Brenner Base Tunnel

Coordinates:47°3′24″N11°29′59″E / 47.05667°N 11.49972°E /47.05667; 11.49972
From Wikipedia, the free encyclopedia
Railway under construction through the Alps
Brenner Base Tunnel
Exploratory Tunnel Aica–Mules
Overview
LocationBrenner Pass
StatusUnder construction
SystemBrenner railway
StartInnsbruck, Austria
EndFranzensfeste, Italy
Operation
Work begun2008
Constructed2007–present
Opened2032 (scheduled)
TrafficFreight trains andpassenger trains
CharacterTwin tube
Passenger and freight
Third exploratory tunnel
Technical
Length64 km (40 mi)
No. oftracksDouble track
Track gauge1,435 mm (4 ft 8+12 in)standard gauge
ElectrifiedElectrified
15 kV 16.7 Hz AC (Austria)
25 kV 50 Hz AC (Italy)
Operating speed
  • Passenger:
  • 250 km/h (155 mph)
  • Freight:
  • 120 km/h (75 mph)
Highest elevation840 metres (2,760 ft)
Tunnel clearance8.1 metres (27 ft)
GradeAustria 7.4/1000
Italy 5/1000
Route map
Brenner Base Tunnel
Lower Inn railway
Lower Inn railway
bridge overriver Inn
Innsbruck bypass
North portal
Ampass shaft
Brenner Base shaft
North portal toInnsbruck
Ahrental shaft
Wolf shaft
Italy-Austria border
Mauls/Mules shaft
Aicha/Aica shaft
Brenner Base Tunnel
South portal
Brenner railway
Franzensfeste
Brenner railway
Riggertal/Val Riga shaft
Albeins/Albes shaft
Eisack/Isarco bridge
Brenner Railway
Klausen/Chiusa shaft
Brenner railway
Brenner railway
Laives/Leifers-Steinmannwald shaft
Brenner railway
Brenner railway

TheBrenner Base Tunnel (German:Brennerbasistunnel;Italian:Galleria di base del Brennero) is a 55-kilometre-long (34 mi)railway tunnel under construction through the base of theEastern Alps beneath theBrenner Pass. Once completed, the Brenner Base Tunnel will rank as either the second or thirdlongest railway tunnel in the world, depending on the definition employed. It will be surpassed in length only by theGotthard Base Tunnel in Switzerland and, depending on the relative completion dates of these projects, theMont d'Ambin Base Tunnel between France and Italy. When combined with theInntal Tunnel, which forms part of the existingInnsbruck bypass, the Brenner Base Tunnel will reach a length of 64 kilometres (40 mi), making it the longest underground railway connection in the world.[1][2]

It will run from nearInnsbruck, inAustria, toFranzensfeste/Fortezza, inItaly, replacing part of the currentBrenner railway.[3] The line is part ofLine 1, the Berlin to Palermo route, ofTrans-European Transport Networks (TEN-T) and funded by Austria and Italy with large contributions by theEuropean Union. The tunnel is scheduled to be completed in 2032.[4][5]

TheBrenner Pass, in the Alps at the border between Austria and Italy, is one of the most important traffic connections between northern and southernEurope, and the motorway going over it is infamous for its frequent traffic jams.[6] Pollution from transit traffic is a major concern because of the combination oftemperature inversion with the narrow shape of the valleys leading to the pass.[7]

The goal is to relieve this situation by greatly improving the railway connection betweenGermany andItaly with the new tunnel, which will allow trains to cross the Alps much faster. Currently, speeds in the Brenner region barely exceed 70 km/h (43 mph) due to the steepness of the existing tracks, which cross the pass at an elevation of 1,371 metres (4,498 ft) above sea level.[8]

The travel time fromInnsbruck toBolzano will be reduced from current 2 hours to just 50 minutes.[9]

Background

[edit]

The passenger and freight traffic across the Alps has increased greatly in recent years and further growth is forecast.[10] Austria is a key country in movement of freight between northern and southern Europe and between eastern and western Europe. The Brenner region is very politically sensitive with respect to both local and cross-border transport issues. Between 1970 and 1999, highway freight increased seven-fold. (3 million to 22 million tonnes)In 1990, 70% of the freight from eastern Europe was transported by rail and the remainder by trucks. These proportions were expected to reverse by 2010.[11]: 182ff About three-quarters of traffic through the Brenner Pass is currently carried by road transport. Local residents have long fought for relief from the associated pollution. The construction of a rail tunnel is considered by its proponents to be necessary for a shift of freight traffic from road to rail.

The railway line fromInnsbruck inNorth Tyrol toBolzano inSouth Tyrol was built between 1860 and 1867. Tight curve radii and gradients of up to 2.6% complicate rail operations. However, improvements on the Italian side in recent years to the existing line, which were completed in late 2008, allow the line theoretically to accommodate 240 trains per day. The grades were not significantly improved.

The new Brenner line would have a maximum gradient of 0.4%-0.7%. Thus, a locomotive would be capable of hauling more than double the weight. The new line (thebase tunnel together with the southern approach fromWaidbruck/Ponte Gardena toFranzensfeste/Fortezza) would cut travel time between Innsbruck and Bolzano from about two hours today to less than half that.

Project

[edit]

Main tunnel

[edit]

The 55-kilometre (34 mi) long, twin-tube tunnel begins in the Innsbruck suburb of Wilten and penetrates theAlps reaching a height of about 840 metres (2,760 ft) above sea level (ASL). The tunnel will be up to 1,720 m (5,640 ft) below the surface at its deepest point in thegneiss section stretching south from the Italian border.[12] Since under the most recent plan the tunnel starts as a twin-tube tunnel, the junction already prepared in theInntal tunnel on theInnsbruck bypass will not be used. Instead, a diversion with several branches is planned.[citation needed]

The volume of rock to be excavated during the construction of the tunnel is estimated at 21 million cubic metres (740 million cubic feet), of which approximately 60% will be incurred in Austria, as about 60% of the tunnel will be in Austria. A part of the spoil will be used asfill for the approach lines and another part of the spoil material is used to produce the concrete segment for the final lining of the tunnel. The main tunnels will have a circular cross section with a diameter of approx. 8.1 m (27 ft).

According to current planning the apex of the tunnel will be at the border at an altitude of about 810 m (2,660 ft) ASL, although an apex farther south would have been lower. The placing of the apex at the border is set out in the treaty between Austria and Italy. As justification for this choice it is stated that this will allow Austrian water to run in the tunnel to Austria and Italian water to Italy.

Northern approach

[edit]

On its north end, the base tunnel (BBT) has two entrances, which must go underground a few kilometres before the junction with the main tunnels, and will also be built as part of the BBT. One route leads from the main Innsbruck station underBergisel and the other connects with the Innsbruck bypass. This route adds about 8 kilometres (5.0 mi) more to the length of the tunnel than the Innsbruck station route; with it included, the BBT, at 62.7 kilometres (39.0 mi), would become the longest continuous railroad tunnel in the world. However, if the Axentunnel extension is added to theGotthard Base Tunnel, its length would become 75 kilometres (47 mi), allowing it to reclaim the 'longest tunnel' title.

The northern approach from Munich within Germany is the 165 kilometres (103 mi)GrafingRosenheim–Kufstein route. The "Brenner Nordzulauf" (Brenner northern link) project aims to construct a high-speed line for speeds of up to 230 km/h (143 mph) betweenGrafing andBrannenburg in addition to the existing line, adapting the route's capacity to the projected increase as a result of the BBT. The project has reached in-depth planning stages but suffers from lacking support by locals.[13][full citation needed] A more direct route between Munich and Innsbruck, for example, viaGarmisch-Partenkirchen,Mittenwald andSeefeld was not pursued, though it could have shortened the Munich Innsbruck line to 129 kilometres (80 mi).

In Austria, anew double-track high-speed line supplements theLower Inn Valley railway betweenWörgl andBaumkirchen. It manages to cut travel time between Munich and Innsbruck from 1:50 via the old tracks to merely 0:55 using the high-speed line.[14] About 32 kilometres (20 mi) of the 40-kilometre (25 mi) line through theLower Inn Valley (Unterinntal) is built underground, in troughs, or under snow sheds. Noise and vibration mitigation is accomplished by the use of 80,000 square metres (860,000 sq ft) of elastomer in amass-spring system. The segment's track superstructure is load class E5. It is capable of handling 260–300 trains per day.[3] This section was opened on 9 December 2012.[15] Planning is under way on the continuation of this line to the German border at Brannenburg.

The southern approach for the BBT will be 189 kilometres (117 mi) long and reach from the southern portal of the tunnel in Franzensfeste/Fortezza toVerona. Planning has been completed for some sections.

  • Start of the TBM at Aicha construction site in April 2008
    Start of theTBM atAicha construction site in April 2008
  • View of the Eisack underpass construction site in September of 2019
    View of theEisack underpass construction site in September of 2019
  • TBM at the Ahrental–Pfons exploratory tunnel
    TBM at theAhrentalPfons exploratory tunnel
  • Excavation material processing plant and depot in Ahrental in July 2016
    Excavation material processing plant and depot in Ahrental in July 2016

History

[edit]

The Brenner tunnel is the most important link in theBerlin–Palermo railway axis, a series of projects that will create a single railway line fromBerlin inGermany toPalermo inSicily. In April 2003, the governments of Austria and Italy signed an agreement to build the tunnel.[16]

Schedule history

[edit]

Early in the preliminary planning, at a Brussels meeting in June 2005, BBT SE (Brenner Base Tunnel Societas Europae), presented an interim status report. Expectations following the meeting were that the project could be finalized and the pilot tunnel started by 2006. The target for the tunnel to start service was 2015.[17][18]

In 2007 a construction timeline with a 2022 finish date was specified in a memorandum signed by the Austrian and Italian ministers of transport.[19]

Funding history

[edit]

In December 2008Antonio Tajani, the European commissioner for transport, approved funds totalling €1.7 billion to finance 11 railway projects that together should establish two major routes across the continent.[20][21]

In May 2009 it was confirmed that final go-ahead for the project had been given.[22]

The final estimated cost was put at €8.384bn at 2018 levels.[19]

Construction history

[edit]

In the summer of 2007 work started on a pilot tunnel to run along the line of the future tunnel and to be used for removing water and spoil during the major construction phase. Construction of the pilot tunnel between 2006 and 2009 was estimated to cost €430 million and would be 50% EU funded.

On 6 July 2019, two Austrian segments were connected, and an unbroken 36 kilometres (22 mi) long tunnel was formed – around 65% of the tunnel's 55 kilometres (34 mi) projected length.[23] On 18 September 2025 for the first time the two tunnel sections, from Italy and from Austria, were joined underground by the break-through of the exploratory tunnel.[24][25] The exploratory tunnel runs 12m below where the final tunnel will be bored and it will be used for drainage and maintenance after the rail connection opens.[23]

As of March 2025, at least three workers died while working on the tunnel.[26][27]

Design

[edit]

The final design will consist of two tunnels, 55 kilometres (34 mi) long. A centre tunnel 12 metres (39 ft) below the two primary tunnels will be used during construction as a guide tunnel to determine geological conditions, and later for drainage and emergency access. There will be a cross over between the tunnels every 333 metres (1,093 ft). Multi-function stations will be located at Trens (inFreienfeld), St. Jodok, and a third station towards the northern end of the tunnel to provide operational and emergency services.ETCS Level 2 will be installed to provide train control.[22]

Funding

[edit]

As the transalpine stretch of the SCAN-MED Corridor, the Brenner Base Tunnel receives substantial funding from the European Union. Between 2015 and 2023, 50% of the costs for the exploratory tunnel (about 330 million Euro) and 40% of the costs for the two main tunnels (about 880 million Euro) were covered by the EU. Austria and Italy will each cover half of the remaining costs.

The 2017 estimate of the basic costs for the Brenner Base Tunnel was 7.8 billion Euro. Considering the planned end date for the project (2028), the estimate total costs, with risk provision and adjustment for inflation are about 8.384 billion Euro. They can be divided into 4 large categories: 60% of the cost comes from the engineering works, 15% is for outfitting, 10% is for planning, services and internal costs, 1% for parcels of land and related issues and 14% for risk provision.[28]

Specifications

[edit]
Cutaway view of the Brenner Base Tunnel

Source:[29]

  • Total tunnel length from the Innsbruck bypass to Fortezza/Franzensfeste: 64 km (39.768 mi)
  • Length from the Innsbruck portal to the Fortezza/Franzensfeste portal: 55 km (34.175 mi)
  • Diameter of each of the single-track tubes: 8.1 m (27 ft)
  • Distance between cross passage tunnels: 333 m (1,093 ft)
  • Elevation at highest point: 794 m (2,605 ft)
  • Maximumoverburden: 1,720 m (5,640 ft)[12]
  • Start of construction: 1999 (preparations), 2007 (exploratory section), 2011 (main tunnel)
  • End of construction: 2032
  • Total cost:8.384 billion
  • Electrification System:
  • Control and command system:ETCS Level 2
  • Operating speed: 250 km/h (155 mph) for passenger trains and 160 km/h (99 mph) for freight trains

See also

[edit]

References

[edit]
  1. ^"Did you know …".BBT-SE.com. Archived fromthe original on 2 February 2016. Retrieved2016-02-01.
  2. ^"BBT: Start of Works on the main Tunnel – tunnel".Archived from the original on 31 October 2020. Retrieved7 December 2019.
  3. ^ab"Case Study: Northern Approach Line to the Brenner Base Tunnel"(PDF). getzner. September 2010. p. 4. Retrieved2014-01-08.
  4. ^Fender, Keith (27 May 2021)."Governors protest latest delay to Brenner Base Tunnel construction".International Railway Journal. Retrieved23 August 2021.
  5. ^Brenner Base Tunnel DelayedModern Railways issue 874 July 2021 page 80
  6. ^Cokelaere, Hanne (August 5, 2019)."Trucking hell in Tyrol".Politico. Retrieved22 October 2020.
  7. ^de Franceschi, M.; Zardi, D. (March 2009). "Study of wintertime high pollution episodes during the Brenner-South ALPNAP measurement campaign".Meteorol Atmos Phys.103 (1–4):237–250.Bibcode:2009MAP...103..237D.doi:10.1007/s00703-008-0327-2.ISSN 1436-5065.S2CID 120275169.
  8. ^Bruzzo, Marco (18 August 2017)."Ferrovia del Brennero, 150 anni fa i primi treni".Tutto Treno Blog (in Italian).Archived from the original on 9 February 2018.
  9. ^Müller-Meiningen, Julius (2008-04-30)."Monumentales Superloch".Sueddeutsche Zeitung (in German). Archived fromthe original on 2008-05-23.
  10. ^Pompigna, Andrea; Mauro, Raffaele (June 2020)."Input/Output models for freight transport demand: a macro approach to traffic analysis for a freight corridor".Archives of Transport.54 (2):21–42.Bibcode:2020ArTr...54...21P.doi:10.5604/01.3001.0014.2729.ISSN 2300-8830.
  11. ^ff Contemporary Issues and Debates in EU Policy: The European Union and ..., p. PA182 ff, atGoogle BooksISBN 071906418X
  12. ^abReynolds, Patrick (February 2011)."Brenner project takes a major leap forward".Tunnel Talk.Archived from the original on 2013-08-20. Retrieved2013-08-14.
  13. ^"Aktuelles - Brenner-Nordzulauf".www.brennernordzulauf.eu.Archived from the original on 2019-04-10. Retrieved2019-04-10.
  14. ^"Die Neue Unterinntalbahn auf höchstem Niveau Kundl-Baumkirchen"(PDF).BEG (in German). October 2007. Archived fromthe original(PDF) on 2017-08-08. Retrieved2019-04-10.
  15. ^"Neue Unterinntalbahn: Highspeed und höchste Sicherheit"(PDF) (in German). ÖBB-holding AG. 2012-11-26. p. 3. Archived fromthe original(PDF) on 2013-09-30. Retrieved2014-01-08.
  16. ^Brenner Base Tunnel AgreementInternational Railway Journal May 2003 page 2
  17. ^"EC welcomes progress - Brenner Base tunnel project".Infrasite.nl. 24 June 2005.Archived from the original on 4 March 2016. Retrieved2013-08-16.
  18. ^"Commission welcomes progress of Brenner Base tunnel project" (Press release). European Commission. 23 June 2005. Retrieved2013-08-06.
  19. ^abvan Miert, Karel (2007-09-10)."Annual activity report by the coordinator Karel Van Miert - PRIORITY PROJECT 1 Berlin-Verona/Milan-Bologna-Naples-Messina-Palermo rail link"(PDF).Archived(PDF) from the original on 2008-02-28. Retrieved2007-12-09.
  20. ^"Brenner Tunnel: construction of the exploratory gallery begins" (Press release).European Commission. 2006-06-29.Archived from the original on 2009-08-31. Retrieved2006-12-13.
  21. ^"TEN-T rail funding signed".Railway Gazette International. 5 December 2008.Archived from the original on 12 February 2011. Retrieved2010-10-18.
  22. ^ab"Brenner base tunnel approved".Railway Gazette International. 11 May 2009.Archived from the original on 12 February 2011. Retrieved2010-10-18.
  23. ^ab"Contractors celebrate Brenner exploratory tunnel breakthrough". 10 July 2020.
  24. ^"Contractors celebrate Brenner exploratory tunnel breakthrough".Reuters. 18 September 2025. Retrieved12 October 2025.
  25. ^Rubenstone, Jeff (22 September 2025)."Major Breakthrough for Brenner Base Tunnel Through the Alps".Engineering News Record. Retrieved12 October 2025.
  26. ^"41-year-old killed while working for the Brenner Base Tunnel (German)". 22 May 2024.
  27. ^"Workers killed in Brenner-based accident tunnel construction site". Retrieved3 April 2025.
  28. ^"Funding".Brenner Base Tunnel. BBT SE. Retrieved17 August 2020.
  29. ^"Project Overview".Brenner Base Tunnel. BBT SE.Archived from the original on 22 September 2012. Retrieved19 February 2013.
  30. ^"Il Tunnel di Base del Brennero (BBT): progettazione e realizzazione del collegamento ferroviario - 8 settembre 2025".cifi.it (in Italian). CIFI - Collegio Ingegneri Ferroviari Italiani. Retrieved2025-10-14.

External links

[edit]
Wikimedia Commons has media related toBrenner Basistunnel.
Current departments (2008–)
Current subsidiaries (2008–)
Services
History
Related topics
International
Geographic

47°3′24″N11°29′59″E / 47.05667°N 11.49972°E /47.05667; 11.49972

Retrieved from "https://en.wikipedia.org/w/index.php?title=Brenner_Base_Tunnel&oldid=1323540409"