.[15] In June 2014, the tunnel was sold toTransurban.[16]
This sectiondoes notcite anysources. Please helpimprove this section byadding citations to reliable sources. Unsourced material may be challenged andremoved.(September 2024) (Learn how and when to remove this message) |
There has been some controversy over the expected and actual usage of the tunnel during its initial operation. The number of vehicles travelling through the tunnel has been debated in the media, along with alleged discrepancies between the actual number of trips and the anticipated number of trips in the tunnel's financial projections.
Tunnel operators indicated that they expected initial uptake of the tunnel to reach approximately 35,000 vehicles per day, increasing over its first year of operation to a projected 90,000 vehicles per day. Once documentation of the official projections was released, it was found that the operators projected daily traffic after six months at 85,352.
Approximately one month after opening it was reported in the media that only 20,000 vehicles a day were using the tunnel, although the government and toll operators maintained that the average number of daily trips since opening was approximately 25,000.
At the completion of the initial three-week toll-free period, the tunnel operators announced that the daily tunnel usage had increased to 53,000 during that time.[17]
A few weeks after the toll had been reinstated, it was reported in the media that usage had dropped back to approximately 27,000, an improvement of 7,000 cars per day compared with usage prior to the toll free period.
Following the toll-free period, the tunnel operator indicated that it would likely be two to three years before the tunnel reached its full potential.
In May 2006, in the first two months after the tunnel operators announced a temporary halving of the toll, media reports indicated that usage had increased to approximately 34,000 per day.[17]
The tunnel is tolled for its entire length, with a lower charge when exiting westbound to Sir John Young Crescent northbound. Truck and heavy vehicle prices are double the price for cars.
Toll road | Class A toll prices[a] | Class B toll prices[a] | Toll increase[20] | Toll concessionaire | Expiry of toll concession[21] |
---|---|---|---|---|---|
Cross City Tunnel | $3.23 (Sir John Young Crescent exit) $6.85 (otherwise) | $6.46 (Sir John Young Crescent exit) $13.69 (otherwise) | Quarterly on 1 January, 1 April, 1 July, and 1 October, by the greater of quarterly CPI or 1% | Transurban | December 2035 |
The Cross City Tunnel is entirely contained within theCity of Sydneylocal government area.
Location | km[1] | mi | Destinations | Notes | |
---|---|---|---|---|---|
Darling Harbour | 0.0 | 0.0 | ![]() | Western terminus of Cross City Tunnel Eastbound tunnel entrance is underneathBathurst Street; Westbound tunnel exit is underneath Druitt Street | |
Harbour Street – Haymarket,Sydney CBD | |||||
Tunnel western terminus and toll western terminus | |||||
Wooloomooloo | 1.4 | 0.87 | ![]() ![]() | Westbound entrance and eastbound exit only | |
1.5 | 0.93 | Sir John Young Crescent (north) -Woolloomooloo, to ![]() | Westbound exit only | ||
Rushcutters Bay | 2.2 | 1.4 | Tunnel eastern terminus and toll eastern terminus | ||
Bayswater Road(e/bound)/New South Head Road(w/bound) -Edgecliff,Dover Heights,Watsons Bay | Cross City Tunnel eastern terminus | ||||
|
This sectionneeds additional citations forverification. Please helpimprove this article byadding citations to reliable sources in this section. Unsourced material may be challenged and removed. Find sources: "Cross City Tunnel" – news ·newspapers ·books ·scholar ·JSTOR(May 2020) (Learn how and when to remove this message) |
There are a number of criticisms that have been made about the Cross City Tunnel (CCT), more so than for similar large capital works programs in Sydney,[citation needed] including the following:
One of the tunnel's major shortcomings is the fact that traffic is forced straight onto suburban roads at both ends, creating additional traffic congestion at these locations. This is likely to be rectified at the Western end when construction of theM4 East Tunnels and theRozelle Interchange are completed in 2023.[citation needed]
In September 2005, as part of the media attention surrounding these criticisms, a local newspaper commissioned an audit of the usage of the tollway by independent surveyors who found that on a single day, around 21,000 vehicles had used the tunnel.[17] This was countered by a spokesman for the tunnel operator, who said about 550,000 vehicles had used the tunnel in its initial operation, at an average of approximately 25,000 cars per day.[citation needed]
In October 2005, a call centre handling calls related to the Cross City Tunnel halved its staff due to the low number of calls.[citation needed]
In September 2006 theSydney Morning Herald reported that the operator had not pursued for 12 months motorists who had not paid the toll[35] (along with theM2 Hills Motorway) due to a lack of agreement on a system for passing of the details to the RTA. The Cross City Motorway subsequently promised that toll evaders will be pursued.