From Wikipedia, the free encyclopedia
Dutch railway line
This article needs to beupdated. Please help update this article to reflect recent events or newly available information.(April 2022)
Betuweroute
Route (red) of the Betuweroute
Overview
OwnerProRail
LocaleSouth Holland andGelderland,
Netherlands
Service
TypeFreight railway
History
Opened16 June 2007
Technical
Line length159 km (99 mi)
Track gauge1,435 mm (4 ft 8+12 in)standard gauge
Electrification25 kV 50 Hz
Kijfhoek yard: 1.5kV DC
Operating speed120 km/h (75 mph)
SignallingETCS Level 2
Kijfhoek yard:ETCS Level 1 andATB-EG
Route map

line fromMaasvlakte
line fromRotterdam Centraal
Kijfhoek
line toBreda
line toBreda
Sophia railway tunnel
A16/E19
Rietbaan
Noordriver
A15/E31
Railway tunnelGiessen
A27/E311
line fromDordrecht toElst
Merwede canal
Lingeriver
A2/E25
line fromBoxtel toUtrecht Centraal
Lingeriver
Lingeriver
havenspoorlijn Tiel
Amsterdam–Rhine canal
Lingeriver
Lingeriver
A50
Valburg yard
line fromNijmegen toArnhem
A325
Lingeriver
Spoortunnel Pannerdensch Kanaal
Spoortunnel Zevenaar
line fromZevenaar
demolished
line fromAmsterdam Centraal
Babberich
State borderGermany -Netherlands
DB 2266 toKleef
demolished
DB 2270 toOberhausen Hbf

TheBetuweroute is adouble trackfreight railway betweenRotterdam andGermany.Betuweroute is the official name, after theBetuwe area through which the route passes. The line is popularly calledBetuwelijn, after an older local rail line in the same region. The line extends into Germany as theOberhausen–Arnhem railway, and it is part of ProjectNo. 5 of theTrans-European Transport Network (TEN-T).[1]

History

[edit]
Map of the Betuweroute

In 1985 the Van Bonde Commission began to investigate the future of west–east transport. The main advocate of the proposed line was the then ministerNeelie Kroes, later Commissioner in the European Union until 2014. In 1992 the German and Dutch governments signed the Treaty of Warnemünde, which addressed enhancing rail traffic and focused on the tracks fromAmsterdam andRotterdam toDuisburg. The original plan was for three branch rail lines towards Germany. The northern branch viaOldenzaal was abandoned in 1999 and the southern branch viaVenlo was abandoned in 2004. Also in 2004, the courts[which?] forbade the construction of a largelogistics centre near the village ofValburg.

Construction of the Betuweroute inMeteren in 2004
ARailion class 189 hauled train using the Betuweroute nearDeil

In 1988 the Dutch state-owned passenger railway companyNS began work on the line. Delayed by two years, the railway was finished mid-2007. The final cost was 4.7 billioneuros, more than twice the original budget of 2.3 billion euros, and more than quadruple the initial estimate from 1990 of 1.1 billion euros.

The large and rising costs, and criticism about government funding, promoted the government to seek private financing for the line, without success. On 16 June 2007, QueenBeatrix of the Netherlands presided over the opening ceremony for the 160 kilometers (99 mi) line that connects Rotterdam to the German border.[2] Despite theTEN-T and bilateral agreements, Germany did not expect to complete reconstruction of their lines that connect with Betuweroute before 2015.[3]

Route

[edit]

The route is a direct line from theMaasvlakte toZevenaar, connecting thePort of Rotterdam to Germany.

Compared with the previous rail route betweenBarendrecht andElst the main deviations are:

Infrastructure

[edit]
A tunnel for the Betuweroute near highwayA15
A bridge nearTiel
Trajectory of the Betuweroute

The most striking infrastructure that was built or reconstructed as part of the Betuweroute includes:

  • Container terminals in Rotterdam, Rail Service CentreMaasvlakte, Rail Service CentreWaalhaven, and Maasvlakte 2.[4]
  • The 3 kilometers (1.9 mi) longBotlekspoortunnel under Rotterdam harbour replaces the antiquated Botlek bridge. The bridge remains in service as backup and for regional traffic. Space around the tunnel was so constrained that after completing the first tube, thetunnel boring machine had to be dismantled inside the tube. The parts were then returned to the starting point and reassembled to bore the second tube.
  • Theclassification yard Kijfhoek betweenBarendrecht andZwijndrecht was reconstructed.[5]
  • Barendrecht railway station has 9 tracks in a 1.5 kilometers (0.93 mi) long structure. Much of the structure is covered with a layer of earth, to reduce noise. On top is a new city park. At the station itself, 4 of the tracks and their platforms have a glass roof. Nearby tracks cross on two levels.
  • Tunnel were built underPannerdensch Kanaal nearAngeren. Instead of the projected bridge, a 2.7 kilometers (1.7 mi) tunnel was bored, to protect the landscape and environment. The tunnel entrances were designed to blend in with the landscape. The tunnel itself has large lockable doors at each end, to prevent a flood on one side of the canal inundating the region on the opposite bank. Because two endangered animal species were found in the vicinity of the tunnel, a new habitat was laid out for theGreat crested newt and theNatterjack Toad, as this video shows.[6]

Specifications and features

[edit]
  • The route is electrified at25 kV AC and signaled using theERTMS2 standard andAF Track Circuits. Electrification meets new European standards, but Dutch locomotives could not use the line's power because they run on a different voltage. The German extension of the route does not comply with the new ERTMS2 standards, and also uses another voltage, thus limiting usability of the track. Custom-made locomotives were needed. The first new-spec locomotive was delivered toRailion in December 2007.
  • Tunnels, viaducts and other parts of the railway are engineered to be 4.0 m wide and 6.15 m high in order to allowdouble stacked container trains under overhead wires,[7] although no such trains will be in use on this route for years to come. The overhead wires were installed at standard height, to accommodate locomotives with standardpantographs. This and viaducts on the connecting lines prevent use of double-stacked containers.[citation needed] In the future, the overhead electrification wires could be raised to allow for double stacking without much effort or cost.[citation needed]
  • For the section fromRotterdam to the largeKijfhoek classification yard, existing track was reconstructed. New construction occurred from Kijfhoek toZevenaar near the German border, which is most of the remaining three quarters of the line.
  • The total length of noise insulation panels on both sides of the track is 160 kilometers (99 mi), the same as the route length.
  • Roll bars along the track keep derailed cars from toppling.
  • 5 tunnels and several roofed sections add up to a length of 20 kilometers (12 mi).
  • There are 190 passages to allow wildlife to cross.
  • There are no level crossings, but instead 130 bridges and viaducts.[8]
  • Once the German line signaling and other infrastructure are updated, the Betuweroute's capacity will be 10 trains per hour in each direction.

Use

[edit]

When the line opened, project managers hoped within five years to reach a daily average of 150 freight trains.[9] In the first six months of operation, the unfinished German connection and problems with safety equipment caused traffic to be light.[10] Usage increased steeply over the years 2008–2011. By mid-2011, 78% of all freight trains between Rotterdam and the German border took the Betuweroute. The other freight trains travelled via eitherVenlo or the border atBad Bentheim, or used the conventional railway through Arnhem toEmmerich am Rhein[11] Beginning in 2009, the heaviest trains in Germany and the Netherlands, 6,000 tonne trains, transported iron ore between the port of Rotterdam andDillingen in Germany using the Betuweroute. As of 2019, the Betuweroute carried 4.2 billionton-kilometers of cargo and 2.3 milliontrain kilometers.[12]

Unlike other Dutch rail network tariffs, the tariff charged to train operators to use the Betuwe rail line is not calculated by train weight but by the distance the train travels. Between 2008 and 2011 the tariff has increased progressively from €1.41 per train kilometer to €2.33 per train kilometer.[13]

Quarterly number of trains over the Betuweroute.
QNo. of trains
2008-I
1,000
2008-II
1,200
2008-III
1,250
2008-IV
1,900
2009-I
2,350
2009-II
2,200
2009-III
2,300
2009-IV
3,000
2010-I
3,900
2010-II
4,300
2010-III
4,400
2010-IV
5,000
2011-I
5,850
2011-II
6,300

[14]

Controversy

[edit]

Many Dutch people, experts and politicians such as members of parliament opposed construction of the Betuweroute. The DutchMinistry of Transport, Public Works and Water Management received 14,000 complaints against the northern branch alone, which was cancelled in 1999.GroenFront![15] (Green Front), one among dozens of activist groups, was responsible for 35 confrontations in 1999–2001.[16] University professors and official institutions heavily criticised the role of the government and ministers in relation to Betuweroute.

The main concerns about the Betuweroute were:

  • Cost - Even at the original budget of 2.3 billion euros, there was much discussion about economic viability. Initial hopes of attracting private investors turned out to be totally unfounded. In 2000 theCourt of Audit convicted the government of having issued unrealistic forecasts about cost, environmental effects and usage of the Betuweroute, as well as insufficient cost control. They stated that promoting river transport should have been considered as a realistic alternative. In 2004 theCentraal Planbureau (Bureau for Economic Policy Analysis), concluded that construction of the line would never pay for itself.[citation needed]
  • Landscape - The line passes through theGroene Hart (Green Heart) of theRandstad and theBetuwe. There were concerns the rail line would damage both regions. The Groene Hart is a more or less rural area amid theNetherlands' largest cities. The Betuwe is a less densely populated green region along the major Dutch rivers. Both feature classic Dutchpolder landscapes. Opposition to the original plans forced the construction of additional tunnels, which further increased the construction budget.
  • Environmental issues - Many environmentalists and neighbours fiercely resisted the new line due to concerns about noise, dangerous chemical spills and the fragmentation of animalhabitats. In response, extra noise insulation panels, tunnels and wildlife passages were built.
  • Alternatives - As the Court of Audit concluded in its 2000 report, river transport was and still is a realistic alternative. River transport is cheaper, more flexible,[how?] safer and not much slower.[citation needed] The Dutchbarge fleet is the largest and among the most modern in Europe,[17] capable of transporting freight to the German industrial heartland with minimal government investment.[citation needed] Major Dutch rivers includingMerwede,Waal and parts of theRhine,Maas (Meuse),IJssel andLek run roughly alongside the Betuweroute. Likewise, theA15, an excellent albeit congested highway, parallels the railway for 95 kilometers (59 mi).

Several parts of thisControversy section are based on a Dutch scientific investigation.[18]

Municipalities along Betuweroute

[edit]

See also

[edit]

References

[edit]

Several parts of this article are based on:"Decision process and construction of Betuweroute, 1985-2007" (in German). Archived fromthe original on 2008-05-17.

  1. ^"Betuweroute and the TEN network"(PDF). Retrieved2011-11-13.
  2. ^"First freight train on the Betuweroute". Dutchnews.nl. 2007-06-18. Retrieved2011-11-13.
  3. ^"Germany ignores Betuwelijn". Dutchnews.nl. 2007-09-05. Retrieved2011-11-13.
  4. ^"Expansion of Rail Infrastructure and Transfer Capacity". Archived fromthe original on 2011-07-15. Retrieved2010-10-31.
  5. ^Website Rail cargo information."Document showing layout Kijfhoek"(PDF) (in Dutch). Retrieved2009-06-05.[permanent dead link]
  6. ^"Short video about new habitat for the Great crested newt, Dutch spoken". Betuweroute.nl. Retrieved2011-11-13.
  7. ^"Betuweroute Double-Track Freight Line - Railway Technology".
  8. ^Features of BetuwerouteArchived December 15, 2007, at theWayback MachineDutch
  9. ^"FAQ Keyrail". Keyrail.nl. Archived fromthe original on 2009-04-12. Retrieved2011-11-13.
  10. ^"Marginal use of Betuweroute". Dutchnews.nl. 2007-08-01. Retrieved2011-11-13.
  11. ^Halfjaarbericht Keyrail, August 2011.
  12. ^Ontwikkeling spoorgoederenverkeer in Nederland 2019 vergeleken met 2018 prorail.nl
  13. ^Betuweroute: Start mit Schwierigkeiten. In:Schweizer Eisenbahn-Revue. Nr. 8/9, 2007,ISSN 1022-7113, S. 382.
  14. ^Halfjaarbericht Keyrail, August 2010,Jaardienstverdeling Keyrail, May 2011.
  15. ^"Vrienden van GroenFront! | EarthFirst! Netherlands Support Group". Groenfront.nl. Archived fromthe original on 2004-08-31. Retrieved2011-11-13.
  16. ^35 actions by Groen Front against the Betuweroute, 1999-2001Archived 2007-06-29 at theWayback MachineDutch
  17. ^River transportation: Market observation 2006Archived October 22, 2007, at theWayback Machine Dutchbarge fleet accounts for more than 50% of total tonnage inRhine andMeusebasins, (p42). And is the most modern, second only to the German fleet, (p55).(in Dutch)
  18. ^Rail transport vs. river transport. Scientific investigation on costs, safety, environment.Archived 2005-12-17 at theWayback MachineDutch

External links

[edit]
Wikimedia Commons has media related toRotterdam-Zevenaar railway.
Corridors
Infrastructures
International
Geographic

Retrieved from "https://en.wikipedia.org/w/index.php?title=Betuweroute&oldid=1291928466"
Categories:
Hidden categories:

[8]ページ先頭

©2009-2026 Movatter.jp