| Coolidge Dam | |
|---|---|
Upstream face of Coolidge Dam, fromHistoric American Engineering Record | |
![]() Interactive map of Coolidge Dam | |
| Country | United States |
| Location | Gila County andPinal County, Arizona |
| Coordinates | 33°10′29″N110°31′40″W / 33.174687°N 110.527863°W /33.174687; -110.527863 |
| Status | Operational |
| Construction began | 1924 |
| Opening date | 1930 (95 years ago) (1930) |
| Construction cost | US$10 million ($149 million in 2024 dollars[1]) |
| Owner | Bureau of Indian Affairs |
| Dam and spillways | |
| Type of dam | Arch dam |
| Impounds | Gila River |
| Height | 249 ft (76 m) |
| Elevation at crest | 2,535 ft (773 m) |
| Width (crest) | 580 ft (180 m) |
| Dam volume | 200,000 cu yd (150,000 m3) |
| Spillways | 2 |
| Spillway type | Ogee |
| Reservoir | |
| Creates | San Carlos Reservoir |
| Total capacity | 910,000 acre⋅ft (1.12×109 m3) |
| Power Station | |
| Commission date | 1935 |
| Decommission date | 1983 |
| Type | Conventional |
| Turbines | 2 × 5MW |
| Installed capacity | 10 MW |
Coolidge Dam | |
| Area | 21 acres (8.5 ha) |
| Built | 1927 |
| Built by | Major C.R. Olberg; Atkinson, Kier Bros. & Spice Co. |
| Architect | Herman Neuffer |
| Architectural style | Multiple Dome Dam |
| NRHP reference No. | 81000135[2] |
| Added to NRHP | October 29, 1981 |

TheCoolidge Dam is areinforced concrete multiple dome andbuttress dam 31 miles (50 km) southeast ofGlobe, Arizona on theGila River. Built between 1924 and 1928, the Coolidge Dam was part of the San Carlos Irrigation Project. Coolidge Dam was named after the 30th US president,Calvin Coolidge and was dedicated by President Coolidge on March 4, 1930. The design and construction engineer was Herman Neuffer, who oversaw much of the construction undertaken by theBureau of Indian Affairs (BIA) during the 1920s in Arizona and New Mexico.
Coolidge Dam impoundsSan Carlos Lake on theSan Carlos Apache Indian Reservation. The project irrigates 100,000 acres (40,000 ha).
Since the water is impounded so it can be released when farmers need it, San Carlos Lake is often at a low level except in wet periods. When former President Coolidge dedicated the dam in 1930, the dam had not begun to fill. HumoristWill Rogers looked at the grass in the lake bed, and said, "If this were my lake, I'd mow it."[3]

Coolidge Dam was constructed between 1924 and 1928 by theBureau of Indian Affairs (BIA), which also owns and operates it, at a cost of US$10 million.[4] The overall structure used 200,000 cubic yards (150,000 m3) of concrete and consists of three domes, which are supported by buttresses on 100-foot (30 m) centers. It rises 249 feet (76 m), with a crest length of 580 feet (180 m). Two uncontrolled ogee crestspillways are concrete-lined and located on eachabutment.[5]
Construction of the dam incurred opposition from theApache tribe, who feared a violation of their treaty rights, according to an author writing for theFederal Writers' Project:
A compromise was finally made with the Indians, and the tribalburial grounds and the old camp from whichGeronimo started his bloody raids now lie deep under the waters of thereservoir. It was proposed todisinter the bodies but the Apache vehemently objected to what they considereddesecration of the dead, so a concrete slab was laid over the principal burial ground at a cost of $11,000.[6]
In 1936, the Coolidge Dam was used an execution site for serial killerEarl Gardner. At the time, federal law mandated that all federal executions had to be carried out by hanging on federal territory. Federal authorities constructed a makeshift gallows using an abandoned rock crusher left over from the dam's construction. Gardner's execution was botched and took over half an hour for him to die. In response, Congress passed a law stating that all federal executions would now be carried out using whatever method was used in the state.[7]
As part of theSan Carlos Indian Irrigation Project (SCIIP), Coolidge Dam formerly generated electricity from a hydroelectric plant. Adiesel electric generating plant also run by the Project was built simultaneously and located on withdrawn land near the town of Coolidge. The latter facility provided power forirrigation wells, local towns, rural users, and mining operations. The diesel generators no longer function, therefore electricity is delivered to SCIP by the Western Area Power Administration.[8] However, flood damage in 1983 rendered the hydroelectric station inoperable and restoration plans have been deemed infeasible.[9] The electric plant at the dam was completed and began generating electricity in 1935, and the diesel plant was completed in December of that year and produced electricity the following year.[10]
In 1988, theBureau of Reclamation completed a study that concluded that the dam needed modifications to prevent a failure should a significant flood or an earthquake occur. Earlier floods that had resulted in water topping the dam had eroded the abutments, and the buttresses were judged to be unstable. Work started in 1991 and included an access road to the downstream side of the dam. The work concluded in 1995. The final cost was estimated at $US46.5 million.[11] ($87.2 million in 2024 dollars[1])
In January 1993, heavy rainfall (up to three times the normal amount) in Arizona filled San Carlos Lake, and the operators were forced to release excess water. The ground was saturated, and the continuing rainfall ran off into the streams and rivers. In addition, the weather pattern for the year caused higher than normal temperatures in areas that would typically remain under snow. These areas received rain instead of snow, and the rivers began to run earlier and with far more volume than normal. Rivers in the southern part of Arizona at that time contained anywhere from three to nearly six times their normal amount of water. To complicate matters, the snowpack was already 150% the normal amount. Dam operators for Coolidge Dam released water in record levels because storage capacity had been reached.[12]
As a result of the heavy water releases, several El Paso Natural Gas pipelines, which crossed the Gila River nearCoolidge,Winkelman, andKelvin were "scoured" or uncovered by the force of the water and failed. The water flow was concentrated through the release gates, as opposed to letting the water overtop the dam, which would have created a different scour rate. The force of the Gila River undermined and ultimately caused the failure of the north and south abutments of the bridge crossing at Attaway Road, upstream from Coolidge.
The flow into San Carlos Lake (from the Gila and San Carlos rivers) during January 1993 peaked between 3,000 to 3,500 cubic metres per second (110,000 to 120,000 cu ft/s). The flow from Coolidge Dam reached 927 cubic metres per second (32,700 cu ft/s), about seven times the expected maximum release rate of 133 cubic metres per second (4,700 cu ft/s), and was the highest release rate for the dam since its construction. Discharge at Winkleman was recorded at 1,050 cubic metres per second (37,000 cu ft/s) on January 20, 1993. Winkleman Flats, a small area near Winkleman, was flooded as well.[12] However, despite earlier concerns about the dam's safety, it survived the flood even though retrofit work was in process at the time.

San Carlos Lake is stocked periodically, and when the winter has experienced average or above average precipitation, is one of the largest lakes in Arizona. The San Carlos Apache Tribe Recreation & Wildlife Dept. stocks several species of fish using various methods to create a good fishing environment. Several species are self-sustaining:
Other fish are stocked from cold-water fisheries includingbrown trout andrainbow trout. Jet-skiing, water skiing and boating are allowed. Individuals who are not members of the San Carlos Apache tribe who wish to use the lake must contact the tribal office for a permit since the lake is on tribal land.[13]
Bicyclists can ride the access road to the dam face and back. The route is scenic and little-traveled, and rises a total of about 700 feet along the 13 mile route. Theelevation at the dam is about the same as the starting point, so the trip is not strictly a climb, but peaks about the middle of the distance and then descends again to about 2,600 ft.
When they reach the dam, cyclists can either return to the starting point along the two-lane paved road, or they can continue eastward along the rougher part of the road until it rejoinsU.S. Route 70. Before traveling on the reservation, non-tribe members must obtain a permit. Amountain bike or other rugged type bicycle is recommended for cyclists traveling east from the dam to Rte 70.[14]
{{cite book}}:ISBN / Date incompatibility (help)